Near Southeast DC Past News Items: West Half St.
See JDLand's West Half St. Project Page
for Photos, History, and Details
In the Pipeline
25 M
Yards/Parcel I
Chiller Site Condos
Yards/Parcel A
1333 M St.
More Capper Apts.
Yards/DC Water site
New Marine Barracks
Nat'l Community Church
Factory 202/Yards
SC1100
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)
 
Go to Full Blog Archive


21 Blog Posts Since 2003
Go to Page: 1 | 2 | 3

The JDLand commentariat (and those who stop by to keep up on Tidbits) knew all of this a few weeks ago, but JBG Smith has now officially announced the start of leasing at West Half, its 465-unit building just across the street from Nats Park. The official web site has floor plans and prices, which show a range from a 365-sf studio starting at $1,770 up to a 1,250-sf three bedroom going for upwards of $6,400. There's also of course information about the building and its amenities, and a hint about...
THE 1205 COLLECTION: What we have been calling "West Half" is now apparently two separate residential "buildings," with the portion closest to the ballpark now dubbed "The 1205 Collection." It will have its own lobby entrance, and has larger units, with terraces, higher-end appliances, and additional amenities. The 1205 will open later this fall.

Also officially announced (and also already posted a few weeks back on the Ticker) are two more food outlets: DC's third outlet of HipCityVeg, and Basebowl, a ramen, dumplings, and Asian barbecue restaurant from the restaurateur behind Reren in Chinatown.
With all of this news, I wandered down to Half and N to check things out, and found that the two residential lobbies are furnished (but the windows were too dusty to take pictures), and vegetation is being planted up on the balconies. But, more importantly, there is now signage marking all of the leased spaces, so you can start sketching out your plan of attack. So I had to make a dumb map.
Starting in the corner space directly across from the Center Field Gate, there's the two-floor space for both the American bistro Gatsby and its sibling the all-day Mah Ze Dahr bakery. Heading up Half, you'll next encounter Basebowl, then then sizeable Atlas Brew Works space, followed by HipCityVeg, and Cold Stone Creamery. Then--surprise!--Compass Coffee and Union Kitchen Grocery run along the building's northern side, along a pedestrian-only "Via" between Half and Van. The two lobbies are on Van Street. As of now, there's no retail announced for the two-story corner space in the building's southwestern corner, at Van and N.
Half Street is gonna feel a little different next season. (And this is just one side of the street, as we await announcements from the Kelvin apartments and Envy condos to see what the offerings will be on the east side of Half, other than Punch Bowl Social.)
Here's a few photos of the signage and whatnot. Just because.
 

Losing track of which project is which? Time for another photo tour....
First, let us welcome the two new skeletons now above ground level, the Maren on Potomac Avenue and Paradigm's project at 1000 1st St., SE, both of which are apartment projects:
(Tishman Speyer's massive Square 696 residential project is just now starting to peek up, but didn't make the above-ground cut this time.)
It's a sign that the frantic construction pace of the past two years that we only have three projects coming out of the ground, and only one where excavation is stlll underway (One Hill South 2). A breather will be nice.
That said, there are still nine other projects that are in the getting-their-faces-on stage of construction. So let's look at the National Association of Broadcasters HQ (and its sibling Avidian condos to the rear) at South Capitol and M, the Funnel on Half Street (aka West Half), the combo project of the Estate apartments at 3rd and Water by the Yards Park and a Thompson hotel at 3rd and Tingey (shown in closeup because I dig the windows), the second phase of Novel South Capitol, Parc Riverside Phase 2 at Half and L, and the Garrett at 2nd and K. The last photo in the bunch is 1250 Half, which is both a still-rising skeleton on its southern end and a face-being-put-on project on its northern end, completely mucking with my flow.
(Follow the links to the project pages for details--I've already written enough words this week!)
Still under construction as well are residential projects the Harlow and the Bower condos/Guild apartments, but I didn't take any updated photos because their exterior work is mostly done. Plus I might have collapsed.
Tired out by this? Now you know why I for the first time grabbed a scooter to cover all of the territory.
But I also used my newfound scooter freedom to get some sorely needed shots at the far edges of the JDLand coverage area. Here are my first photos of the work on the new Douglass Bridge, as seen from the old Douglass Bridge (and no, that platform is not the new bridge), as well as a picture of the Emblem on Barracks Row condo building at 8th and Virginia, now completed despite my having almost completely ignored it during its construction:
Speaking of the new Douglass Bridge, if you go to the official web site and scroll down to Project Gallery, you will see what I think is a new animation of the new bridges and ovals and whatnot.
As for what's on the boards to get underway in 2019, I'd say that the most likely contenders are the new DDOT HQ at 250 M and Lerner's 1000 South Capitol Street residential building, and maybe one other I will write about soon. As for others? We Shall See.
I also belatedly have added the GSA warehouse at 49 L to my Demolished Buildings Gallery, as #181. That's a lot of demo.
 

It would be terribly hokey for me to say something along the lines of, "It's almost Halloween, and the neighborhood is appropriately decked out with skeletons." So, I won't. But there is a whole lot of construction going on, counting not only nearly finished buildings, but also buildings getting their faces put on or heading toward topping out or now "going vertical" below ground level.
I'll go in order from newest to oldest, starting with peering down into holes that you might not be looking into yourselves.
Three residential projects that began excavating in the spring are already starting to climb upward, as you can see in the above photos from 1000 1st Street and the Maren at Florida Rock. Tishman Speyer's mystery residential project that covers all of what's known as Square 696 is a hybrid, with some excavation still underway while the eastern half is now starting to rise. (and no, we still don't have renderings.) Then there's phase two of One Hill South (Two Hill South? One Hill South Two? Return of One Hill South? One Hill South, Electric Boogaloo?), where digging is being hampered by complaints of fumes emanating from the site's past life as a gas station.
Next we turn to the neighborhood's EIGHT projects that are above ground but not yet topped out. (I could call it six, since there are two projects with two buildings going up concurrently, but let's call an eight an eight.)
Let's start with residential projects The Garrett at 2nd and I, Parc Riverside Phase II at Half and L, and the second phase of Novel South Capitol at 4 I, which was kind of a shocker to see go up since it was never really announced that the entire project would be under construction at once:
I'll note that the photo of the Garrett is a bit of a triumph, because it's the first one I've gotten from the northeast, now that the wrapping up of tunnel construction has given me some sidewalk access to the intersection at 2nd and H. (Which hopefully will be open completely by Oct. 18, the Whole Foods Day of All Days.)
Next, let's wander down to the Ballpark District, where the National Association of Broadcasters headquarters is a whisker away from topping out and its sibling the Avidian condo building is now well visble. One block away, 1250 Half is in its final minutes of not being completely above ground, as the portion closer to N Street is now right even with the street, while its northern portion has been skeletoning for quite some time. And at 3rd and Tingey, the combo project of the Thompson hotel and the Estate apartment building are beginning to change the feel of the western side of the Yards Park.
{Pant, pant.}
Now, a quick look at the buildings getting their faces on, since this is the stage when everyone is pretty much tapping their toes and waiting for the projects to be finished already. (There's a section of Virginia Avenue that qualifies for that, too.) May I present West Half at Half and N, the Harlow mixed-income building at 3rd and L, the Bower/Guild condo/rental buildings, and the new DC Water headquarters.
To wrap it up, there's one additional ghostly building to keep an eye on, though I don't wish to be flippant about it. Ward 6 councilmember Charles Allen is holding a hearing on Oct. 25 about the fire and response, for those interested.
And that's "it." Ha. Ha. I imagine the next major update will be in December, when I will spend most of the time complaining about how the low sun angle and a decade's worth of construction has made it impossible to take photos unruined by shadows. I may have to (gasp!) go out on cloudy days until spring.
 

Washington Business Journal has the scoop on some big news for the block just north of Nats Park, which is that the team behind DC restaurants Succotash and Mi Vida are planning to open The Commons, a 300-seat, 9,000-square-foot, two-story restaurant "that will look into the stadium from its second floor" at JBG Smith's under-construction West Half residential building.
And, not only will it have lunch and dinner menus with "a sort of contemporary, upscale diner feel," but it is apparently intending to have a bakery and breakfast operation, Mah-Ze-Dahr at The Commons, from the owners of the New York bakery.
The article says that The Commons is aiming for a late 2019 or early 2020 opening.
This is the first retail offering announced for West Half, which will have over 65,000 square feet of retail on two floors.
Comments (37)
More posts: Restaurants/Nightlife, West Half St.
 

In the past few posts I've shown you the neighborhood's newest skeletons/skeletons to be, I've shown you buildings that are topped out but still getting exterior work done, and holes in the ground, and I know you are long since bored of this stretch of posts, but I will still do one more, looking at two projects that between them are managing to fall into all categories at once.
Plus, they are probably the two most watched projects in the neighborhood at the moment.
These are two views of JBG Smith's West Half 420-unit residential development, which, if I can count floors correctly, is still not yet topped out, but which, as seen in the second photo, is already hanging glass on the lower floors, presumably to protect the spaces from the roving gangs of All-Star hooligans that will descend next month. I think both photos do a good job of showing the very unique structure of this building, as it appears from the north to be funneling down into the ballpark. It also looks like the corner of the building facing the ballpark is prepped to have some signage hung. Digital? Temporary? Permanent? We Shall See! This building is expected to have about 65,000 square feet of retail on its first two floors.
And, across the way, we have:
The east side of the street will be home to 1250 Half Street, a residential project that is both a nearly topped-out skeleton (on the north end of the site) and a still-not-yet-out-of-the-ground hole to peer into (on the south end of the site). It is actually all one building, it's just that the foundation was built on the north end back when Monument Realty had plans to develop the rest of the block as it was building the 55 M office building, before, well, you know, Things Happened. So this allowed Jair Lynch Development Partners to plow ahead with above-ground work there while prepping the rest of the former Monument Valley hole to go vertical. This building will have as many as 440 rental units and over 60,000 square feet of retail (including anchor tenant Punch Bowl Social) when it's finished, though I should note that it is going to be completed in two phases, with construction of the phase two "boutique residential building" facing N Street coming later.
And here's what both will look like to people exiting the ballpark when they are finished.
Which is a little different from:
With that, I am done running down all of the latest construction statuses (statusi?). If you are worn out, don't blame me, blame the SEVENTEEN separate construction projects underway (19 if you include the Virginia Avenue Tunnel and the new South Capitol Street bridge).
Comments (12)
More posts: 1250 Half St., Development News, photos, West Half St.
 

Yes, it's time for another edition of JD Looks Behind Fences and Into Holes So You Don't Have To, and we start the rundown with two new spots to add to the lineup, where dirt has just begun to be moved: 71 Potomac, the 264-unit sibling to Dock 79 at Florida Rock, and "Square 696," Tishman Speyer's still-not-publicly-unveiled residential and retail project on the block bounded by I, K, 1st, and Half Streets. Plus I'll add an up-to-date shot of the excavation at Paradigm's 1000 1st Street project, just because it doesn't fit anywhere else in this post:
(Note that I'm giving Tishman a few more weeks before I craft my own rendering. And thanks to the 71 Potomac folks for the pretty wood fences with holes in them that are perfect for snooping bloggers to look through!)
Next, let's talk about the "hybrid" hole in the ground at 1250 Half Street, aka the old Monument Valley site just across N Street from Nats Park. This is where two cranes mark the slow beginnings of vertical construction at the bottom of the hole, while six-plus floors of construction are already complete at the north end of the project, since that part of the hole was dug and the foundation was completed back in 2007 when Monument thought it would be building out the entire block instead of just the 55 M office building. This is where a two-phase project with up to 440 units of residential and more than 60,000 square feet of retail will be built:
(I need this project to hurry up and get to ground level because it's impossible to get a shot of the bottom of the hole without going up to a nearby roof.)
Now we'll move to the corner of South Capitol and M, where the National Association of Broadcasters HQ is graduating from hole-in-the-ground to skeleton, while its sibling, the condo building Avidian, is still not quite yet visible above the fence line. I forgot to walk down to get a photo through the fence of the Avidian footprint, so instead I'll just include this very bad shot I took a few weeks ago of the first hints of construction on the new Douglass Bridge, because it needs to be documented.
Three more projects are on their way upwards, including the Garrett at 2nd and I and the co-projects Parcel L residential/Thompson Hotel hole at 3rd and Tingey in the Yards shown here. (I forgot to get a shot of the Parc Riverside II hole. Probably looks like a hole with concrete and rebar, like the others):
So, in case you're not counting, that's nine projects either still below ground or just at ground level (or 10 if you include the permanently below-ground Virginia Avenue Tunnel, or 11 if you include the currently below-water Douglass Bridge work).
Then you can add those to the eight other projects that are above-ground, topped out, or nearing completion, and you can understand why it's okay to feel like the neighborhood is still a perpetual construction site, and will be for a while yet. Here's shots of seven of them, in order of progress: the 99 M office building, the DC Water headquarters, the Bower condos and sibling Parcel O rental building, and additional residential projects 2 I Street, Square 769N, and West Half (alas, I haven't made it over recently to check out the status of the Emblem condo project at 8th and Virginia, so I'm one short):
No wonder I'm so tired.
 

I somewhat unexpectedly found myself wandering around on Sunday, and though the official JDLand camera stayed home and drank hot chocolate, the JDLand cellphone (a Pixel 2, thanks for asking) stepped in to catch some progress pics.Here's a rundown:
* HELLO, AVIDIAN: After being burned multiple times over the years with projects being said to include condos during the design phase only to end up as rentals, it's nice to have confirmation via the purty new fence signage at South Capitol and M that not only that the corner will be home to the new headquarters for the National Association of Broadcasters, but that the sibling building immediately to the south that was oddly dubbed 10 Van is now known as the Avidian, and that it will be condominiums, "Selling 2018." The building should have 170ish units and will probably be completed in 2019.
* PEEKING OUT: We have three newcomers to ground level, as the 380-unit apartment building at South Capitol and I is now clearly visible from the street, as is the 190-unit rental sibling to the further-along Bower at Yards Parcel O on 4th Street. Plus, the 420-unit West Half building immediately north of Nats Park now has its first batches of rebar out of the ground, if your eyes know what to look for. (And yes, I'm still completely failing at catching the work underway on what's now known as the Emblem at Barracks Row, the 20-unit condo building at 8th and Virginia. One of these days.)
* ONWARD AND UPWARD: The new DC Water HQ continues to get its face put on, while the condo building known as the Bower at 4th and Tingey has completed seven of its 10ish floors, and at 2nd and L the next Capper mixed-income building is through Floor #4 of its own 10ish floors. {Trying to avoid any arguments about whether penthouses = floors.}
* DOWN ON THE CORNER: There's officially another project underway, as digging is now proceeding at 2nd and I for The Garrett, the third and final portion of WC Smith's "Collective" development that also includes the Park Chelsea and Agora (and this, of course). Meanwhile, there are still holes at the second phase of the Parc Riverside at Half and L (below), and at Monument Valley, which is impossible to get a shot of from street level so you'll just have to imagine it. And I forgot to look behind the fence at Parcel L.
There will probably be some new holes in the ground in coming months, as both the rumor mill and the permitting pipeline hint that at least three more projects will get underway: Dock 79's residential sibling at the old Florida Rock site, the large residential development on the old "Congressional Square" site at 1st and K, and Paradigm's 275ish-unit residential building on the old Market Deli site at 1st and L. (Though I'll note that each of these still do not have permit applications in the system yet beyond the initial shoring/sheeting/excavation step.) The number of still-empty lots keeps a'shrinking....
 

Time for my quarterly {ahem} update on all of the construction projects you are picking your way past when you walk/drive/bike around the Hood:
I'll start with the new openings and the coming soons, with both Due South Dockside and Morini Piccolo now operating (softly) on the Yards Park boardwalk, and Cava in the Homewood Suites at Half and M in Any Second Now territory:
As for buildings getting their faces on, I present Skanska's 99 M office building and the new DC Water headquarters:
There's also now two new arrivals above ground, as PN Hoffman's condo project The Bower has at last made its debut at 4th and Tingey, as has the DC Housing Authority's as-yet unnamed mixed-income rental building at 2nd and L, both of which are shot from the south instead of the intersection because it's now the time of year when anything shot to the south-southeast, south or south-southwest will look terrible, no matter what time of day:
Next on the assembly line, two more residential projects projects are likely to be making their above-ground debuts before the end of the year: JBG's West Half project directly north of Nats Park, and the McDonalds-slaying 2 I Street project:
Other holes in the ground I won't highlight this time around include the Bower's sibling rental project at 4th and Water, Toll Brother's Parc Riverside Phase II at Half and L, the Jair Lynch residential project at the Half Street Hole, and the combo project at South Capitol and M for the new National Association of Broadcasters headquarters and its next-door residential project labeled 10 Van.
Also, WC Smith has cleared the lot at 2nd and I to make way for the beginning of work on the Garrett, the third and final apartment building that makes up "The Collective" on that block. Plus, fences are up along 3rd Street for the next project in the Yards lineup, the 270-unit apartment building currently known as "Parcel L2." (Great, I have to update my Highlighted Projects map again.)
Just to make sure all ends of the construction spectrum are represented, one hole is even starting to get covered over, and that's in the 200 and 300 blocks of Virginia Avenue, where the Virginia Avenue Tunnel work is far enough along that you can actually start to imagine a street appearing again in those blocks in the coming months:
Finally, I'll close with a shot of a tearing down rather than a building up, and that's the pile of debris formerly known as 37 L Street SE--just in time to mark the 40th anniversary of the Cinema Follies fire, on Oct. 24, 1977.
So, while the neighborhood is taking a back seat these days to all of the excitement surrounding the opening of the Wharf down the road, there is still a fair amount happening. (And hopefully the neighborhood blogger will someday get back in the groove. Still riding the rollercoaster of my new not-yet-ready-to-call-it-normal.)
 

The siren song of a stunningly clear and breezy Saturday in August was of course irresistible to me, and I walked more than nine miles over four hours to grab a whole lot of pictures from a whole lot of locations. Here's some highlights. Click to enlarge, as always.
It turns out having a public roof space at a central location in the neighborhood is going to be veeeeery handy for me, as it allowed me to grab a great shot of the DC Water Headquarters construction that shows exactly how the new steel is wrapping around the existing O Street Pumping Station. It also allowed me to check on the progress of the excavations at 1250 Half, West Half, and the One M/10 Van combo project in a single shot.
Then there's the Any Minute Now retail offerings, with the Juice Laundry telling Instagram followers that they really are coming soon (really!), and representatives of the new Taylor Gourmet on 1st Street telling nearby office tenants that they expect to open on Aug. 23. We shall see!
Meanwhile, exterior work seems to be starting to wrap up at the 1221 Van residential building just north of the ballpark (and note all that retail space on the first two floors), while the 99 M office building is celebrating its topping out later this month. And while the neighborhood waits with baited breath to see exactly when the Whole Foods build-out will begin at Agora, there are now nice new sidewalks on the stretch of H Street SE that is in the process of materializing.
Finally, there are holes in the ground that now show evidence of the start of vertical construction, so these might be my final downward peeks into the two residential projects at the Yards Parcel O on 4th Street, the large residential project at 2 I Street, and the mixed-income Capper Hope VI apartment building at 3rd and L.
And, finally, while I have no intention of adding the new DC United soccer stadium to my lineup, I was surprised to see how visible it is from just within the JDLand boundaries at South Capitol and Potomac. So, here.
But this is just a very small sample. If you want to see a whole lot more of the shots I took, here's 333 of them. Or follow any of the above links, or click on the projects on the map at the upper right of any JDLand page to see the latest for those projects under construction.
 

Enough tidbits in the hopper to actually go less than a week between posts. Yay!
* 816 POTOMAC: Developers of the empty lot on the northwest corner of 9th and Potomac, SE have gotten an initial green light from the Historic Preservation Review Board for a four-story residential building with below-grade parking. This project will also incorporate an existing historic building at 819 L (sort of visible here), which will remain separate from the new building. Here is a video showing what the project would look like, and a screengrab from it of the proposed building is at right. No word on timing, and this does not include the existing old apartment building next door at 812 Potomac.
* 99 M TENANT: The under-construction office building at the corner of 1st and M has signed its first tenant, with Pyxera Global taking 17,000 square feet on the fourth floor. As I mentioned a few posts ago, Skanska said recently that some tenant announcements would be in the offing, and this would appear to be one of them. (Bisnow)
* POP-UP BBQ: If you've noticed the picnic tables on the northwest corner of 1st and N, where the F1rst sales trailer was, it's the home of a Rocklands Barbeque and Grilling Company pop-up offering on Nats game days, from now through the end of the season (and post-season). Service off of the "full food truck menu." including beer and wine, will start 90 minutes before gametime, through the first 30 minutes after first patch.
* MORE PROGRESS: On my way to and from the ballpark this weekend, I took a few smudgy cellphone photos of progress, showing the new DC Water HQ, District Winery, and (water-filled) holes in the ground at Parc Riverside II and West Half (forgot to go across the street to Lynch Half), and evidence of previously tidbitted items about the warehouse at 49 L Street and the A1 Garage site. Maybe I'll get out with the real camera this weekend for a full update, weather and energies permitting.
One that I didn't take was the view southward from M Street between 1st and New Jersey--I have to admit I was not expecting the DC Water HQ to be so visible from the north.
 
21 Posts: