Since January, 2003
            
 Page Through from Before to After

It was more than six years ago that word first seeped out that Forest City Washington was looking to bring a large movie theater to the Yards, on land owned by DC Water that the development company would acquire.
But those negotiations have still not completely been resolved, and, in a time-extension request filed last week with the Zoning Commission, Forest City described the current situation, which will displease long-frustrated neighborhood moviegoers:
"Because of the extensive delays tied to the important and expansive discussions regarding DC Water's relocation and operational needs, as well as DC Water's need to retain control of the F-1 Parcel to facilitation construction of its headquarters building, Forest City's rights with respect to the lease with the theater operator have expired. Despite efforts to reconstitute that deal, it is clear that Forest City will not be able to proceed with the original approved program for a two-level, 16-screen theater above a four-level parking garage."
The filing goes on to say that the company is "now pursuing additional refinements to the approved plans." While the building's size and scale will likely stay the same, it is possible that the theater will be "reduced in size" and/or "incorporating other appropriate and compatible uses for the site to ensure a viable project." There is also apparently a need to relocate the building's planned loading and service access onto N Place and away from DC Water's ongoing operations. The facade design will likely change as well.
The filing states that the "very complicated planning constraints on this unique site" have "nearly reached final resolution," but that Forest City now requests an additional two years to work on redesigning the plan.
(Of course, this means that the replacement of "When will Whole Foods open?" with "When will the movie theater open?" as the most-asked question at JDLand will continue on for a while.)
Comments (2)
   
 
 More About The Yards at DC Water

JDLand.com Home

Comments

CJBabyDaddy says: (1/9/19 5:12 PM)
As a traditionalist, I, for one, will never stop asking, “When will Whole Foods open?”


jdc says: (1/10/19 9:14 AM)
With all of the apartments coming online over the next two years, I think a further delay is probably fine - you really need a lot of residential to support a 16 screen theater and I have always wondered what the catchment area is for this site...Still, I am hopeful a movie theater is the ultimate tenant because as a nearby office worker it would make seeing afternoon films very easy on half-days.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

202_cyclist on Super Tuesday Tidbits: 2-story retail is such a waste for the 1299 First Street lot.
CJBabyDaddy on Super Tuesday Tidbits: @JES: With all the stress and anxiety we’re enduring, you had to go rub salt in...
202_cyclist on Super Tuesday Tidbits: Gary— yes, they play that and He revelry every morning at the Navy Yard. Someti...
JES on Super Tuesday Tidbits: @NWtoSE I just saw "Coming 2019 Showplace ICON theatre" on the map in ...
NWtoSE on Super Tuesday Tidbits: https://www.mgaco.com/spaces/lease-sale/1299-1st-st-se
NWtoSE on Super Tuesday Tidbits: @JScott280- I don't think they have a tenant, but the developer plans to build a...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1200 B/O 1ST ST SE   THEFT
Theft First Degree (all Other Larceny)
 04/07/20
1200 B/O HALF ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 03/28/20
1200 B/O HALF ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 03/23/20
1500 B/O SOUTH CAPITOL ST SE   THEFT
Shoplifting
 03/11/20
200 B/O I ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 03/09/20

Recent Issued Building Permits Archive  
1300 4TH ST SE 1001   
03/16/20 
LA FAMOSA LLC / null
P2004796 / SUPPLEMENTAL
   
03/20/20 
LA FAMOSA LLC / null
E2005975 / SUPPLEMENTAL
1300 4TH ST SE 1006   
03/16/20 
LA FAMOSA LLC / null
M2001859 / SUPPLEMENTAL
1300 4TH ST SE   
03/13/20 
LA FAMOSA LLC / KIMOY LALLEMENT; POTOMAC CONSTRUCTION SERVICES
TL2000028 / CONSTRUCTION
New tenant layout for commercial kitchen, two restrooms, point of sale bar, and dining seating, new lighting and mechanical zones. 2,338 sf INDOOR OCCUPANCY: 84 PERSONS WITH 59 SEATS OUTDOOR OCCUPANCY: 38 PERSONS WITH 38 SEATS TOTAL MAX OCCUPANCY: 122
900 5TH ST SE   
03/24/20 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / KAYLA TRICE; DELAWARE
EN2001608 / SHOP DRAWING
Install 3 new hydraulic passenger elevators
200 I ST SE   
03/17/20 
DISTRICT OF COLUMBIA / LEIA TERRELL
B2006382 / CONSTRUCTION
Tenant Alterations of existing office doors and wall. Including relocation of existing electrical, and mechanical terminals. NO CHANGE OF EGRESS, USE OF OCCUPANCY, NO EXTERIOR LAND DISTURBANCE, NO BASE BUILDING STRUCTURAL WORK.
   
04/01/20 
DISTRICT OF COLUMBIA / null
E2006294 / SUPPLEMENTAL
300 M ST SE   
04/02/20 
FEDERAL CENTER LP / CENTER; EDGE CONSTRUCTION
B2004640 / CONSTRUCTION
INTERIOR RENOVATION TO 4TH FLOOR OFFICE SPACE. PARTITIONS, FURNITURE, MECHANICAL, ELECTRICAL, LIFE SAFETY AND STRUCTURAL HANGING PARTITION. 3500 SQUARE FEET. AMENTUM
139 N ST SE   
03/16/20 
PARCEL I FC ROWAN / MIGUEL RIOS; GRIFFIN DEWATERING, LLC
SB2000152 / CONSTRUCTION
Type of proposed System: Deep well dewatering system consisting of 16 wells around the perimeter of the shored excavation and 2 wells within the excavation in a mutually agreed layout. • Installation Method: Wells will be drilled up to 70’ deep, utilizing Griffin’s hollow stem auger drilling rig to drill up to a 10.25” I.D. borehole. Deep wells come complete with screen, casing, riser pipe and a s...
1299 NEW JERSEY AVE SE   
03/13/20 
FOREST CITY SEFC LLC / SARAH J. NAPIER
BCIV2000067 / CONSTRUCTION
Revisions to BCIV1800153. This submission is for approval stamps only. No change in work.
71 POTOMAC AVE SE   
03/27/20 
MRP RESIDENTIAL / KAYLA SHATTUCK; KAYLA SHATTUCK; PARADIGM CONTRACTORS LLC
BCIV2000036 / CONSTRUCTION
This permit is for site civil work at 71 Potomac Avenue SE including stormwater management and erosion & sediment control. See plans for more details.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.