The blistering pace of new projects slowed a bit this year, allowing me some (needed) breathing space in terms of keeping up with construction progress. But I wandered around on Saturday, and here's a few things of note I saw:
* The JBG apartment project now known as 1221 Van is speeding along, and has changed the skyline along South Capitol considerably. Taking southward-facing photos in the winter months is always dicey, but I couldn't pass up a shot of the new structure and its neighbor directly to the south.
* Insignia on M's logo at the top of its New Jersey Avenue face does easily catch one's eye.
* The preparation work to transform the O Street Pumping Station into the glimmery new DC Water Headquarters is now underway.
* CSX announced this week that the new second-track Virginia Avenue Tunnel is "nearing completion," and it certainly looks that way at the western mouth of both new and old tunnels. And I got to see a train coming out, too! (But the project isn't over--next work will shift to reconstructing the 100-year-old original tunnel.)
* The excavation for the combination condo-and-rental buildings project known as "Parcel O" at the Yards has proceeded apace.
* Conversely, the hole for the 99 M office building has remained basically unchanged since late summer. (Compare the below photo to this one taken in August.) There was a new crane-related after-hours permit approved for the site last week, so maybe things are about to start moving again. UPDATE, 12/13: A representative for the 99 M project has gotten in touch with me to say that there has actually been considerable "complex" work going on at the site, it's just that it's mostly underground/out of sight.
Comments (10)
   
 
 More About Development News

JDLand.com Home

Comments

dude says: (12/12/16 9:29 PM)
I like the look of Insomnia...


jdc says: (12/13/16 8:38 AM)
The pace of 99 M has definitely surprised me, compared to the speed of the hotel and projects also on 1st. Is it because of the massive hole that needed to be dug and shored up?


JD says: (12/13/16 9:20 AM)
As I mentioned in the post, it's not a slow pace--it's been stopped altogether since August. Given that it is right next to the Metro station, and that there are huge steel thingamabobs holding up the western and southern walls, there must be some issues with the shoring that they have been having to come up with a solution for.


202_cyclist says: (12/13/16 11:17 AM)
Perhaps because 1221 Van is out on its own along So. Capitol Street, it appears to be pretty big when viewed from a distance.

Also, I noticed that Dock 79 has a dog park. Is this only for residents of that building? Since we don't have a dog, I haven't paid attention to any previous discussion of that.


JD says: (12/13/16 12:11 PM)
UPDATE, 12/13: A representative for the 99 M project has gotten in touch with me to say that there has actually been considerable "complex" work going on at the site, it's just that it's mostly underground/out of sight.


conngs0 says: (12/13/16 12:47 PM)
Perhaps the "complex" work taking place underground that 99 M is referring to SafeTrack?


202_cyclist says: (12/13/16 12:53 PM)
@JD: Maybe 99M is building the secret tunnels....


Section314 says: (12/13/16 1:22 PM)
Now that the trailers are gone and McDonald's is closing, do you have any sense of when construction will start on these projects or on "Monument Valley"?


JD says: (12/13/16 1:28 PM)
There are excavation and/or foundation permits in process for the empty part of the Fairgrounds, and Monument Valley, and the NAB HQ/10 Van joint project, and the McD's project, and the Capper apt bldg at 2nd and L, and the second phase of the Parc Riverside. Those are all the ones I expect to get started in coming months, though of course something can always derail plans. But those are the ones that really seem to be planning to roll once they get their permits.


CJBabyDaddy says: (12/20/16 1:36 AM)
4th & Tingey: Billboard for The Bower is up, promoting sales to begin Spring 2017.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2018!
 Recent Posts

202_cyclist on Weekly Open Thread: Also, that photo in the WBJ article explains what the helicopters are doing flyi...
202_cyclist on Weekly Open Thread: JD-- regarding the link that you Tweeted about, more housing is always welcome b...
JES on Weekly Open Thread: Looks like Circa is still coming, but Open Road is no more. From reading this, i...
UpEarly on Weekly Open Thread: The CSX land behind ORE 82 is under contract to Greystar (national apartment dev...
JD on Weekly Open Thread: Greystar is under contract to buy the huge CSX parcel that runs west from New Je...
JD on Weekly Open Thread: In case you see it elsewhere like it's new, the news of Bluestone Lane coming to...
  
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 05/22/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 05/21/18
300 B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 05/19/18
400 B/O M ST SE   THEFT
Shoplifting
 05/16/18
100 B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 05/16/18
400 B/O M ST SE   THEFT
Shoplifting
 05/15/18
900 B/O NEW JERSEY AVE SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 05/12/18
UNIT B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 05/11/18
100 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 05/10/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 05/10/18
1200 B/O VAN ST SE   THEFT
Theft First Degree (all Other Larceny)
 05/10/18
100 B/O M ST SE   THEFT
Theft First Degree (all Other Larceny)
 05/09/18
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 05/09/18
UNIT B/O M ST SE   BURGLARY
Burglary Two
 05/09/18
1000 B/O HALF ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 05/08/18
UNIT B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 05/08/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 05/08/18
700 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 05/06/18
800 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 05/06/18
400 B/O M ST SE   THEFT
Shoplifting
 05/06/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 04/30/18
900 B/O 5TH ST SE   HOMICIDE
Murder II
 04/30/18
100 B/O L ST SE   ROBBERY  04/30/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 04/27/18
1100 B/O NEW JERSEY AVE SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 04/26/18
1200 B/O SOUTH CAPITOL ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 04/26/18
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 04/25/18

Recent Issued Building Permits Archive  
1331 2ND ST SE 20003   
05/01/18 
DC WATER / DAVE LEVINE
AH1800901 / CONSTRUCTION
AFTER HOURS WORK FOR STRUCTURE EXCAVATION AND SUPPORT FOR B1311474 DC WATER. CORMAN CONSTRUCTION 301-34-5417.
907 4TH ST SE   
05/01/18 
RYAN WILLING / null
E1806431 / SUPPLEMENTAL
   
04/30/18 
RYAN M WILLING / KYLE YOST
SOL1800442 / CONSTRUCTION
4.2kw rooftop solar pv system, less than 4' above roof
101 H ST SE   
05/14/18 
SQUARE 737 LLC / DFM DEVELOPMENT SERVICES, LLC
B1808785 / CONSTRUCTION
Revision to Permit TL1800054 to revise the Whole Foods Market permit address from 800 New Jersey SE to 101 H Street SE.
100 H ST SE   
05/14/18 
DISTRICT OF COLUMBIA / null
E1806787 / SUPPLEMENTAL
101 H ST SE   
05/22/18 
SQUARE 737 LLC / null
M1802469 / SUPPLEMENTAL
   
05/23/18 
SQUARE 737 LLC / null
P1806213 / SUPPLEMENTAL
2 I ST SE   
05/22/18 
CRESCENT CAPITOL VIEW / null
E1807051 / SUPPLEMENTAL
   
05/08/18 
CRESENT CAPITOL VIEW MF LLC / COMPOSITION SYSTEMS INC
AH1800928 / CONSTRUCTION
AFTER HOURS PERMIT TO WORK SUNDAY 5 / 13 / 18 FROM 7 AM UNTIL 7 PM UNDER OCCUPANCY PERMIT PA10636830 TO INSTALL A SIGN BAND.
   
05/23/18 
CRESCENT CAPITAL VIEW, LLC / ERICKA CLARK
TC1800034 / CONSTRUCTION
Renewal of tower crane permit #TC1700022 EXTENSION WILL EXPIRE ON 11 / 23 / 2018
10 I ST SE   
05/02/18 
CAPITOL HILL RACQUET CLUB / JOHN WYCKOFF
SB1800290 / CONSTRUCTION
Install 4 soil borings to less than 50 feet using dual tube geoprobe DPT tooling. Collect soil samples and install 1-inch diameter sch 40 PVC temp monitoring wells in 2 of 4 borings. Wells and borings will be abandoned with 24 hours of sampling using a bentonite grout mixture with bentonite / water ratio of 2 to 1. All IDW will be contained in drums.
150 I ST SE   
05/17/18 
SQUARE 737 LLC / JAMES WOLF
P1806078 / SUPPLEMENTAL
421 L ST SE   
05/16/18 
DORAN BUTUCHE / DORAN BUTUCHE
F1800255 / CONSTRUCTION
To install a fence and gate to the front yard. The construction, placement, style and color will be similar to fencing already in place at adjoining homes. Entire fence is in public space.
202 M ST SE   
05/18/18 
NURI EROL / PAT SNYDER
B1804587 / CONSTRUCTION
EXISTING PIZZA RESTAURANT - NEW OWNER, NEW EQUIPMENT + NEW GELATO & COFFEE SERVICE. MINOR HVAC, PLUMBING & ELECTRIC
800 NEW JERSEY AVE SE 1ST FL   
05/14/18 
SQUARE 737 LLC / JOHN SONNER 4438727277
E1806780 / SUPPLEMENTAL
800 NEW JERSEY AVE SE   
05/09/18 
WHOLE FOODS MARKET / MELISSA DIAZ
TL1800054 / CONSTRUCTION
THE PROJECT IS A TENANT FIT-OUT OF AN EXISTING SPACE IN A MIXED USE PROJECT BEING DEVELOPED UNDER A SEPARATE PERMIT. THE PROJECT IS A WHOLE FOODS MARKET OCCUPYING THE GROUND FLOOR AND A MEZZANINE WITHIN THE BUILDING. - TPR
   
05/11/18 
SQUARE 737 LLC / null
P1805955 / SUPPLEMENTAL
   
05/24/18 
SQUARE 737 LLC / null
P1806243 / SUPPLEMENTAL
861 NEW JERSEY AVE SE   
05/11/18 
CONSOLIDATED RAIL CORPORATION / RPS INC
SB1800309 / CONSTRUCTION
Per " Work Plan, Geotechnical Investigation, dated May 2, 2018 (see attached), the work involves drilling 6 soil borings using a hollow stem auger rig and a mud rotary drill rig for the purpose of collecting soil samples for geotechnical subsurface exploration. Boring depths range from 75 to 150 ft.
   
05/23/18 
CONSOLIDATED RAIL CORPORATION / NA CSX TRANSPORTATION INC.
AH1800974 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities. **TO EXCLUDE LEGAL HOLIDAYS**
1100 NEW JERSEY AVE SE 2ND FL   
05/10/18 
SQUARE 742 LLC / null
P1805902 / SUPPLEMENTAL
1115 NEW JERSEY AVE SE   
05/22/18 
DONOHOE REAL ESTATE SERVICES / null
M1802478 / SUPPLEMENTAL
71 POTOMAC AVE SE   
05/11/18 
MRP REALTY / ELIZABETH DE SMET
SB1800270 / CONSTRUCTION
Installation of 124 wellpoints to assist in the construction of mixed use structure at Potomac Avenue.
   
05/18/18 
FORIDA ROCK PROPERTIES INC / ANKIT K SINGH
UT1800039 / CONSTRUCTION
Removal of an Underground Storage Tank (UST) 7 feet in diameter and approximately 9 feet long (approximately 2000 gallons). Suspected Fuel Tank. Tank is filled with 8 inches of unknown content. Tank will be removed and disposed off as per the appropriate standards and requirements.
221 TINGEY ST SE   
04/30/18 
GONE YARD HOTEL OWNER, LLC / DFM DEVELOPMENT SERVICES, LLC
B1808252 / CONSTRUCTION
Yards Parcel L-1 : Permit Revision for B1801074 to update owner information to Gone Yard Hotel Owner, LLC and permit address to new address: 221 Tingey Street SE.
300 TINGEY ST SE   
05/09/18 
FC BOILERMAKER LLC / FAY A KENNEDY
E1806640 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.