Half at L, Looking Northwest (see more)

While these dates are always subject to change, CSX announced on Friday that it expects to reopen 4th Street just south of the freeway by Wednesday, Nov. 23, as it completes the demolition of the Phase 1 temporary bridge deck over the new tunnel that is being built, and construction of the new Phase 2 deck over the existing tunnel that will now be rebuilt and expanded.
Once the 4th Street intersection opens, the next big closure will be prepped, with the expectation that 3rd Street SE will close at Virginia Avenue for up to eight weeks, beginning perhaps on Monday, Nov. 28, to do the same demolition of the Phase 1 deck and construction of the Phase 2 deck.
Note that, unlike when the Phase 1 deck was built over 3rd Street earlier this year in a way that allowed northbound traffic to continue to flow, this is a full closure. (Though pedestrian access will remain in place, as will access to the Capitol Quarter driveway entrance on 3rd.)
This does not affect access to I-695 from the 3rd Street ramp.
If you want to see recent photos of the new tunnel and all the related construction, the Coffee with Chuck slides from Nov. 16 have a pile of them. (The slides also note that this is month #18 of the expected 42 months of total construction.)
Comments (10)
   
 
 More About CSX/Virginia Ave. Tunnel

JDLand.com Home

Comments

202_cyclist says: (11/21/16 11:04 AM)
It's outside of the neighborhood but the NYT has a good profile of Capitol Hill, along with some nice photos: link .


G Street says: (11/21/16 12:01 PM)
I don't want to jinx it, of course, but (so far) this tunnel project has gone = pretty smoothly


conngs0 says: (11/21/16 12:45 PM)
I think it's been pretty much as-advertised, which is a good thing. There's no arguing that closing 3rd Street is going to be a significant inconvenience, but hopefully traffic flows reasonably well through the alternative routes and the closure doesn't last any longer than the planned 6-8 weeks. It's like your standard broken bone!


Ampersand says: (11/21/16 12:52 PM)
If 3rd was going to need to be closed for this long, I can't think of a better time to do it than now. Few or no major events in the neighborhood, and much less regular traffic due to the holidays. I do hope that the northbound light at 6th and Virginia is retimed, though; the left-turn lanes already get pretty backed up without all the diverted traffic. I don't go through at rush hour much, but it's very frustrating to sit in a 12-car line with a red light while VA is empty of westbound cars. I almost think it might function better as a four-way stop...


JD says: (11/21/16 12:57 PM)
I agree with @Ampersand on this being optimal timing to close 3rd. Longtime area residents such as myself know how much this town empties out between Thanksgiving and Christmas, and with a change in administration and the party in the White House, I expect that to be even more pronounced this year.

(I bet they will be pressed by TPTB to be sure to have 3rd reopened by the inauguration, though.)

I also hope there will be a retiming of the 3rd Street light. Coming southbound on 3rd right now there's at most time for three cars (more often two, if the first driver isn't quick on the gas) to get through before it turns back to red, and at that point only drivers who know that northbound 3rd still has a green and a left arrow know that they can turn right-on-red to get to the freeway ramp if there's no oncoming traffic.


202_cyclist says: (11/21/16 12:59 PM)
In other news, the Capitol Hill Corner blog has a post on the new community center.

Capitol Quarter Community Center – Key to Mixed Income Community – a Ship without a Captain
link


Ampersand says: (11/21/16 4:39 PM)
@JD oh gosh, I hate 3rd & VA southbound. In addition to the stupidly short cycle, the worst part in my opinion is that the southbound green only triggers if you trip a sensor. On a bike, it's impossible to trigger, and in a car if you miss it you'll sit there indefinitely with cycle after cycle of permanent red light. I once was driving home at 1am or so and it Just Would Not Trigger. I waited at a completely empty intersection for 5+ minutes (6 cycles) before giving up and running the red light. After that I gave up and started diverting to 4th; I use the pass-through on a bike, and in a car I turn right onto VA and left onto 3rd.

I would love to see the northbound left turn arrow moved to the beginning of the cycle, then after a ~10 second lead a switch to two-way greens. Also for the crosswalk to get a countdown timer, as I see a lot of pedestrians who give up hope and jaywalk.


dude says: (11/21/16 10:23 PM)
Yeah, closing 3rd will suck for me. Ah well, 8 weeks isn't too long.


dude says: (12/7/16 10:35 PM)
In case people haven't seen, they've closed this now. 8 week countdown in process.


conngs0 says: (12/8/16 1:10 PM)
Two days in a row I've forgotten that 3rd is closed and tried to head north under the freeway that way! That morning autopilot takes awhile to change course I suppose.... I agree with dude that eight weeks can't come soon enough!

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Top News

202_cyclist on Capitol Riverfront BID: JD-- congratulations on the award. This morning I noticed that glass is being i...
Joni on Capitol Riverfront BID: Congratulations on your well deserved award! I think I've told you before that y...
sameter on Capitol Riverfront BID: congrats on being a constant in the community and being a positive change. well...
CJBabyDaddy on Capitol Riverfront BID: A meet-up after tomorrow’s 15th anniversary gala sounds like a great idea. (Can...
Message Board (beta)

  
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
300 B/O K ST SE   BURGLARY
Burglary Two
 01/13/18
1000 B/O 4TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 01/11/18
500 B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 01/09/18
900 B/O 4TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 01/07/18
100 B/O I ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 01/04/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 01/04/18
400 B/O M ST SE   THEFT
Shoplifting
 01/02/18
UNIT B/O K ST SE   THEFT
Theft 2nd Degree (theft From Building)
 12/31/17
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/19/17

Recent Issued Building Permits Archive  
1331 2ND ST SE   
12/22/17 
DC WATER / DAVE LEVINE
AH1800369 / CONSTRUCTION
After Hours work for structure excavation and support for B1311474 DC Water, Corman Construction 301-343-5417. TO EXCLUDE LEGAL HOLIDAYS.
1331 4TH ST SE CU   
12/27/17 
FC 1331 LLC / GARY BRENT; N/A
SG1800119 / CONSTRUCTION
Install 1 illuminated blade sign and 7 non-illuminated window vinyl signs - CHLOE BY HAIDAR KAROUM
   
12/28/17 
FC 1331 LLC / BEN BEDDO
TL1700205 / CONSTRUCTION
New Tenant Layout for restaurant
1300 4TH ST SE   
01/05/18 
FORREST CITY WASHINGTON / GEORGE ARTHUR KING
SB1800091 / CONSTRUCTION
To abandon 18 6 inch diameter 80 foot deep dewatering wells and 4 2 inch diameter 50 feet deep observation wells per the DOEE regulations
1346 4TH ST SE   
01/12/18 
ALAN OWINGS / ROBERT HENRY
AH1800415 / CONSTRUCTION
After Hours Permit for 1 / 15 / 18 from 7AM to 7PM to perform concrete operations, framing, operations, and utility operations.
411 I ST SE   
12/27/17 
ABIGAIL A SMITH / ROBERT D. JOHNSTON
E1802679 / SUPPLEMENTAL
337 L ST SE   
12/22/17 
JENNIFER LANCASTER / null
E1802602 / SUPPLEMENTAL
   
01/11/18 
JENNIFER LANCASTER / BJORN FALK
SOL1800005 / CONSTRUCTION
Installation of a 3.6kW solar PV system. Roof Mounted, 10 panels
300 M ST SE STE# 400   
01/03/18 
FEDERAL CENTER LP / SAM HOLLEN
B1803531 / CONSTRUCTION
INTERIOR RENOVATION TO 4TH FLOOR OFFICE CONFERENCE ROOM. PARTITIONS, CEILING, MECHANICAL, ELECTRICAL AND LIFE SAFETY. NO PLUMBING OR STRUCTURAL. 680 SQUARE FEET. CACI SUITE 400
25 POTOMAC AVE SE DOCK 79   
01/11/18 
RIVERFRONT HOLDINGS I LLC / null
P1802701 / SUPPLEMENTAL
227 TINGEY ST SE   
12/29/17 
JW CAPITAL PARTNERS / MELISSA DIAZ
FD1700126 / CONSTRUCTION
Parcel L1- Foundation to Grade permit for the new construction on an 11 story full service hotel building with restaurant and retail.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.