More than two years after four teams were shortlisted for the opportunity to compete for the project, DDOT announced today that it has issued the final Request for Proposals (RFP) for the first phase of the South Capitol Street Corridor reconstruction, which includes a new Douglass Bridge and approach work, plus a new interchange at I-295 and the Suitland Parkway.
The release today says that design/build proposals from the four teams are due this fall, and that DDOT expects to begin construction in the spring of 2017, and complete this first phase in 2020, but, well, We Shall See.
I absolutely cannot bear to write about this in any detail AGAIN, so if you haven't been keeping up with the plans to replace the existing 67-year-old bridge, please check out my post from August 2015, when it was announced that the project got its federal approval/record of decision, or my post from late 2014 about the supplemental EIS that presented some tweaks to the plan that had been stalled after a preferred alternative was identified back in 2011.
But if clicking on one of those links is more than you yourself can bear, I will just plagiarize the summary I wrote in August:
As you can see in the pilfered-from-DDOT graphic above, the new bridge will run immediately parallel and downriver of the existing bridge, with two new large traffic ovals on its approaches. There will also be a much-needed reconstruction of the I-295/Suitland Parkway interchange.
The bridge will have three travel lanes in each direction, along with 18-feet-wide pedestrian/bike paths on both the up-river and down-river edges of the bridge, which will be configured as one 8-foot-wide lane for pedestrians and a 10-foot-wide bidirectional bike path.
The eventual second phase of this overall "South Capitol Street Corridor Project" will be streetscape improvements to the north end of the street, similar to the spiffening that the blocks from N to Potomac received back in 2007 that give the street more of an "urban boulevard" feel. This will include a full redesign of the M Street intersection and a reconfiguration of South Capitol's interchange with I-395.
My South Capitol Street and South Capitol Street Bridge project pages are also good places to go for details.
Comments (9)
   
 
 More About Douglass Bridge

JDLand.com Home

Comments

MJM says: (3/30/16 3:39 PM)
No lights at the circle, ped tunnels under the road to the circle and removal of the gas station on Anacostia would be nice but sadly won't happen. But they really need to get this new bridge up, current bridge is crumbling (just walk it its in sad shape - not preaching to JD).


conngs0 says: (3/30/16 3:46 PM)
This will be a very important design with respect to integrating the east side of South Capitol Street where Nats Park is and the west side where the DC United Stadium will be. Moreover, I think it will be great to have two pedestrian and bike friendly ways to traverse the Anacostia River once this bridge and the 11th Street SE bridge park are completed.


jdc says: (3/30/16 4:59 PM)
I wish segments 4 and 5 came sooner, though I can see the benefit of waiting to do serious streetscape improvements until a lot of the heavy construction, and resulting wear and tear, is done.


dbt says: (3/31/16 1:59 PM)
One thing I still don't get about Phase 2 is how they expect to turn New Jersey Ave into a nice, wide urban boulevard, especially with ORE 82 jutting out almost to the curb in the current street alignment.


conngs0 says: (3/31/16 2:14 PM)
Agreed. That building single-handedly ruins any chance of turning New Jersey Avenue into a "boulevard". With all of the construction in the neighborhood taking place, New Jersey Avenue will certainly be long overdue for some improvements in terms of paving, etc., but there's really no point in other expenditures with that eyesore occupying the west side of the road.


JD says: (3/31/16 3:06 PM)
Yeah, the New Jersey Avenue thing is some lip service at this point.


crafter11 says: (4/1/16 10:49 AM)
Can you post a link to the RFP? Thanks!


JD says: (4/1/16 10:55 AM)
I haven't found the RFP online, perhaps because it's just going to the four teams shortlisted. (It'll probably show up eventually, somewhere.)


MarkinDC says: (4/1/16 11:43 AM)
I'm happy to see that I'm not the only one who looks at ORE 82 in disgust.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

malatesta on Whole Foods: You guys, Whole Foods is good now.
JES on Whole Foods: Oh yeah, and uhh... given the absolute mess that the NJ & I intersection was...
walt on Whole Foods: Shrinking the movie theater from 16 to 7 screens would be ideal! 16 Screens is ...
JES on Whole Foods: Just went for lunch. Chef Kwame is there all day serving up Philly Wing Fry orde...
JES on Whole Foods: Holy crap, that dry aged beef locker..... *drool*
JD on Whole Foods: There are indeed premade sandwiches. And everything else. It's quite something. ...
  
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
400 B/O M ST SE   THEFT
Shoplifting
 10/17/18
100 B/O N ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/17/18
700 B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 10/10/18
50 M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 10/08/18
1100 B/O 10TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/07/18
100 B/O M ST SE   ROBBERY  10/05/18
700 B/O L ST SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 10/04/18
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (theft From Building)
 09/28/18
1100 B/O 1ST ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/27/18
100 B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 09/26/18
100 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/26/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/26/18
1100 B/O 5TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/24/18
150 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/22/18
700 B/O L ST SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 09/22/18

Recent Issued Building Permits Archive  
1100 2ND PL SE   
10/12/18 
null / DONNA G GRAHAM
AH1900071 / CONSTRUCTION
WR #3585809 - M.ALLEN / A.PRICE - 1100 2ND PLACE SE - PEPCO CREWS WILL BE SPLICING CABLES AT NIGHT STARTING 10 / 15 / 18 UNTIL 11 / 2 / 18 FROM 10:00 PM TIL 7:00AM MONDAY THROUGH SUNDAYS
1346 4TH ST SE   
09/28/18 
ALAN OWINGS / ROBERT HENRY
AH1801345 / CONSTRUCTION
After Hours Permit for 10 / 08 / 2018 to perform construction work with the below activities: Interior Operations: 7AM - 7PM - ADVANCED NOTICE TO RESIDENTS, OPERATION CONTACT PERSON ON SITE TO ADDRESS ANY UNEXPECTED NOISE ISSUES BEFORE 9:00AM WITH CONTACT NAME AND TELEPHONE. Exterior Operations: 9AM-7PM - NO EXTERIOR ACTIVITY, TRAFFIC, NOISE GENERATION BEFORE 9am WITH ON SITE OBSERVANCE. ...
   
10/09/18 
FC 1346, LLC / null
E1900300 / SUPPLEMENTAL
2 I ST SE   
09/25/18 
MCDONALDS CORPORATION / TAMIKA STATON; OTIS
EN1802612 / SHOP DRAWING
Install 1 New G2S Elevator - 4000LBS @ 350FPM
   
09/25/18 
MCDONALDS CORPORATION / TAMIKA STATON; OTIS
EN1802611 / SHOP DRAWING
Install 3 new G2S Elevators - 3500LBS @ 350FPM
   
09/26/18 
MCDONALDS CORPORATION / null
E1811060 / SUPPLEMENTAL
   
10/09/18 
CRESECENT CAPTIAL VIEW / null
P1900223 / SUPPLEMENTAL
   
10/17/18 
MCDONALDS CORPORATION / DONNA G GRAHAM
AH1900080 / CONSTRUCTION
WR #3573836 - M.ALLEN / BRUNO - WARD 6 - 20003 - PEPCO CREWS WILL BE WORKING #2 I ST SE - MAY NEED TO BLOCK "I" STREET ON OCCASION TO INSTALL NETWORK TRANSFORMERS AND INSTALL AND SPLICE CABLES - CREW WILL BE WORKING AT NIGHTS DURING THE WEEK (MONDAY-FRIDAYS) FROM 9PM TIL 7AM - PEPCO CREWS WILL ALSO BE WORKING SATURDAY AND SUNDAYS FROM 6AM TIL 6PM - WORK IS ONGOING
4 I ST SE   
10/09/18 
CRESCENT COMMUNITIES / null
P1900221 / SUPPLEMENTAL
328 K ST SE   
09/27/18 
MARK BARRETT / null
E1811075 / SUPPLEMENTAL
   
10/04/18 
MARK BARRETT / BJORN FALK
SOL1800999 / CONSTRUCTION
Installation of a 5.559kW solar PV system. Roof mounted, 17 panels with integrated microinverters.
401 L ST SE   
10/11/18 
MICHAEL R BRICKMAN / FLOYD H. FURR
P1900299 / SUPPLEMENTAL
   
10/11/18 
MICHAEL R BRICKMAN / DARIUS LYVERS 703-491-1234
M1900108 / SUPPLEMENTAL
300 M ST SE 1ST 20024   
09/21/18 
ELLEN OPDYKE / null
P1809360 / SUPPLEMENTAL
300 M ST SE 3   
09/21/18 
FEDERAL CENTER LP / null
P1809359 / SUPPLEMENTAL
300 M ST SE 8 20024   
09/24/18 
BARBARA D HAMLETT / null
P1809404 / SUPPLEMENTAL
300 M ST SE   
09/25/18 
FEDERAL CENTER LP / null
E1811000 / SUPPLEMENTAL
   
09/25/18 
FEDERAL CENTER LP / null
E1811001 / SUPPLEMENTAL
   
09/25/18 
FEDERAL CENTER LP / null
E1810999 / SUPPLEMENTAL
1111 NEW JERSEY AVE SE   
09/21/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
P1809362 / SUPPLEMENTAL
   
10/17/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
E1900581 / SUPPLEMENTAL
79 POTOMAC AVE SE 1ST FL   
10/03/18 
RIVERFRONT HOLDINGS I LLC / null
P1900101 / SUPPLEMENTAL
71 POTOMAC AVE SE   
09/28/18 
FORIDA ROCK PROPERTIES INC / BARR CONCRETE
AH1801325 / CONSTRUCTION
After hours to pour concrete with pump truck 9 / 28 / 2018 to 10 / 28 / 22018 from 11pm to 7am
   
10/04/18 
FORIDA ROCK PROPERTIES INC / BARR CONCRETE
AH1900029 / CONSTRUCTION
Afterhours to pour concrete with pump truck saturday 10 / 06 / 2018 from 12am to 7am
79 POTOMAC AVE SE   
10/04/18 
RIVERFRONT HOLDINGS I LLC / null
M1900054 / SUPPLEMENTAL
201 TINGEY ST SE   
10/09/18 
JBG/SEFC 170 LLC / DONNA G GRAHAM
AH1900051 / CONSTRUCTION
WR #3566756 - M.ALLEN / BRUNO - 201 TINGEY ST SE - PEPCO CREWS WILL BE INSTALLING NETWORK TRANSFORMERS AND INSTALLING CABLES - PEPCO WILL HAVE TO SHUT DOWN 3RD ST BETWEEN WATER ST & TINGEY ST SE TO SET TRANSFORMERS ONLY - WORK WILL BEGIN 10 / 12 / 18 THROUGH 11 / 30 / 18 - MONDAY THRU FRIDAYS FROM 10PM TIL 8AM AND SATURDAYS AND SUNDAYS FROM 6AM TIL 6PM
227 TINGEY ST SE   
10/09/18 
FOREST CITY WASHINGTON / DFM DEVELOPMENT SERVICES, LLC
AH1900056 / CONSTRUCTION
Yards Parcel L-2. Afterhours permit for follow-up test run of the precast concrete façade panel installation. Work to take place 7pm on 10 / 10 to 7am on 10 / 11.
   
10/15/18 
GONE YARD HOTEL OWNER LLC / MICHAEL ERIC CAMPBELL 703-631-2711
FB1900011 / SUPPLEMENTAL
NO. TO BE INSTALLED (2) GROSS RATING: 999999 BTU / HR NATURAL GAS STEAM PRESSURE 160 PSI OUTPUT: 960,000 BTU / HR
   
10/15/18 
GONE YARD HOTEL OWNER LLC / MICHAEL ERIC CAMPBELL
UP1900012 / SUPPLEMENTAL
   
10/17/18 
UNITED STATES OF AMERICA / DFM DEVELOPMENT SERVICES, LLC
AH1900079 / CONSTRUCTION
Yards Parcel L-2. Afterhours permit for the purpose of installing precast concrete façade panels. Work to take place 7PM to 7AM, 10 / 22 through 11 / 3.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.