More than two years after four teams were shortlisted for the opportunity to compete for the project, DDOT announced today that it has issued the final Request for Proposals (RFP) for the first phase of the South Capitol Street Corridor reconstruction, which includes a new Douglass Bridge and approach work, plus a new interchange at I-295 and the Suitland Parkway.
The release today says that design/build proposals from the four teams are due this fall, and that DDOT expects to begin construction in the spring of 2017, and complete this first phase in 2020, but, well, We Shall See.
I absolutely cannot bear to write about this in any detail AGAIN, so if you haven't been keeping up with the plans to replace the existing 67-year-old bridge, please check out my post from August 2015, when it was announced that the project got its federal approval/record of decision, or my post from late 2014 about the supplemental EIS that presented some tweaks to the plan that had been stalled after a preferred alternative was identified back in 2011.
But if clicking on one of those links is more than you yourself can bear, I will just plagiarize the summary I wrote in August:
As you can see in the pilfered-from-DDOT graphic above, the new bridge will run immediately parallel and downriver of the existing bridge, with two new large traffic ovals on its approaches. There will also be a much-needed reconstruction of the I-295/Suitland Parkway interchange.
The bridge will have three travel lanes in each direction, along with 18-feet-wide pedestrian/bike paths on both the up-river and down-river edges of the bridge, which will be configured as one 8-foot-wide lane for pedestrians and a 10-foot-wide bidirectional bike path.
The eventual second phase of this overall "South Capitol Street Corridor Project" will be streetscape improvements to the north end of the street, similar to the spiffening that the blocks from N to Potomac received back in 2007 that give the street more of an "urban boulevard" feel. This will include a full redesign of the M Street intersection and a reconfiguration of South Capitol's interchange with I-395.
My South Capitol Street and South Capitol Street Bridge project pages are also good places to go for details.
Comments (9)
   
 
 More About Douglass Bridge

JDLand.com Home

Comments

MJM says: (3/30/16 3:39 PM)
No lights at the circle, ped tunnels under the road to the circle and removal of the gas station on Anacostia would be nice but sadly won't happen. But they really need to get this new bridge up, current bridge is crumbling (just walk it its in sad shape - not preaching to JD).


conngs0 says: (3/30/16 3:46 PM)
This will be a very important design with respect to integrating the east side of South Capitol Street where Nats Park is and the west side where the DC United Stadium will be. Moreover, I think it will be great to have two pedestrian and bike friendly ways to traverse the Anacostia River once this bridge and the 11th Street SE bridge park are completed.


jdc says: (3/30/16 4:59 PM)
I wish segments 4 and 5 came sooner, though I can see the benefit of waiting to do serious streetscape improvements until a lot of the heavy construction, and resulting wear and tear, is done.


dbt says: (3/31/16 1:59 PM)
One thing I still don't get about Phase 2 is how they expect to turn New Jersey Ave into a nice, wide urban boulevard, especially with ORE 82 jutting out almost to the curb in the current street alignment.


conngs0 says: (3/31/16 2:14 PM)
Agreed. That building single-handedly ruins any chance of turning New Jersey Avenue into a "boulevard". With all of the construction in the neighborhood taking place, New Jersey Avenue will certainly be long overdue for some improvements in terms of paving, etc., but there's really no point in other expenditures with that eyesore occupying the west side of the road.


JD says: (3/31/16 3:06 PM)
Yeah, the New Jersey Avenue thing is some lip service at this point.


crafter11 says: (4/1/16 10:49 AM)
Can you post a link to the RFP? Thanks!


JD says: (4/1/16 10:55 AM)
I haven't found the RFP online, perhaps because it's just going to the four teams shortlisted. (It'll probably show up eventually, somewhere.)


MarkinDC says: (4/1/16 11:43 AM)
I'm happy to see that I'm not the only one who looks at ORE 82 in disgust.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Top News

RMP on DDOT Unveils Planned: The OR/BL/SV lines are fine, but transferring to/from GR isn't ideal especially ...
Westnorth on DDOT Unveils Planned: I really love this "Downtown Ward 6" bus route! @RMP: A longer-term p...
202_cyclist on Peet's Coffee Coming: It looks like construction has started for 820 Potomac Ave. I saw a pile-drivin...
walt on DDOT Unveils Planned: This is excellent news! Can't wait to get on that circulator.
Message Board (beta)

  
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
900 B/O 5TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/15/17
1200 B/O 4TH ST SE   THEFT
Theft 2nd Degree (theft From Building)
 12/12/17
1200 B/O 4TH ST SE   THEFT
Theft 2nd Degree (theft From Building)
 12/11/17
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/11/17
1100 B/O 1ST ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/08/17
900 B/O NEW JERSEY AVE SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 12/08/17
1100 B/O NEW JERSEY AVE SE   THEFT
Shoplifting
 12/03/17
300 B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 12/02/17
500 B/O L ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 12/02/17
1100 5TH ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 12/01/17
400 B/O M ST SE   THEFT
Shoplifting
 11/29/17
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/28/17
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/27/17
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/26/17
1000 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/26/17
1000 B/O 8TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 11/24/17
1200 B/O NEW JERSEY AVE SE   THEFT
Theft First Degree (all Other Larceny)
 11/24/17
400 B/O M ST SE   THEFT
Shoplifting
 11/22/17
100 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 11/19/17

Recent Issued Building Permits Archive  
1100 2ND PL SE   
12/13/17 
BAKER DC / CHRISTINE LONG
AH1800290 / CONSTRUCTION
An after hours permit is respectfully requested from 5am thru 9pm daily
1331 2ND ST SE   
11/29/17 
DC WATER / DAVE LEVINE
AH1800282 / CONSTRUCTION
After Hours work for structure excavation and support for B1311474 DC Water. Corman Construction 301-343-5417
2 I ST SE   
11/29/17 
MCDONALDS CORPORATION / MICHAEL ERIC CAMPBELL
M1800603 / SUPPLEMENTAL
   
11/29/17 
MCDONALDS CORPORATION / DANIEL P. THOMPSON
P1801598 / SUPPLEMENTAL
   
12/01/17 
CRESCENT CAPITAL VIEW, LLC N/A / ERICKA CLARK
AH1800280 / CONSTRUCTION
Place and finish concrete. Minimal noise impact, and required for reduction on impact to traffic.
   
12/14/17 
CRESCENT CAPITAL VIEW, LLC N/A / ERICKA CLARK
AH1800324 / CONSTRUCTION
Place and finish concrete. Minimal noise impact, and required for reduction on impact to traffic.
70 I ST SE   
11/28/17 
DISTRICT OF COLUMBIA / OTIS ELEVATOR COMPANY; OTIS ELEVATOR COMPANY
ER1800447 / SHOP DRAWING
BODY OF WORK: Replace machine and recable elevator # 1.
337 L ST SE   
12/06/17 
JENNIFER LANCASTER / null
E1802092 / SUPPLEMENTAL
347 L ST SE   
12/07/17 
THOMAS PAQUIN / null
E1802129 / SUPPLEMENTAL
   
12/14/17 
THOMAS PAQUIN / BJORN FALK
SOL1800006 / CONSTRUCTION
Installation of a 5.4kW solar PV system. Parapet mounted, 15 panels
555 L ST SE   
11/27/17 
UNITED STATES OF AMERICA / CLIFFORD DIXON
B1714199 / CONSTRUCTION
DGS PROJECT This permit is for interior work only.SWING SPACE FOR WARD 6 CLINIC TO EXISTING VACANT JOY EVANS RECREATION CENTER TEMPORARILY FOR 12 TO 18 MONTHS
515 M ST SE   
12/11/17 
null / BLUE STAR DESIGN BUILD
BP1801085 / POST CARD
300 M ST SE STE# 402 20024   
12/13/17 
FEDERAL CENTER LP / null
P1802065 / SUPPLEMENTAL
100 M ST SE   
12/05/17 
CRANE SERVICE CO / CHRISTINE LONG
AH1800304 / CONSTRUCTION
An after hours permit is respectfully requested from 7AM Saturday thru 7PM Sunday
110 M ST SE   
12/13/17 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / THUY LE
TL1700234 / CONSTRUCTION
Interior alteration for new tenant, restaurant with 37 seats, 49 in occupancy load.
861 NEW JERSEY AVE SE   
12/14/17 
CSX TRANSPORTATION INC. / NA CSX TRANSPORTATION, INC.
AH1800330 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities.
1100 NEW JERSEY AVE SE 3RD FL   
11/22/17 
SQUARE 742 LLC / null
P1801490 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
12/06/17 
SQUARE 742 LLC / DOMINIC E TOTARO
M1800664 / SUPPLEMENTAL
   
12/08/17 
SQUARE 742 LLC / SAM HOLLEN
B1801219 / CONSTRUCTION
INTERIOR RENOVATION TO 2ND FLOOR OFFICE SPACE. PARTITIONS, FURNITURE, MEP, LIFE SAFETY AND STRUCTURAL HANGING MOVABLE PARTITION. 25,226 SQUARE FEET. ALION SCIENCE AND TECHNOLOGY **LEVEL 2 ALTERATION
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2017 JD.