With a zoning hearing coming up later this month, developers Brandywine REIT and Akridge have submitted additional materials to the Zoning Commission on their proposed 25 M Street, a 247,000-square-foot office building on the southwest corner of Half and M Streets, SE, currently home to the north end of the Fairgrounds.
The submissions expand on the details and renderings we first saw a few weeks ago, but the basics remain the same. The building received zoning approvals back in 2009, but now with a change in the development team and with an eye toward shifting desires of office tenants, some modifications to the approvals are being sought, most specifically reducing the distance from the edge of the building to its core to 45 feet to allow for "more natural light flowing into the interior offices," which resulted in the building's gross floor area space being reduced by about 23,000 square feet.
There are also now new terraces on the 3rd, 4th, and 9th floors in addition to the roof, and the building will also have about 21,000 square feet of retail space. However, the planned third underground level of parking has been removed, with the building now having 157 spaces on two levels.
The drawings below show the new design as seen from street level on M Street looking east (left), on Half Street looking west (middle) and on Van Street looking east (right), while the one at the top of this post is the building's Half Street facade and the second is of the view at Half and M. The second and third photos below show the "Via", a pedestrian walk between 25 M and JBG's planned Half Street residential project on the south end of the block.
The design was approved at Monday night's ANC 6D meeting 6-0-0--you can read the full text of the ANC's letter to the Zoning Commission about the project here.
No timetable for construction has been announced, but it is now the third of the three "missing pieces" on the block of Half Street just north of Nats Park to go through the zoning approval process in the past year with a revised design. So maybe the neighborhood's most visible and most lagging block will be on its way to completion by the time the stadium celebrates its 10th anniversary--and hosts the All-Star Game--in 2018.
Comments (7)
   
 
 More About Development News
 All posts: 25m, Development News, zoning

JDLand.com Home

Comments

knavyard says: (3/15/16 10:15 AM)
I think the building looks really great, but I'm disappointed they reduced the parking capacity.


ttassa says: (3/15/16 12:45 PM)
Wow, I think this building, and the other buildings on half, look great. Can't wait to see the completed versions, but I'm pessimistic they will be completed by the 2018 ASG.


jdc says: (3/15/16 1:37 PM)
I cannot wait to talk past THIS, instead of what's currently there. What an eyesore those containers have become. This, plus NAB building and the finished hotel on the opposite corner, will go a long, long way to making M and Half more attractive.


MJM says: (3/15/16 3:53 PM)
I cannot wait to talk past THIS, instead of what's currently there. What an eyesore those containers have become. This, plus NAB building and the finished hotel on the opposite corner, will go a long, long way to making M and Half more attractive.




Sorry I had to plagiarize, perfect comment!


dude says: (3/15/16 7:18 PM)
You talk past it and I'll walk past it.

Looks good!


jdc says: (3/16/16 2:24 PM)
ha MJM. I was reading 'your' comment and thinking 'hey, this sounds awfully like MY comment.' Then I got to your disclaimer and laughed.


Blue says: (3/21/16 11:19 PM)
Wafted seeing bjarke ingels' designs on 60 minutes last week, I think this neighborhood is sorely in need of some fresher designs. His New York building models are breathtaking and innovative!

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts
  

Alex B. on Transportation Study Meeting: That rendering of Walters seems a bit misleading, as it would imply a two story ...
caphillguy on Transportation Study Meeting: For everyone's information: the intersection at Virginia Ave and 7th Street was ...
JD on Transportation Study Meeting: Some details on Walters Sports Bar, still planning on coming to the space below ...
202_cyclist on Transportation Study Meeting: Exciting news folks! It looks like there was soil testing today for the former ...
CJBabyDaddy on Transportation Study Meeting: @RMP & @jdc: Sign on the front door says: “We are waiting on some officia...
conngs0 on Transportation Study Meeting: JD, thanks for passing along the update on the Capper Seniors building. I suppo...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1000 B/O 1ST ST SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 12/15/18
200 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 12/14/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 12/13/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/13/18
900 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (theft From Building)
 12/11/18
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (theft From Building)
 12/09/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/09/18
1100 B/O NEW JERSEY AVE SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 12/08/18
900 B/O 1ST ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 12/06/18
UNIT B/O N ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 12/05/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 12/01/18
1200 B/O HALF ST SE   ROBBERY  11/30/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/28/18
700 B/O L ST SE   THEFT
Shoplifting
 11/26/18
1255 1ST ST SE   ASSAULT WITH A DANGEROUS WEAPON  11/25/18
1200 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/23/18

Recent Issued Building Permits Archive  
1300 4TH ST SE 1ST FL   
12/12/18 
null / WAYNE DAUGHERTY 7035247911
E1902414 / SUPPLEMENTAL
1300 4TH ST SE   
12/11/18 
PARCEL O 1-LLC / N/A
B1900015 / CONSTRUCTION
Yards Parcel O1 - Revision to Base Building Permit B1609947 to incorporate minor design changes including converting a residential unit to a fitness center. TPR
1300 4TH ST SE B1   
12/12/18 
null / WAYNE DAUGHERTY 7035247911
E1902413 / SUPPLEMENTAL
1331 4TH ST SE CU   
12/10/18 
FC 1331 LLC / null
P1902045 / SUPPLEMENTAL
1300 4TH ST SE PENTHOUSE   
12/12/18 
null / WAYNE DAUGHERTY 7035247911
E1902412 / SUPPLEMENTAL
1300 4TH ST SE   
12/10/18 
PARCEL O-1 LLC / RICHARD V CAREY 301-424-8899
FB1900032 / SUPPLEMENTAL
(2) NEW INSTALL Gross 1,840,000 BTU / HR Natural Gas HW
1346 4TH ST SE   
12/07/18 
FC 1346 LLC / null
FB1900031 / SUPPLEMENTAL
1000 5TH ST SE   
12/11/18 
UNITED STATES OF AMERICA / null
E1902394 / SUPPLEMENTAL
   
12/11/18 
UNITED STATES OF AMERICA / BRANDON WILSON; BRANDON M WILSON
B1902777 / CONSTRUCTION
Kitchen Area: -Interior only Frame about 7lf around one column as per 2 / A030 -Add 260 SQF bulkhead as per 1 / A030 None Load bearing wall on first floor and second floor.. M,E,P, will be provided on another permit. IT Lounge -Add 194 SQF bulkhead as per 3 / A030
2 I ST SE   
12/10/18 
MCDONALDS CORPORATION / KIM MITCHELL
B1814290 / CONSTRUCTION
The submitted drawings are a revision to those approved under building permit #B1703907, and include the incorporation of a new corridor connection at the roof level between phase 1 and phase 2 buildings, and corresponding revisions. Revised Mechanical / Plumbing / Electrical drawings are included to reflect the change of Engineers of Record. Interior Design Drawings are also included. Various...
   
12/14/18 
CRESCENT CAPITAL VIEW, LLC / ERICKA CLARK
AH1900295 / CONSTRUCTION
Dismantle of tower crane. Minimal noise impact and required for reduction on impact to traffic.
250 M ST SE   
11/28/18 
SQUARE 769 LLC. / CONOR LAW
BCIV1800147 / CONSTRUCTION
New construction of erosion and sediment controls, domestic water service, fire service, sanitary sewer service, storm sewer service, curb & gutter, street trees, misc. landscaping, sidewalk, storm water management.
   
12/05/18 
null
E1902214 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE STE# 420   
11/27/18 
SQUARE 742 LLC / JAMES W LASHER
E1901850 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
11/20/18 
SQUARE 742 LLC / null
E1901715 / SUPPLEMENTAL
   
11/26/18 
SQUARE 742 LLC / null
P1901600 / SUPPLEMENTAL
   
11/26/18 
SQUARE 742 LLC / null
M1900652 / SUPPLEMENTAL
   
11/29/18 
SQUARE 742 LLC / JOE SAFFER
P1901753 / SUPPLEMENTAL
   
12/04/18 
SQUARE 742 LLC / PAUL WHITLEY
AN1900004 / CONSTRUCTION
This project consists on installing (9)proposed antennas , RRU's, and hybrid cables on an existing building, and removing (9) existing antennas, RRU's, TMA's, and hybrid cables.
   
12/05/18 
SQUARE 742 LLC / JOHN M. GIUSEPPE
B1900960 / CONSTRUCTION
renovations to 3rd floor office space SUITE 300 NATIONAL ASSOCIATION OF AREA AGENCIES ON AGING as shown on the electronically submitted mech., plumb., elect., fire protection, demolition, and architectural dwgs. Interior work only. No change in use. NO structural work involved. 7000 sf. **LEVEL 2 ALTERATION, DEMOLITION
125 O ST SE 2-6FL   
11/28/18 
DISTRICT OF COLUMBIA / ANDREW KLEIN 2408991526
E1901923 / SUPPLEMENTAL
125 O ST SE   
11/27/18 
DISTRICT OF COLUMBIA / MICHAEL P. LYONS
E1901853 / SUPPLEMENTAL
   
11/27/18 
DISTRICT OF COLUMBIA / WILLIAM H. JONES
E1901854 / SUPPLEMENTAL
   
11/29/18 
DISTRICT OF COLUMBIA / WESLEY R. DAVIS
E1901951 / SUPPLEMENTAL
   
11/29/18 
DISTRICT OF COLUMBIA / null
P1901748 / SUPPLEMENTAL
79 POTOMAC AVE SE   
11/27/18 
RIVERFRONT HOLDINGS LLC / null
AH1900270 / CONSTRUCTION
AFTER HOURS 7PM TO 7AM FINAL CONNECTION OF RELOCATED 8” SANITARY LINE
71 POTOMAC AVE SE   
11/26/18 
RIVERFRONT HOLDINGS I LLC / JUSTIN BELLOW
B1804337 / CONSTRUCTION
New 264-Unit 13-Stories Apartment House
   
12/03/18 
RIVERFRONT PROPERTIES LLC / null
P1901813 / SUPPLEMENTAL
   
12/13/18 
RIVERFRONT HOLDINGS LL, LLC / PARKER HARRELL
SB1900071 / CONSTRUCTION
Abandoning 20 temporary wellpoints and 3 gravel packed wells originally installed for dewatering during construction.
79 POTOMAC AVE SE   
12/13/18 
RIVERFRONT HOLDINGS I LLC / null
E1902479 / SUPPLEMENTAL
227 TINGEY ST SE   
11/30/18 
FOREST CITY WASHINGTON / DFM DEVELOPMENT SERVICES, LLC
AH1900285 / CONSTRUCTION
Yards Parcel L-2. Afterhours permit for the purpose of installing precast concrete façade panels. Work to take place 7PM to 7AM, 12 / 5 / 2018 to 1 / 5 / 2019.
300 TINGEY ST SE   
12/04/18 
FC BOILERMAKER LLC / STEPHEN ADAMS 2403042373
E1902120 / SUPPLEMENTAL
   
12/06/18 
FC BOILERMAKER LLC / GARY BRENT; N/A
SG1900027 / CONSTRUCTION
Install 1 illuminated edge-lit wall logo sign, 1 illuminated halo-lit letter sign, 1 double-sided push thru edge-lit blade sign - LULULEMON
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.