Last week DDOT released its Southeast Blvd. Feasibility Study, in which the agency "evaluated the feasibility of transitioning a segment of the former Southeast Freeway from 11th Street to Barney Circle into an urban boulevard more consistent with the expected travel demand and the character of the adjacent neighborhood."
This study was a follow-on to the Office of Planning's Southeast Blvd. Planning Study, which came about after residents expressed displeasure with the initial efforts seen in the Barney Circle-Southeast Blvd. Transportation Planning Study.
And what does the feasibility study say? DDOT's report determines that changing the current Southeast Blvd. from the limited-access quick route between 11th Street SE and Barney Circle to a street with connections to its north and south and development along the footprint is feasible, but the transformation "would be neither inexpensive nor quick."
The study then goes through the issues that make clear this would not be a snap-the-fingers-and-make-it-so proposition:
*Ownership: There are two small parcels within the study area owned by the National Park Service--and we know quickly either arranging for a change in ownership or "coordinating" with NPS can go. The study refers to it as being clear "that there would be significant process requirements and challenges to disposing the NPS and incorporating them into private development." That the process to "surplus" any excess land along the footprint not needed for the road(s) itself is governed by the Federal Highway Administration would also not point to a lightning-quick resolution.
* Transit Garages: The inclusion of some location that would allow for the parking of tour buses, transit buses and streetcars {cough}--a big part of DDOT's wishes for the area but something that residents are not particularly keen on--"could be provided at Southeast Boulevard that takes advantage of the location and topography of the site to minimize visual impacts to surrounding neighborhoods and so that vehicles accessing the facility would not use residential neighborhood streets."
* Cost: The study's "cursory assessment" says that constructing the transportation elements of the project would cost around $120 million, with a transit garage adding about $65-70 million in costs (in 2015 dollars). This includes reconfiguring Barney Circle into an at-grade signalized traffic circle, raising Southeast Boulevard to the same level as L Street, and constructing a four-lane street that includes sidewalks, bike facilities, and traffic signals. Plus some contingency costs built in.
* Schedule: The graphic at right breaks out a not-short ballpark timeline of 10 years for both the "transportation" portion of the project and the land redevelopment project.
With all of that, DDOT says that the first step forward is to restart the Barney Circle and Southeast Blvd. Transportation Planning Study begun in 2013, though even that now has a road block, that this Environmental Assessment now can't be completed "until a financial plan for project implementation is identified and included in the regional Constrained Long-Range Transportation Plan (CLRP)." DDOT advises interested groups "to continue discussions with a broad spectrum of stakeholders during the EA to confirm community support for the project, engage with AWI Signatories, and evaluate project costs and funding options."
This final draft was presented to ANC 6B's Transportation Committee on Jan. 6, and Capitol Hill Corner reports that DDOT's representative told the committee that there were no "fatal flaws" in any of the Office of Planning's three concepts for reimagining the road--but that it will be "up to ANC 6B to push the project forward" by requesting the environmental assessment.
I am skimming it all, so if this project is of interest to you, be sure to read the feasibility report, and perhaps attend ANC 6B's meeting on Jan. 12, at which a draft letter will apparently be considered to support going ahead with the EA.
You can also wander through my posts on the subject from the past few years, especially on the completion of the OP study back in July and the three general concepts advanced for how to remake this stretch of land that currently serves as such a barrier between Capitol Hill/Hill East and the Anacostia River.
Comments (7)
   
 
 More About Traffic Issues

JDLand.com Home

Comments

dude says: (1/11/16 7:42 AM)
Seems like an awful lot of money for what it achieves.


jdc says: (1/11/16 8:32 AM)
To me this is sort of a 'no brainer' in terms of spreading around - and linking to - the massive redevelopment going on in near SE. From the city's perspective, more development = more taxes.


202_cyclist says: (1/11/16 8:56 AM)
@jdc:

Exactly right-- someone posted a comment on the Capitol Hill Corner blog estimating the expected future tax revenue of creating an entirely new neighborhood: link

Additionally, there are other benefits, such as linking neighborhoods and allowing more people to live in a walkable neighborhood and near transit, including the Potomac Ave station.


monkeyrotica says: (1/11/16 10:22 AM)
More roads = more congestion. Why does this "boulevard" even exist? Instead of spending $120 mil (which will eventually bloat to $200+ mil) just sell the land, build residential/retail, and re-open the north/south streets.


conngs0 says: (1/11/16 11:01 AM)
Agree with jdc. Doesn't the status quo risk maintaining a barrier between the planned development in Hill East by Stadium Armory and the 11th Street Bridge Park and the rest of the Navy Yard area? It sure seems like this would help maximize the returns on those other investments.


jdc says: (1/11/16 12:03 PM)
My fantasy - yes, I may need help - is that the explosive growth and interest in SE, then SW, and then 'eco district' they're building around L'Enfant, will lead to financial incentives sometime in my lifetime to tunneling and locating 695/SE-SE Freeway underground. Basically, selling air rights. It's about 5 miles as configured, and I wonder if that figure could be cut down if it took a more direct route. Yes, everyone will think of the "Big Dig" mess - but, a recent piece sort of exonerated the project and I bet in another 10-20 years it will be an accepted piece of US infrastructure. Plus, the lessons learned and the advancement in drilling will make this an easier project in all likelihood.


conngs0 says: (1/11/16 2:05 PM)
Even in the case of the Big Dig, I don't think it's the project itself that needs exoneration - it's the execution of the project. One of the reasons why the people of Boston were so against hosting the Olympics was that, based on the cost overruns and delays, they had zero faith that their local government could properly execute such a huge expenditure. After all, it's not that hosting an Olympics has to cripple the local economy; it's that hosting an Olympics typical cripples the local economy because the host country/city does such a poor job of planning the games.

I have a similar opinion of your fantasy regarding putting the SE Freeway underground. Would it benefit the neighborhood and the city (and commuters)? Could it be a worthwhile project? Absolutely. But you have to have faith in the execution.

An even better example of this phenomenon is the Metro 2040 plan. link This would undoubtedly be fantastic for the city. It'll never happen though because the people responsible for implementing such a plan will certainly mess it up!

Let's see how the Capitol Crossing project pans out. If that winds up being a success, perhaps there will be more support for significant infrastructure improvement along the lines you have in mind.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts
  

walt on West Half Now: I love the West Half logo. But there should probably be a $$ in there somewher...
CJBabyDaddy on Entertainment Venue Addition: @conngs0: And let the church say “Amen.” You and I need to storm Lerner HQ and...
conngs0 on Entertainment Venue Addition: CJ, I am willing to go to Nats Park in October even after an inevitable playoff ...
CJBabyDaddy on Entertainment Venue Addition: @conngs0: I thought the Nats’ recurring playoff collapses were the worst things...
GarfieldPark on Entertainment Venue Addition: ORE residents received a notice that the sidewalk will be closing on NJ avenue (...
202_cyclist on Entertainment Venue Addition: @conngs0— I agree, I couldn’t care less about sports betting but I am glad there...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1100 B/O NEW JERSEY AVE SE   THEFT
Shoplifting
 09/13/19
300 B/O M ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 09/13/19
400 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/11/19
400 B/O M ST SE   THEFT
Shoplifting
 09/10/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/09/19
54 M ST SE   BURGLARY
Burglary Two
 09/07/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 09/05/19
400 B/O M ST SE   THEFT
Shoplifting
 08/30/19
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (theft From Building)
 08/28/19
500 B/O M ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 08/28/19
800 B/O VIRGINIA AVE SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 08/28/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 08/28/19
500 B/O L ST SE   ROBBERY  08/26/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/25/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/25/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/23/19
300 B/O K ST SE   THEFT
Theft 2nd Degree - Felony (all Other Larceny)
 08/23/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/22/19
1100 B/O 2ND PLACE SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 08/21/19
300 B/O L ST SE   BURGLARY
Burglary One
 08/21/19
100 B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 08/20/19
1200 B/O SOUTH CAPITOL ST SE   ROBBERY  08/20/19
150 B/O L ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 08/18/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/15/19
700 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/15/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 08/15/19

Recent Issued Building Permits Archive  
1300 4TH ST SE   
08/20/19 
YAAN REAL ESTATE LP / MITCH A. PERMUY; MITCH A. PERMUY
E1910356 / SUPPLEMENTAL
1346 4TH ST SE   
09/11/19 
FC 1346 HOLDCO I LLC / null
E1911472 / SUPPLEMENTAL
900 5TH ST SE   
08/30/19 
CAPPER CARROLLSBURG VENTURES, LLC / DFM DEVELOPMENT SERVICES, LLC
B1906215 / CONSTRUCTION
Reconstruction of 4-story residential building, the Arthur Capper Senior Center, damaged by fire.
150 I ST SE   
08/20/19 
null
E1910665 / SUPPLEMENTAL
200 I ST SE   
09/04/19 
DISTRICT OF COLUMBIA / ROGER L PEACE
BP1904525 / POST CARD
   
09/04/19 
DISTRICT OF COLUMBIA / ROGER L PEACE
BP1904526 / POST CARD
   
09/04/19 
DISTRICT OF COLUMBIA / ROGER L PEACE
BP1904529 / POST CARD
419 K ST SE   
08/19/19 
FAROOQ MITHA / KYLE YOST; KYLE YOST
SOL1901385 / CONSTRUCTION
rooftop solar pv system, less than 4' above roof
   
08/21/19 
FAROOQ A MITHA / null
E1910733 / SUPPLEMENTAL
100 M ST SE 20003   
08/21/19 
PARSONS / null
E1910735 / SUPPLEMENTAL
100 M ST SE 9TH FLOOR   
09/05/19 
SQUARE 743 INC / DAVID FLEMING; DAVID FLEMING
P1909280 / SUPPLEMENTAL
100 M ST SE SUITE 910   
08/22/19 
SQUARE 743 INC / null
E1910764 / SUPPLEMENTAL
100 M ST SE   
09/05/19 
SQUARE 743 INC / FREDERICK S. DONHAM; FREDERICK S. DONHAM
P1909275 / SUPPLEMENTAL
ONE OPEN SITE DRAIN
250 M ST SE   
08/26/19 
null / ;
P1908962 / SUPPLEMENTAL
   
08/27/19 
SQUARE 769 LLC / STEVEN CHEN
AH1901196 / CONSTRUCTION
After hours permit is respectfully requested from 3am to 7am daily.
   
09/04/19 
SQUARE 769 LLC / JEFFREY D WOLF
AH1901226 / CONSTRUCTION
After hours permit respectfully requested from 3 am to 7 am daily.
861 NEW JERSEY AVE SE   
08/26/19 
CSX TRANSPORTATION, INC / ; N/A; TBD
R1900100 / CONSTRUCTION
RAZE 1 STORY WOOD FRAMED STRUCTURE
1275 NEW JERSEY AVE SE   
08/20/19 
UNITED STATES OF AMERICA / JUSTIN BELLOW; JUSTIN BELLOW; TBD
BCIV1900130 / CONSTRUCTION
Civil permit for grading, site demo, and installation of sediment erosion control measures Site utilities, provide property. Stormwater management will be under subsequent permits.
1100 NEW JERSEY AVE SE   
08/22/19 
SQUARE 742 LLC / null
E1910802 / SUPPLEMENTAL
1275 NEW JERSEY AVE SE   
08/23/19 
UNITED STATES OF AMERICA / ROBERT K WILLETT; ROBERT K WILLETT
E1910857 / SUPPLEMENTAL
   
09/03/19 
UNITED STATES OF AMERICA / PARKER HARRELL; PARKER HARRELL
SB1900287 / CONSTRUCTION
We propose to furnish and install fifteen (15) gravel packed wells, fourteen (14) around the perimeter, and one (1) at the elevator pit. We will also be installing 3 monitoring wells and potentially 5 contingency wells. We will only pump from up to 15 wells at a time. All wells will be located in a mutually agreed layout. The wells will be installed by advancing up to a 10.25 I.D. hollow stem auge...
125 O ST SE   
08/19/19 
DC WATER / null
E1910631 / SUPPLEMENTAL
79 POTOMAC AVE SE   
08/19/19 
RIVERFRONT HOLDINGS I LLC / null
E1910633 / SUPPLEMENTAL
301 TINGEY ST SE C-1   
09/03/19 
SEFC 160, LLC / JEFF NOLD
AH1901221 / CONSTRUCTION
Work will occur on 3rd Street SE between Tingey St SE & Water St SE. We will be assessing and providing a CCTV inspection of a sewer line.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2019 JD.