2nd (East) at K, Looking South-Southeast (see more)

While the appearance of a canopy over a front entrance does not signal that an under-construction apartment building is ready to start welcoming residents next week, it's still an interesting progress point to see at both the Park Chelsea and Arris residential projects. There's also landscaping starting to go in along the Park Chelsea's sidewalks on both New Jersey and would-you-just-open-already I Street--plus the leasing countdown clock has remained set for January 2016 for a few months now. As for Arris, the latest word remains "early 2016" for when it will open--and 2016 just isn't as far away as it used to be.
To the east, the not-minor project to do the masonry work and the siding at the 195-unit mixed-income Lofts at Capitol Quarter at 7th Street continues--apologies for only showing the rear of the building when I take a wide shot, but with the trees and the narrowness of L Street it's basically impossible for me to get a good photograph of the front. (Plus the low sun angle from late October through early March makes southern-facing photos a pretty miserable experience with a pretty miserable outcome, anyway.)
At 5th and K, the Capper Community Center's exterior isn't changing too much at this stage, but I'd get the shakes if I tried to not photograph it.
At New Jersey and Tingey, the new trapeze school building's blue-and-white exterior is mostly finished, though I'm such a bad blogger that it didn't occur to me to walk up to the big opening and peek in--but TSNYDC has posted a photo of the inside.
As for the Brig, the beer garden-to-be at 8th and L, the building itself looks pretty well finished now, though the "garden" portion of the venture does not appear to have gotten underway yet. And with two pit bulls on guard (!), I wasn't about to poke my camera through the fence for a better view.
And while I had designs on pressing my camera up against the glass at Buffalo Wild Wings on Half Street, they were having a staff training session when I arrived, and so I chickened out (Bad Blogger Data Point #2). But the gentleman I spoke with there confirmed again the Nov. 16 opening date, saying that the doors will open that day at 10 am--and that they generally have people camping out over Sunday nights to be among the first 100 customers through the door, who are then winners of the free-wings-once-a-week-for-a-year prize. Hope y'all have warm sleeping bags!
Still to come, the skeletons-and-holes report.
Comments (10)
   
 
 More About Development News

JDLand.com Home

Comments

conngs0 says: (11/10/15 10:20 AM)
"chickened out". Nice.


crispy says: (11/10/15 10:22 AM)
It looks like Arris and Park Chelsea are going to open about the same time, which is going to bring a huge flux of people down to the Navy Yard area. I hope Metro is planning to add more trains to the morning rush hour!


JHUGrad says: (11/10/15 10:42 AM)
My prediction is that in 5 years, the Capitol Riverfront will be a mini downtown DC.


NavyYardGuy says: (11/10/15 11:02 AM)
@JHU Grad: Do we really want it to be a miniature version of dtwn DC? At times I feel the downtown area to be very generic--and Navy Yard starting to feel like V I R G I N I A..


JD says: (11/10/15 11:17 AM)
In other news, a first rendering for Lerner's 1000 South Capitol proposed residential building:

link

(It's a U-shaped building, with the courtyard facing east toward 1015 Half St.)



Daedam says: (11/10/15 11:20 AM)
Maybe residents in Park Chelsea will feel the crunch on the Green line and walk to Capitol South. Either way, the Green line is going to start feeling pretty cramped by 2018, especially on baseball and/or soccer days.


JD says: (11/10/15 11:33 AM)
The Park Chelsea (and then its sibling the Whole Foods building) will be by far the largest apartment buildings anywhere close to Capitol South. I wouldn't be surprised that a lot of people who decide to live there will already be Orange/Blue line commuters. (Or Hill rats.)


RMP says: (11/10/15 11:45 AM)
I contacted the Forest City leasing office to ask about Arris and all they said was that they added me to an "interest list" but gave zero information about when leasing actually begins.


JES says: (11/10/15 12:01 PM)
LOL. Metro adding trains. Now THAT is a good joke.


BethD says: (11/10/15 12:24 PM)
I live in Capitol Hill Tower and already prefer to walk up to Capitol South. More walking but removes an AM rush transfer at Gallery Place which is not a great way to start the day.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Top News
  

kalicki on A Photo Tour: I generally like the style of this building, but man, the white lights on the fa...
conngs0 on A Photo Tour: Whoops! I don't know how I jumped to full replacement! Sorry! Regardless, kee...
JD on A Photo Tour: Not a hip replacement! Had to have the torn labrum repaired and the head of the ...
conngs0 on A Photo Tour: Thanks for the update, JD! I know you've been waiting for a cell phone store fo...
Message Board (beta)

Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 02/22/18
400 B/O M ST SE   THEFT
Shoplifting
 02/21/18
UNIT B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 02/19/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/15/18
1000 B/O 3RD ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/07/18

Recent Issued Building Permits Archive  
1100 2ND PL SE   
02/21/18 
BAKER DC / CHRISTINE LONG
AH1800618 / CONSTRUCTION
An after hours permit is respectfully requested from 5AM to 9PM daily
1331 2ND ST SE 20003   
01/29/18 
DC WATER / DAVE LEVINE
AH1800505 / CONSTRUCTION
After hours work for structure exaction and support for B1311474 DC Water. Corman Construction 202-863-0052.
1016 3RD ST SE   
02/01/18 
ANAMARIA R MOTTOLA / DAVID L. HAHN
P1803348 / SUPPLEMENTAL
1346 4TH ST SE   
02/06/18 
ALAN OWINGS / ROBERT SEV HENRY
AH1800541 / CONSTRUCTION
After Hours Permit for 2 / 19 / 18 from 7AM to 7PM to perform concrete, framing, and utility operations.
   
02/06/18 
FC 1346 LLC / RICHARD V CAREY
P1803428 / SUPPLEMENTAL
150 I ST SE   
02/05/18 
WC SMITH / null
P1803402 / SUPPLEMENTAL
140 M ST SE   
02/07/18 
SPAULDING & SLYE/STE100 / null
E1803798 / SUPPLEMENTAL
110 M ST SE   
01/29/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / JAMES WEAVER
E1803534 / SUPPLEMENTAL
   
02/02/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
P1803361 / SUPPLEMENTAL
140 M ST SE 20032   
02/14/18 
SYLVIA LINDSEY / null
P1803641 / SUPPLEMENTAL
202 M ST SE   
01/29/18 
UNITED STATES OF AMERICA / NURI EROL
D1800281 / CONSTRUCTION
Remove Existing flooring. Remove some of the furnitures, equipment.
300 M ST SE 53533   
02/08/18 
FEDERAL CENTER LP / SPENCER TEEL
BP1801893 / POST CARD
300 M ST SE   
02/16/18 
FEDERAL CENTER LP / STEVEN MERCHANT
B1803279 / CONSTRUCTION
New Sprint store sustainable design tenant build-out in an existing building, partical first floor. Work will consist of building a new sales floor and back of the house. New work sill consist of display fixtures, ceiling, plumbing fixtures, mechanical ductwork to diffusers, interior partitions, floor finishes, outlets and new locations of electrical panels. **CHANGE IN USE, LEVEL 2 ALTERATION
401 M ST SE   
01/30/18 
DOEE C/O DEV MURALI / JESSICA REICHARD
AH1800507 / CONSTRUCTION
After hours permit to preform manhole inspections during off peak hours 7pm - 7am for all Manhole Locations covered under permit # PA10374319-R1 for DOEE Anacostia river sediment project.
861 NEW JERSEY AVE SE   
01/31/18 
CONSOLIDATED RAIL CORPORATION / NA CSX TRANSPORTATION, INC.
AH1800467 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities.***TO EXCLUDE LEGAL HOLIDAYS**
1100 NEW JERSEY AVE SE 2ND FL   
02/09/18 
SQUARE 742 LLC / null
P1803534 / SUPPLEMENTAL
   
02/14/18 
SQUARE 742 LLC / null
P1803681 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
02/15/18 
SQUARE 742 LLC / null
E1804057 / SUPPLEMENTAL
79 POTOMAC AVE SE   
02/21/18 
RIVERFRONT HOLDINGS I LLC / JUSTIN BELLOW
B1805358 / CONSTRUCTION
Address revision only for B1702971 from 25 Potomac Ave SE to 79 Potomac Ave SE.
640 SOUTH CAPITOL ST SE   
02/05/18 
JIM LATISIS ZAYO GROUP
B1707197 / CONSTRUCTION
Addition to existing concrete telecom building.
401 TINGEY ST SE   
01/30/18 
PEPCO / BARBARA ANN STEDMAN
AH1800520 / CONSTRUCTION
UG TRANSFORMER WORK TO BE PERFORMED ON THE 400 BLK OF TINGEY ST SE. MANHOLE ACCESS. WORK TO BE PERFORMED BETWEEN THE HOURS OF 7:30AM AND MIGHTNIGHT ON 1 / 30 / 18 AND 1 / 31 / 18.
227 TINGEY ST SE   
01/29/18 
UNITED STATES OF AMERICA / ERICKA CLARK
TC1800021 / CONSTRUCTION
2 tower cranes
   
01/30/18 
FOREST CITY WASHINGTON / MELISSA DIAZ
B1802750 / CONSTRUCTION
Revision to Permit SH1700028. Sheeting and shoring for Yards Parcel L-2 project. Revision includes 10-foot precut excavation and layback on Water Street, 3rd Street and northern L-1 elevations, and removal of upper tier of rakers at L-1 elevation and upper tier of tiebacks at the Water Street and 3rd Street elevations.
   
02/20/18 
FOREST CITY WASHINGTON / FOREST CITY WASHINGTON; DFM DEVELOPMENT SERVICES
FD1700057 / CONSTRUCTION
Yards parcel L-2. Construction of foundation and underground parking garage for new 11 story multi-family mixed used residential building at 227 Tingey Street SE as part of development of Parcel L at the Yards
325 VIRGINIA AVE SE 20003   
02/14/18 
JASON W GOLDSMITH / null
E1804039 / SUPPLEMENTAL
325 VIRGINIA AVE SE   
02/06/18 
JASON W GOLDSMITH / CRAIG HARTSOCK
B1804721 / CONSTRUCTION
Remove two non-structural walls on ground level of townhouse and re-frame in new configuration to create a full bathroom on ground floor.
   
02/07/18 
JASON W GOLDSMITH / MORIS O. OCHOA PINEDA
P1803462 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
1001 NEW JERSEY AV SE   12/28/17
$ 687,365
WHATS ON SECOND PROPERTIES LLC
 


Project Directory
Completed
Agora ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.