This is mainly an excuse for me to post photos I got by schlepping up onto the Douglass Bridge on Sunday, but it's worth noting that it was announced last week that vertical construction is now finished on Dock 79, the 305-unit residential building that is the first phase of the never-thought-it-would-finally-happen redevelopment of the Florida Rock site along the Anacostia River. And so let's take a moment to look back to what the site looked like in 2005, and what it looks like now:
One other item of note at the site--as seen below, beams have been placed connecting a portion of the main concrete walkway at Diamond Teague Park to what will be Dock 79's plaza and Anacostia Riverwalk footprint, and without realizing it I did a pretty good job of matching my photo of the beams to the rendering of the same location:
There will be over 15,000 square feet of retail in the building, and in a press release from developer MRP Realty last week, John Begert is quoted as saying the retail space is being "programmed" with "a dynamic mix of local authentic restaurant operators," though no retail tenants have been announced as yet.
Most of this retail space will be facing the "esplanade" and this plaza, which MRP's press release says is "inspired by the concept of the “ecotone,” an ecological term referring to the transitional zone between two ecosystems."
The plaza also is directly south of the "grand staircase" of Nationals Park, ensuring that (some) views of the river from those steps and the viewing platform on the upper concourse are not completely lost.
The building is expected to deliver in the summer of 2016, and will have a ground-floor club/game room, a health club, a rooftop swimming pool, WiFi, air-conditioned storage, bike storage, a business lounge, and a 24-hour front desk.
The subsequent phases of the six-acre project are currently envisioned as a second residential building with 282 units and 5,600 square feet of retail, followed by a 313,000-square-foot office building with 11,500 square feet of retail, and then a fourth building that could be a hotel or another residential or office building, with 260,000 square feet of space and 12,600 square feet of ground-floor retail. (The footprint of the final two phases is, however, right up against the western end of the existing Douglass Bridge, so it might be awhile before those come to pass.)
See my Dock 79/Florida Rock page for lots more photos and renderings.
Comments (3)
   
 
 More About Florida Rock
 All posts: dock79, Florida Rock, riverwalk

JDLand.com Home

Comments

Jaybird says: (11/9/15 11:04 AM)
I'm anticipating arriving at a Nats game via the Alexandria ferry, sipping a pre-game beer at this place, then stepping inside the park, all with a certain ease not possible any other way, which is to say it avoids the crowds on the north side and is all close together.



Chaifetz10 says: (11/9/15 1:57 PM)
We went down to Sideyards this past weekend, and walking down New Jersey Ave from the Metro, we could see active construction equipment at what would be roughly New Jersey Ave and N St, on the south side. So far I haven't tracked anything down for this parcel... can anyone help me figure out what's being worked on here?


JD says: (11/9/15 1:58 PM)
That's DC Water doing infrastructure work as part of its huge Clean Rivers project.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Top News
  

kalicki on A Photo Tour: I generally like the style of this building, but man, the white lights on the fa...
conngs0 on A Photo Tour: Whoops! I don't know how I jumped to full replacement! Sorry! Regardless, kee...
JD on A Photo Tour: Not a hip replacement! Had to have the torn labrum repaired and the head of the ...
conngs0 on A Photo Tour: Thanks for the update, JD! I know you've been waiting for a cell phone store fo...
Message Board (beta)

Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 02/22/18
400 B/O M ST SE   THEFT
Shoplifting
 02/21/18
UNIT B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 02/19/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/15/18
1000 B/O 3RD ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/07/18

Recent Issued Building Permits Archive  
1100 2ND PL SE   
02/21/18 
BAKER DC / CHRISTINE LONG
AH1800618 / CONSTRUCTION
An after hours permit is respectfully requested from 5AM to 9PM daily
1331 2ND ST SE 20003   
01/29/18 
DC WATER / DAVE LEVINE
AH1800505 / CONSTRUCTION
After hours work for structure exaction and support for B1311474 DC Water. Corman Construction 202-863-0052.
1016 3RD ST SE   
02/01/18 
ANAMARIA R MOTTOLA / DAVID L. HAHN
P1803348 / SUPPLEMENTAL
1346 4TH ST SE   
02/06/18 
ALAN OWINGS / ROBERT SEV HENRY
AH1800541 / CONSTRUCTION
After Hours Permit for 2 / 19 / 18 from 7AM to 7PM to perform concrete, framing, and utility operations.
   
02/06/18 
FC 1346 LLC / RICHARD V CAREY
P1803428 / SUPPLEMENTAL
150 I ST SE   
02/05/18 
WC SMITH / null
P1803402 / SUPPLEMENTAL
140 M ST SE   
02/07/18 
SPAULDING & SLYE/STE100 / null
E1803798 / SUPPLEMENTAL
110 M ST SE   
01/29/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / JAMES WEAVER
E1803534 / SUPPLEMENTAL
   
02/02/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
P1803361 / SUPPLEMENTAL
140 M ST SE 20032   
02/14/18 
SYLVIA LINDSEY / null
P1803641 / SUPPLEMENTAL
202 M ST SE   
01/29/18 
UNITED STATES OF AMERICA / NURI EROL
D1800281 / CONSTRUCTION
Remove Existing flooring. Remove some of the furnitures, equipment.
300 M ST SE 53533   
02/08/18 
FEDERAL CENTER LP / SPENCER TEEL
BP1801893 / POST CARD
300 M ST SE   
02/16/18 
FEDERAL CENTER LP / STEVEN MERCHANT
B1803279 / CONSTRUCTION
New Sprint store sustainable design tenant build-out in an existing building, partical first floor. Work will consist of building a new sales floor and back of the house. New work sill consist of display fixtures, ceiling, plumbing fixtures, mechanical ductwork to diffusers, interior partitions, floor finishes, outlets and new locations of electrical panels. **CHANGE IN USE, LEVEL 2 ALTERATION
401 M ST SE   
01/30/18 
DOEE C/O DEV MURALI / JESSICA REICHARD
AH1800507 / CONSTRUCTION
After hours permit to preform manhole inspections during off peak hours 7pm - 7am for all Manhole Locations covered under permit # PA10374319-R1 for DOEE Anacostia river sediment project.
861 NEW JERSEY AVE SE   
01/31/18 
CONSOLIDATED RAIL CORPORATION / NA CSX TRANSPORTATION, INC.
AH1800467 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities.***TO EXCLUDE LEGAL HOLIDAYS**
1100 NEW JERSEY AVE SE 2ND FL   
02/09/18 
SQUARE 742 LLC / null
P1803534 / SUPPLEMENTAL
   
02/14/18 
SQUARE 742 LLC / null
P1803681 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
02/15/18 
SQUARE 742 LLC / null
E1804057 / SUPPLEMENTAL
79 POTOMAC AVE SE   
02/21/18 
RIVERFRONT HOLDINGS I LLC / JUSTIN BELLOW
B1805358 / CONSTRUCTION
Address revision only for B1702971 from 25 Potomac Ave SE to 79 Potomac Ave SE.
640 SOUTH CAPITOL ST SE   
02/05/18 
JIM LATISIS ZAYO GROUP
B1707197 / CONSTRUCTION
Addition to existing concrete telecom building.
401 TINGEY ST SE   
01/30/18 
PEPCO / BARBARA ANN STEDMAN
AH1800520 / CONSTRUCTION
UG TRANSFORMER WORK TO BE PERFORMED ON THE 400 BLK OF TINGEY ST SE. MANHOLE ACCESS. WORK TO BE PERFORMED BETWEEN THE HOURS OF 7:30AM AND MIGHTNIGHT ON 1 / 30 / 18 AND 1 / 31 / 18.
227 TINGEY ST SE   
01/29/18 
UNITED STATES OF AMERICA / ERICKA CLARK
TC1800021 / CONSTRUCTION
2 tower cranes
   
01/30/18 
FOREST CITY WASHINGTON / MELISSA DIAZ
B1802750 / CONSTRUCTION
Revision to Permit SH1700028. Sheeting and shoring for Yards Parcel L-2 project. Revision includes 10-foot precut excavation and layback on Water Street, 3rd Street and northern L-1 elevations, and removal of upper tier of rakers at L-1 elevation and upper tier of tiebacks at the Water Street and 3rd Street elevations.
   
02/20/18 
FOREST CITY WASHINGTON / FOREST CITY WASHINGTON; DFM DEVELOPMENT SERVICES
FD1700057 / CONSTRUCTION
Yards parcel L-2. Construction of foundation and underground parking garage for new 11 story multi-family mixed used residential building at 227 Tingey Street SE as part of development of Parcel L at the Yards
325 VIRGINIA AVE SE 20003   
02/14/18 
JASON W GOLDSMITH / null
E1804039 / SUPPLEMENTAL
325 VIRGINIA AVE SE   
02/06/18 
JASON W GOLDSMITH / CRAIG HARTSOCK
B1804721 / CONSTRUCTION
Remove two non-structural walls on ground level of townhouse and re-frame in new configuration to create a full bathroom on ground floor.
   
02/07/18 
JASON W GOLDSMITH / MORIS O. OCHOA PINEDA
P1803462 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
1001 NEW JERSEY AV SE   12/28/17
$ 687,365
WHATS ON SECOND PROPERTIES LLC
 


Project Directory
Completed
Agora ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.