I recently took you along the multiple blocks of Virginia Avenue that are in the process of getting dug up as part of CSX's tunnel expansion and reconstruction project. But even though it's going to be a few years before the tunnels are completed, the process is underway to talk about what Virginia Avenue will look like after the construction is over.
CSX is in charge of this streetscape-and-landscaping upgrade and has submitted draft plans to various groups for review, and has posted some big (BIG) PDFs on the project web site. Meanwhile, ANC 6D commissioner Meredith Fascett put out the call last week looking for volunteers to join a neighborhood working group on the restoration plans.
But for those who don't want to wade through the PDFs, here are some partial screen grabs of CSX's submittals for the new Virginia Avenue, and I'm sure the bike/ped paths (both shared and separate) will be of interest, along with the plans to perk up Virginia Avenue Park.
These first two screen grabs show the general landscape and "roadway" plans from 2nd to 4th Street, and from 4th to 5th (click to enlarge):
For the westernmost blocks, there will be a shared porous asphalt path on the street's south side. Then, starting at 4th Street, there will be separate asphalt bike path and a companion walking path with permeable pavers. The second image also shows the expanded pocket park between 4th and 5th that will be created thanks to the planned realignment of Virginia. Note that it also has a bike path that runs down to the I Street stub--which will make for a decent cut-over to I and its bike lanes from 3rd St. SE all the way into Southwest (well, once that little part between 2nd and New Jersey opens!).
The split paths continue from 5th Street to 9th Street, as you see below (once you click to enlarge, that is):
East of 9th, into Virginia Avenue Park, the path being built by CSX disappears, but the park design seen at right shows a path that runs along the north end of the park to 11th Street, where we can all dream of a day that it hooks up with the path that is supposed to be built alongside Southeast Blvd. to Barney Circle, making for an alternate route to the Anacostia Riverwalk Trail near RFK without having to go along M Street SE.
As for the park itself, the current dog park will be reconfigured, with both "large dog" and "small dog" areas. Some of the original paving stones recently uncovered will be placed in the park as well.
A public meeting to receive resident comments and feedback is expected to be happening soon, which I'm sure will be announced two minutes after I finish this post. UPDATE: Yup, less than 24 hours later, I'm seeing that the public meeting will be on Monday, Sept. 28 at 6:30, at a location to be determined.
Take a look at the full lineup of PDFs for better detail.
UPDATE, 10/7: After the meeting, updated block-by-block designs were made available (including a revision to reestablish the connection between the 400 block of I Street and Virginia Avenue), along with notes from the meeting.
Comments (4)
   
 
 More About CSX/Virginia Ave. Tunnel

JDLand.com Home

Comments

202_cyclist says: (9/10/15 10:03 AM)
Not related to the VA Ave tunnel but are the any updates for what is planned on the fenced-in lot next to Parc Riverside? There was a flatbed truck there this morning removing debris. Perhaps this was just left over from the construction of Parc Riverside and doesn't portend anything planned for the neighboring lot.


JD says: (9/10/15 10:08 AM)
No building permits, no announcements.

(Didn't we just talk about this a couple of weeks ago?)


BLT says: (9/10/15 10:54 AM)
Looks like they are storing construction equipment and materials. I have a feeling that this may be functioning as a storage area for the Homewood Suites since there isn't a lot of room next to that lot. Construction equipment/materials seem to be moving between the two.


conngs0 says: (9/10/15 1:47 PM)
The renderings of the parks look like a good start. The separate bike and walking paths are definitely a nice feature. I can't wait for this project to be completed!

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

Westnorth on Catching Up With: WBJ reporting that Chemonics, a contractor for USAID etc., is going to anchor th...
dcgent on Catching Up With: Rising Stars Chef Michael Rafidi and Sommelier Brent Kroll Will Open a Restauran...
dcgent on Catching Up With: Some more restaurants coming https://www.washingtonian.com/2018/11/19/two-of-dcs...
ColoradoCane on Catching Up With: Justin's Cafe closed seemingly due to money troubles. The business filed for ba...
jdc on Catching Up With: Isn't parking also metered north of M Street, too? It seems to be on Half, L, et...
NavyYardNittany on Catching Up With: Washingtonian piece on two new places in the ‘hood scheduled to open next summer...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/13/18
150 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/12/18
400 B/O M ST SE   THEFT FROM AUTO
Theft Of Motor Vehicle Parts Or Accessories
 11/11/18
700 B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle) - Convenience Store
 11/11/18
800 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 11/09/18
700 B/O M ST SE   THEFT
Theft First Degree (all Other Larceny)
 11/09/18
1200 B/O 4TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/08/18
400 B/O M ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 11/07/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/07/18
800 B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 10/31/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/30/18
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (theft From Building)
 10/29/18
50 B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 10/28/18
100 B/O O ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 10/28/18
1400 B/O M ST SE   ASSAULT WITH A DANGEROUS WEAPON  10/26/18
100 B/O M ST SE   THEFT
Theft 2nd Degree - Felony (all Other Larceny)
 10/23/18
900 B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 10/23/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/22/18
900 B/O 5TH ST SE   HOMICIDE
Murder I
 10/20/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/20/18
1000 B/O 1ST ST SE   THEFT
Theft 2nd Degree (theft From Building)
 10/19/18

Recent Issued Building Permits Archive  
1100 2ND PL SE   
10/23/18 
null / ANDY MCKELVEY
SP1800044 / CONSTRUCTION
Construct outdoor swimming pool on 10th floor roof of new building
1013 4TH ST SE   
11/05/18 
EVA WALTER / KYLE YOST
SOL1900066 / CONSTRUCTION
5.89kw rooftop solar pv system, less than 4' above roof
   
11/07/18 
EVA WALTER / null
E1901297 / SUPPLEMENTAL
1346 4TH ST SE   
11/01/18 
ALAN OWINGS / ROBERT HENRY
AH1900133 / CONSTRUCTION
After Hours Permit for 11 / 12 / 2018, to perform construction work with the below activities: Interior Operations: 7AM-7PM Exterior Operations: 9AM-7PM
1000 5TH ST SE   
10/31/18 
UNITED STATES OF AMERICA / JOY WILDER
B1901427 / CONSTRUCTION
Non Construction permit to change load for current Child Development Center with 26 children 3 to 6 years old +3 Staff to Child Development Center with 30 Children + 3 Staff.
   
11/16/18 
UNITED STATES OF AMERICA / BRANDON M WILSON
BP1900670 / POST CARD
2 I ST SE   
11/05/18 
CRESCENT CAPITAL VIEW / CASSANDRA MOSLEY
AH1900160 / CONSTRUCTION
Installation of wet utility services to the new building at 4 I Street SE including fire service, domestic service, and storm sewer.
   
11/14/18 
MCDONALDS CORPORATION / JUSTIN BISHOP
SP1800022 / CONSTRUCTION
Construct a 614 sqft in-ground, concrete swimming pool. All MEP, decking, and fencing work to be done under separate permit.
10 I ST SE   
10/24/18 
CAPITOL HILL RACQUET CLUB / BOB BIROONAK; N/A
SG1900026 / CONSTRUCTION
Relocating existing freestanding sign
   
11/14/18 
CAPITOL HILL RACQUET CLUB / BOB BIROONAK; N/A
SG1900075 / CONSTRUCTION
revision to existing approved sign permit SG1900026 Change to the footer only
110 I ST SE   
11/06/18 
null
E1901238 / SUPPLEMENTAL
200 I ST SE 20009   
10/25/18 
DISTRICT OF COLUMBIA / null
M1900267 / SUPPLEMENTAL
200 I ST SE   
11/05/18 
GOVERNMENT OF THE DISTRICT OF COLUMBIA / null
E1901223 / SUPPLEMENTAL
   
10/25/18 
DISTRICT OF COLUMBIA / CLIFFORD DIXON
B1809410 / CONSTRUCTION
DGS OCTO BUILDING...NEW GENERATOR ON THE ROOF WITH ASSOCIATED MECHANICAL
   
11/07/18 
DISTRICT OF COLUMBIA / DANIEL MCGUIRE
P1901098 / SUPPLEMENTAL
300 M ST SE 8TH FL   
10/24/18 
FEDERAL CENTER LP / ALFRED JORDAN 2024375067
E1900838 / SUPPLEMENTAL
300 M ST SE 8TH FLOOR 20003   
10/22/18 
JBG SMITH - MORGAN JOHNSON-MASSEY / null
E1900736 / SUPPLEMENTAL
130 M ST SE   
11/09/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / RICHARD PLUMLEY
P1901176 / SUPPLEMENTAL
250 M ST SE   
11/07/18 
WCSMITH - BRIAN STROTT / GEORGE ARTHUR KING
SB1900025 / CONSTRUCTION
Drill and construct two 2 inch diameter observation wells 42 feet below existing grade utilizing mud rotary drilling methods. All drill spoils will be contained, tested and disposed of per DOEE regulation.
400 M ST SE   
11/02/18 
CAPPER SENIOR 11 LIMITED PARTNERSHIP / null
E1901156 / SUPPLEMENTAL
861 NEW JERSEY AVE SE   
10/31/18 
CONSOLIDATED RAIL CORPORATION / BRANDON KNAPP
AH1900131 / CONSTRUCTION
Work in the public ROW with the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, concrete structure, paving, and site restoration construction activities.
   
11/07/18 
CONSOLIDATED RAIL CORPORATION / RPS INC
SB1900023 / CONSTRUCTION
Per Work Plan, Geotechnical Investigation, dated October 18, 2018 (see attached), the work involves drilling 12 soil borings using a HSA rig for the purpose of collecting soil samples for geotechnical subsurface exploration. Boring depths range from 80 to 150 ft. Borings will be properly backfilled after completion.
1100 NEW JERSEY AVE SE   
11/16/18 
SQUARE 742 LLC / IAN AND LEON COMMUN-ET LLC
B1901037 / CONSTRUCTION
EXISTING CONDITIONS TO BE DEMOLISHED AND NEW OFFICE SPACE BUILT TO TENANTS STANDARDS. OFFICE CONSISTS OF OPEN OFFICE AND PRIVATE OFFICES WITH SUPPORT AREAS. SUPPORT AREAS INCLUDE BREAK ROOM / PRODUCTION ROOM COMBINATION, SERVER ROOM WITH DEDICATED A / C, MOTHERS / WELLNESS ROOM AND CONFERENCING.
1111 NEW JERSEY AVE SE   
10/23/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / MICHAEL PISA; PISA
SG1800505 / CONSTRUCTION
Install 2 sets of wall mounted illuminated channel letters
   
10/25/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
E1900860 / SUPPLEMENTAL
   
11/05/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / MICHAEL B. BELL
E1901199 / SUPPLEMENTAL
125 O ST SE   
11/14/18 
DISTRICT OF COLUMBIA / CARL LAVENDT 2408821268
E1901525 / SUPPLEMENTAL
300 TINGEY ST SE STE# 140   
11/13/18 
FC BOILERMAKER LLC / ANTHONY DIRENZO
E1901464 / SUPPLEMENTAL
227 TINGEY ST SE   
11/01/18 
JOHN MORIARTY & ASSOCIATES / DFM DEVELOPMENT SERVICES, LLC
AH1900141 / CONSTRUCTION
Yards Parcel L-2. Afterhours permit for the purpose of installing precast concrete façade panels. Work to take place 7PM to 7AM, 11 / 5 through 12 / 5.
300 TINGEY ST SE   
11/05/18 
FC BOILERMAKER LLC / DREW PEISHEL; JOHN RANOUS
B1813340 / CONSTRUCTION
Minor interior tenant improvment including building one non-load bearing partitiion wall adding millwork fixtures including cash desk, fitting rooms. No Structural work. Some electrical updates. **LEVEL 2 ALTERATION
   
11/08/18 
FC BOILERMAKER LLC / STEPHEN ADAMS 2403042373
E1901337 / SUPPLEMENTAL
   
11/16/18 
FC BOILERMAKER LLC / ANTHONY L HARRISON
E1901597 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.