Since January, 2003
            
 Page Through from Before to After

With a May 28 Capitol Gateway Overlay design review on the calendar, the Jair Lynch/Half Street Hole project has within the past few days submitted additional materials to the Zoning Commission. And since I know how much everyone loves renderings....
The one I know will be of most interest is above left, showing what the new skyline would look like just to the northeast of Nats Park as seen from home plate, where Lynch's planned residential project will be situated. (They seemed to have tried to go for some sort of tilt-shift look, so it's not your eyes or my image file that's blurry, it's the original.) At right is a sharper/snazzier view of the building as seen from ground-level at Half and N, with the glass-walled corner portion of the planned 60,000-plus square feet of retail space a definite focal point. The darker fa├žade facing N Street delineates the planned condo portion of the project from the rental units (and possibly a hotel, or possibly not) around the corner on Half.
I wrote in detail about the plans for the site a few weeks ago, or you can check my Lynch Half project page for additional details.
Meanwhile, in other Ballpark District 2.0 news, I see an indication of forward progress on JBG's planned 290-unit residential project just north of the ballpark at 1244 South Capitol: an application was filed last week for a shoring/sheeting/excavation permit (got to dig down before you can build up!). The company has said they are looking to begin construction in late 2015 or early 2016.
Comments (8)
   
 
 More About Development News

JDLand.com Home

Comments

Section314 says: (5/18/15 6:10 PM)
How long does it usually take for a permit from application to approval if it is a big one like this one for shoring and excavation?


JD says: (5/18/15 6:12 PM)
It can take a few months, or it can take more than a few months.

Then there's the foundation-to-grade permit, and then the actual building permit.

If a late 2015 start is being eyed, this is not "too early," that's for sure.


conngs0 says: (5/18/15 9:36 PM)
Another round of bbq rumors! If Hill Country has committed to leaving the National Building Museum though, perhaps this rumor has legs...?

link


202_cyclist says: (5/18/15 10:28 PM)
Conngs0-- King Ribs in Siuthwest, across from Arena Stage, is without question the best BBQ in the immediate area.


202_cyclist says: (5/18/15 10:31 PM)
Hopefully one day the Public Storage building next to 1244 So. Cspitol St will be redeveloped.


conngs0 says: (5/19/15 9:18 AM)
I've heard King Ribs is awesome and can't wait to get over there to give it a try! In the meantime, I'm excited about the possibility of strolling over to will hopefully be a decent outdoor bbq venue in the immediate vicinity (if it happens) to complement what I consider to be a fairly underrated contribution from Willie's.


Jaybird says: (5/19/15 10:13 AM)
Interesting that the image on the upper left is a batting practice scene.

At first, I thought, why show all the empty seats???


ttassa says: (5/22/15 12:38 PM)
Hoping there is more of an iconic look to this building once it is built. In some ways, because of its view from homeplate and the activity it's going to inspire, it may be one of the most important buildings in this area. Right now, it doesn't look much different than other new developments in DC. Only so much you can do without height, I guess.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

JD on Retail Roundup: Yes, right the first time! [image]
Jscott280 on Retail Roundup: Sorry Parcel i lol
Jscott280 on Retail Roundup: Spoke with a parking lot attendant at Parcel I after I saw all monthly parking w...
AUshutterbug on Anchovy Social Opens: @Sasq thanks! We are anxious too. The "flood" happened 3 days before t...
Sasq on Anchovy Social Opens: @Aushutterbug I went to Maialiano Mare last Friday. When I told a server that I'...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
UNIT B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/15/20
400 B/O M ST SE   ASSAULT WITH A DANGEROUS WEAPON  02/08/20
300 B/O TINGEY ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/02/20
700 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/01/20
600 B/O VIRGINIA AVE SE   ASSAULT WITH A DANGEROUS WEAPON  01/29/20
1300 B/O 4TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 01/27/20
1100 B/O 8TH ST SE   BURGLARY
Burglary Two
 01/25/20
303 VIRGINIA AVE SE   ROBBERY  01/25/20
400 B/O M ST SE   THEFT
Shoplifting
 01/23/20
1255 1ST ST SE   THEFT
Theft 2nd Degree (theft From Building)
 01/19/20
400 B/O M ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 01/17/20

Recent Issued Building Permits Archive  
909 4TH ST SE   
02/12/20 
MEREDITH FASCETT / null
E2004655 / SUPPLEMENTAL
1300 4TH ST SE APT 214   
02/03/20 
null / NA NA NA
EHOP20983190 / HOME OCCUPATION
900 5TH ST SE   
01/24/20 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / WILLIAM B. CRIST; WILLIAM B. CRIST
E2003968 / SUPPLEMENTAL
1021 5TH ST SE   
02/13/20 
KEVIN WILLIAMS / KEVIN WILLIAMS; KEVIN WILLIAMS
B2005053 / CONSTRUCTION
Apply for building permit to have final closing inspection for permit #B1602481 & B1602513 per inspector inspection report since these permits has expired.
82 I ST SE   
01/27/20 
GDV EYE STREET LLC / null
P2003302 / SUPPLEMENTAL
   
01/27/20 
GDV EYE STREET LLC / null
M2001261 / SUPPLEMENTAL
100 I ST SE APT T-13   
01/25/20 
null / NA NA NA
EHOP20960826 / HOME OCCUPATION
150 I ST SE   
02/14/20 
SQUARE 737 LLC / JASON D DORRIS
AH2000818 / CONSTRUCTION
Construction of a new 13 story apartment building with three below grade parking levels, 1st floor retail, and amenity areas; 375 units and 181 parking spaces. To include mechanical, electrical, plumbing, elevators and structural work.
250 M ST SE   
02/14/20 
SQUARE 769 LLC / null
P2003901 / SUPPLEMENTAL
800 NEW JERSEY AVE SE   
01/30/20 
NEW JERSEY AT H LLC / MICHELLE GABBITAS
AH2000649 / CONSTRUCTION
Manhole rehabilitation on New Jersey, 2nd St and M St SE to repair 3 existing sewer manholes in DDOT ROW. Work will all be done through existing manholes (trenchless) and include lining, rebuilding and bypass of existing manholes.
861 NEW JERSEY AVE SE   
01/28/20 
DISTRICT OF COLUMBIA / JANE MCCRAY
AH2000647 / CONSTRUCTION
Pepco contractor, W.A.Chester, will be splicing cable on 02 / 01 / 2020 - 02 / 28 / 2020, from 9 PM - 7 AM.
1275 NEW JERSEY AVE SE 20003   
02/14/20 
BROOKFIELD PROPOERTIES / TIM GOOD
AH2000849 / CONSTRUCTION
After hours to conduct work on 1275 New Jersey Ave SE on the upcoming holiday, Presidents Day, February 17, 2020. Operations would include below grade concrete and waterproofing activities with access limited to N Street. This permit would not include extended work hours beyond the normal 7am to 7pm period.
1275 NEW JERSEY AVE SE   
01/29/20 
US GOVERNMENT / null
E2004153 / SUPPLEMENTAL
   
01/29/20 
MILLER AND LONG / WILLIAM MOORE
AH2000659 / CONSTRUCTION
Afterhours to pour concrete with pump truck from 11pm to 7am from 2 / 6 / 2020 to 3 / 6 / 2020
   
01/30/20 
UNITED STATES OF AMERICA / VINCENT J. BROWNING; VINCENT J. BROWNING
P2003449 / SUPPLEMENTAL
1-Oil / Sand interceptor
   
01/30/20 
US GOVERNMENT / null
E2004202 / SUPPLEMENTAL
   
02/07/20 
MILLER AND LONG / WILLIAM MOORE
AH2000699 / CONSTRUCTION
Afterhours to put up towercrane with mobile crane saturday 2 / 8 / 2020 and 2 / 9 / 2020 from 5am to 1159pm
1322 PATTERSON AVE SE   
02/13/20 
JOINT BASE ANACOSTIA BOLLING - UNITED STATES NAVAL OBSERVATORY SI / TONYA HARRIS; TONYA HARRIS; TBD
BCIV2000046 / CONSTRUCTION
***FEDERAL PROPERTY*** PROJECT WILL CONSIST OF DREDGING THE EXISTING RETENTION POND AND INSPECTING AND CLEANING THE OUTLET CONTROL STRUCTURE (S1) LOCATED ON THE UNITED STATES NAVAL OBSERVATORY TO REMOVE SEDIMENT ACCUMULATION. CONTRACTOR SHALL AVOID THE CLEARING OF VEGETATION ON POND EMBANKMENTS AND SURROUNDING AREAS SO AS TO KEEP RESTORATION AND REPLANTING TO A MINIMUM.
71 POTOMAC AVE SE   
02/13/20 
MRP REALTY / JAMES VANEGAS
AH2000681 / CONSTRUCTION
Perform interior and exterior construction activities. New construction 14-story new residential multi-family building.
79 POTOMAC AVE SE   
01/23/20 
RIVERFRONT HOLDINGS I LLC / ; W&M NA
B2003750 / CONSTRUCTION
320 SQ Ft metal canopy extension to exterior canopy. Existing canopy is standalone structure covering an outdoor bar area.
227 TINGEY ST SE   
01/23/20 
FFC 227 / ANDY MCKELVEY; ANDY MCKELVEY
SP1900050 / CONSTRUCTION
Install in-ground, gunite swimming pool on 11th floor of new construction. Scope includes gunite pool shell, finishes, and closed pool circulation system. All fresh water plumbing, sewer, electrical and mechanical work / connections by others. this permit is for a new commercial swimming pool
   
02/12/20 
GONE YARD HOTEL OWNER LLC / BOB BIROONAK; BOB BIROONAK
SG2000048 / CONSTRUCTION
one double face illuminated blade sign
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.