Since January, 2003
            
 Page Through from Before to After

Not quite six months after buying the land on the northeast corner of Half and N streets across from Nats Park currently known as Monument Valley, the MacFarlane/Jair Lynch joint venture has now submitted to the Zoning Commission its new plans for the site, a 10-story building with 461,700 square feet of residential (and possibly hotel) development, combined with at least 60,000 square feet of retail.
Back a couple of lifetimes ago, Monument Realty also planned a residential, retail, and hotel project on this site, so this filing is actually a modification to the previously approved plans. The new designs by architectural firm Hord Coplan Macht, seen in these renderings purloined from the zoning filing, would add at least 23,000 square feet of retail to what had been planned, mostly in the second-floor space along Half Street, as shown in the drawing below, as well as potentially an additional 8,000 square feet on the second floor facing N Street, depending on the all-important "market conditions."
The new project would have either 445 residential units and no hotel at all, or 365 residential units and a 80-room hotel on the north end of the site (down from a 200-room hotel in Monument's designs). The new design includes condos (apparently 130ish of them) in the south wing along N Street, with the rest being rental units.
As in the original designs, there would still be a small street called "Monument Place" running between this building and its neighbor to the north, 55 M Street, allowing the retail offerings to wrap around onto the building's north side--however, in these new plans it would be a pedestrian-only street, negating the need for a curb cut on Half Street.
In addition, the basically-an-alley Cushing Place would still be extended through to N Street, through an opening in the ground floor of the south side of Lynch's building. (If you look closely at the top rendering, you can see it.) There would still be three levels of underground parking with approximately 231 spaces. And there would be all manner of streetscape work to make the sidewalks--and the walk to the ballpark--a bit more inviting than they are now.
For you zoning groupies, there's also one special exception being requested, that the project be allowed to have two roof enclosures instead of one on the south wing of the building that fronts N Street. And note that this is all under the Capitol Gateway Overlay design review process.
These new plans will be presented to ANC 6D on Monday night (March 9), with a zoning hearing date apparently as yet unannounced. My Monument Valley project page has a few of the old Monument renderings, should you wish to compare.
UPDATE: The zoning hearing is apparently now scheduled for May 28.
Comments (13)
   
 
 More About Monument Valley/Half St.

JDLand.com Home

Comments

BLT says: (3/8/15 8:33 PM)
The good thing is once construction does begin, it will go vertical rather quickly! This is exciting to see.


JES says: (3/9/15 11:54 AM)
So I'm not too familiar with construction timelines. Assuming zoning has no issues with this plan, what would be the earliest we'd see construction starting? A year?


JD says: (3/9/15 11:58 AM)
They have said they are targeting 2016. A CG Overlay review is a quicker process than a PUD, especially since this is a modification. Then it's building permits. And finalizing construction financing.



BLT says: (3/9/15 12:39 PM)
Looks like a construction trailer and equipment have arrived at the Homewood Suites site today. They were wotking on the fencing earlier today.


JD says: (3/9/15 12:40 PM)
If you're having trouble keeping track of the Half Street 2.0 resurgence, I created this handy graphic:
link

It's part of my spruced-up-for-Opening-Day What's New Since Last Season page:
link



JD says: (3/9/15 12:41 PM)
@BLT, thanks for the update! I look forward to the race amongst readers to be the first to report ground being broken there. :)


BLT says: (3/9/15 3:53 PM)
And the Bonchon signs are going up! I should win a jdland t-shirt for this special reporting. :)


JD says: (3/9/15 5:40 PM)
Since MJM sent me a pic on Twitter showing fencing stuff happening at the Ballpark Square/99 M site, can somebody confirm that there was also stuff happening today at the 50 M/Homewood Suites site? (right across Half from the Big Stick)



BLT says: (3/9/15 5:56 PM)
@jd...I can walk over to 50 M and snap a picture. Can I send to an email?


JD says: (3/9/15 6:01 PM)
Sure! You can just send to jd at jdland etc. Thanks.

(Not that I didn't trust you--just that sometimes people confuse project locations, and since there was action elsewhere, just wanted to be doubly sure.)


BLT says: (3/9/15 6:07 PM)
No problem. Lots going on around here and I'm sure sites are confused often.


JD says: (3/9/15 6:10 PM)
I now have photographic evidence that BLT was correct. :)



Westnorth says: (3/10/15 11:43 AM)
60,000 feet -- finally, a retail space big enough for a "junior anchor." Most of the buildings around here have had spaces <20,000 feet, and there's only so much specialty retail to go around so far.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

CJBabyDaddy on Roundup of Some: @WestNorth: Methinks the proposed land swap involves/involved Navy Yard waterfr...
conngs0 on Roundup of Some: Cool news about the museum. It'll be interesting to see how it progresses from ...
Westnorth on Roundup of Some: Navy Museum is fundraising for a $450M new spot outside the Navy Yard gates, for...
VelocityChris on Roundup of Some: They're adding two floors to the top of the WeWork building.
GarfieldPark on Roundup of Some: Anyone know what is happening on First st outside of WeWork bldg? They are doing...
right-toe on Roundup of Some: Lots of little changes around: Sidewalk has opened up around the DDOT building,... [image]
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
UNIT B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/12/20
1000 B/O 1ST ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 10/12/20
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/09/20
1000 B/O 8TH ST SE   ROBBERY
Armed Carjacking
 10/09/20
400 B/O M ST SE   THEFT
Theft 2nd Degree - Felony (theft From Building)
 10/07/20
900 B/O M ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 10/01/20
1000 B/O 3RD ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 09/30/20
UNIT B/O K ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 09/29/20
1100 B/O 2ND PLACE SE   ROBBERY
Assault W/i To Commit Robbery (simple Assault)
 09/28/20
1000 B/O 4TH ST SE   ROBBERY
Carjacking
 09/26/20
1200 B/O HALF ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 09/22/20
600 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/21/20
1200 B/O VAN ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/19/20
1000 B/O 1ST ST SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 09/16/20
100 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/16/20
200 B/O L ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 09/13/20
1000 B/O 3RD PLACE SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 09/13/20

Recent Issued Building Permits Archive  
1031 5TH ST SE   
09/30/20 
CLARICE GEE / null
P2009304 / SUPPLEMENTAL
100 M ST SE   
09/25/20 
LHREV WASHINGTON M STREET LLC / THUY LE; NA
B2010745 / CONSTRUCTION
Suite 950 - Interior alteration. Work is to include minor change in MEP and Fire. No Structure.
1275 NEW JERSEY AVE SE   
09/18/20 
BROOKFIELD PROPERTIES / TIM GOOD
AH2001915 / CONSTRUCTION
After hours to conduct work on 1275 New Jersey Ave SE on the upcoming holiday, Columbus Indigenous Peoples' Day, Monday, October 12th, 2020. Operations would include above grade concrete and mechanical, electrical and plumbing rough-in and exterior facade (Masonry, Glass & Glazing) activities with access limited to N Street. This permit would not include extended work hours beyond the normal 7am...
125 O ST SE   
09/23/20 
DISTRICT OF COLUMBIA / CHRISTOPHER J QUINN-BEAN; NA
B1903205 / CONSTRUCTION
Reinstate heating and ventilation systems at DC Water's O Street Pumping Station. Replace five fans and associated louvers, ducts, accessories and controls. Install louvers in existing openings. Infill floor plates with concrete. Replace lighting in the Stormwater Wet Well. Relocate selected controls for the odor control system. 125 O Street SE
   
10/02/20 
DISTRICT OF COLUMBIA / null
M2100033 / SUPPLEMENTAL
79 POTOMAC AVE SE APT 945   
09/18/20 
null / NA NA NA
EHOP20918703 / HOME OCCUPATION
227 TINGEY ST SE   
09/30/20 
FC 227, LLC / BRIAN QUINN
B2011139 / CONSTRUCTION
Conversion of apartment unit to model unit.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.