I finally got my lazy self over to 11th Street with my camera this past weekend, and got quite the view of the soon-to-arrive Southeast Blvd., the reconstituted road between Barney Circle and 11th Street that runs along the path of the old sunken east end of the Southeast Freeway.
A kind official, taking a wild guess at who that old lady shooting photos of construction might possibly be, guided me in for a quick peek over the crest of the hill, eastward toward Barney Circle:
The new road will be two lanes in each direction, separated by a fair amount of non-road area, as you can see. At the new signalized intersection with 11th Street, the lanes align with the new ramps to and from the Southeast Freeway. Here's what the approach to 11th Street looked like in 2012, when the freeway still ran beneath 11th, along with the similar-but-higher-up view now. (Click to enlarge, and use the massive freeway pylons and flyover to orient yourself, especially in terms of the vertical change.)
As I have written about previously, there has been a fair amount of consternation over this road, both in terms of what some people feel is a rush to get it reopened along with much unhappiness when DDOT unveiled its initial concepts for the road's long-term design. The Office of Planning has since been working on a new set of designs to better meet a goal of reintegrating this area with the surrounding neighborhood, and last week there was a public meeting to go over these concepts, seen below and laid out in detail in the presentation slides.
When comparing these concepts to the road about to open, you can see that the general layout of the traffic lanes and available space are the same, though Concept B has just one lane in each direction just one new two-lane boulevard heading eastward while A and C have two lanes in each direction (UPDATED to fix how B is characterized). (And bike lanes! There are bike lanes!) However, all three would build up the boulevard so that it would become level with L Street, and would then allow 13th, 14th, and 15th streets to intersect with the boulevard for both vehicular and pedestrian traffic.
At right is a side view showing the proposed elevation for Concept A, running from L Street at left over to the train tracks and then down to the river.The CSX train tracks that run to the right of the road's footprints prevent further connection of these streets to M Street and the river, but there could be pedestrian bridges built to bring people across the tracks. (Note that all three concepts show the position of the planned 1333 M Street residential project just south of the boulevard.)
Two of the designs call for development within the huge median, either of low-rise multi-family buildings or townhouses or some combination thereof (at right is a rendering of the Concept A vision). The third design leaves it as a wide-open park space. And two of the three plans show the parking beneath the boulevard for buses that seems to be a requirement from DDOT's point of view.
I'm not going to go into great detail about what was said at the meeting--you can browse the presentation slides and read Capitol Hill Corner's report, which includes the many concerns of nearby residents, especially the ones who don't have much interest in connecting L, 13th, 14th, and 15th to this road.
At this stage, these truly are just concepts. There would next need to be a feasibility study/traffic flow analysis done by DDOT, an undertaking that has no timetable. There is also the issue of this land having been turned over to the city by the feds with the requirement that it be used for "transportation purposes," which raises questions about whether plopping residential buildings in the middle of it all would be an issue.
In the meantime, the new version of this road should open early in 2015.
Here's one more before-and-almost-after, looking eastward from down in the depths back in 2012 (left) and then an expanded version of the current view. Use the apartment building and retaining wall at left to orient. The embankment in the median in the "before" photo is the remnant of the ramps from the old 11th Street Bridges to and from RFK.
Comments (6)
   
 
 More About Traffic Issues

JDLand.com Home

Comments

E. Masquinongy says: (12/17/14 10:31 AM)
Awesome writeup, JD. Many thanks.


JD says: (12/17/14 10:48 AM)
Shoot, I meant to include a photo I took on Sunday from 12th and M, where you can see the difference in elevation between the new SE Blvd and the train tracks. This is the tiny version--I'll dig out a larger cropped version tonight:

link


Gamble Rogers says: (12/17/14 11:59 AM)
Totally agree with E. Masquinongy -- thanks for the great summary and links, JD. It's too bad that DDOT quietly moved ahead with plans for the freeway reopening without first completing the planning process. If DDOT started the process when they closed the old SE Freeway, the contractor could be building it now.

Any word on whether Charles Allen is interested in this issue? Based on DDOT's track record, I doubt this will move unless Allen keeps the pressure on.


JD says: (12/17/14 12:02 PM)
I said this on Twitter a little while ago--I wouldn't be surprised if this has a hard time moving forward until some developer eyes that big chunk of available land in the median and gets interested in building on it. Then people will be astonished at how fast it moves. :-)



202_cyclist says: (12/17/14 3:38 PM)
I support Concepts A and B because DC desperately needs more housing. Additionally, both Concepts A and B would help improve the feasibility of the 11th Street pedestrian bridge proposal by having more residents and activity nearby, rather than having the bridge isolated as it is now.

There are so many different moving parts to this. How would redeveloping the RFK site affect this? If done proprerly, we can have a really great section of waterfront from the Wharf development in Southwest all of the way to RFK and Kingman Island.


E. Masquinongy says: (12/18/14 10:02 AM)
All three plans show the rehabilitation of Barney Circle, reconnecting it to L Street (I think that is what it is) behind Congressional Cemetery. The new circle will interrupt straight-shot Pennsylvania Avenue that cuts through there now.

Is that really going to happen? Pennsylvania is a major commuter route that backs up pretty bad; I cannot imagine DDOT will do anything to make it worse.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2018!
 Top News
  

NavyYardNittany on Wednesday Om Nom: Someone close to that situation told me last week that Justin has moved to Charl...
jdc on Wednesday Om Nom: re: Justin's, I assume he's renting that space and I imagine the rent has been o...
Ampersand on Wednesday Om Nom: @Packinblackandred - yay!!
JD on Wednesday Om Nom: I haven't heard that, but he's been in that spot for nearly 10 years--he might d...
ColoradoCane on Wednesday Om Nom: I was at Justin's Cafe last night and someone mentioned that Justin might be sel...
Message Board (beta)

Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1100 B/O NEW JERSEY AVE SE   SEX ABUSE
First Degree Sexual Abuse
 04/17/18
400 B/O M ST SE   THEFT
Shoplifting
 04/17/18
100 B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 04/17/18
UNIT B/O N ST SE   ROBBERY  04/14/18
100 B/O I ST SE   THEFT
Theft 2nd Degree (theft From Building)
 04/12/18
UNIT B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 04/12/18
1200 B/O 4TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 04/09/18
150 B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 04/07/18
1000 B/O 3RD ST SE   BURGLARY
Burglary One
 04/07/18
1200 B/O NEW JERSEY AVE SE   ROBBERY
Assault W/i To Commit Robbery (simple Assault)
 04/05/18
UNIT B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 04/01/18
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 03/31/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 03/28/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 03/28/18
300 B/O I ST SE   ASSAULT WITH A DANGEROUS WEAPON  03/25/18
UNIT B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 03/23/18
100 B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 03/23/18
UNIT B/O I ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 03/23/18

Recent Issued Building Permits Archive  
1331 2 ST SE   
04/02/18 
DISTRICT OF COLUMBIA / MARK HARLOW CLIFFORD
SB1800225 / CONSTRUCTION
Application for Well Abandonment Workplan Approval for the abandonment of 8 monitoring wells and 21 inclinometers at the Main Pumping Station site for the DC Water Clean Rivers Project, Division I, installed under Permit Number SB1400419.
1100 2ND PL SE   
04/19/18 
CAPPER CARROLLSBURG VENTURE, LLC / TAMIKA STATON; OTIS
EN1801710 / SHOP DRAWING
Install 1 New G2S 3500LBS @350FPM, Elevator 2; 13 Floors
   
04/19/18 
CAPPER CARROLLSBURG VENTURE, LLC / TAMIKA STATON; OTIS
EN1801712 / SHOP DRAWING
Install 2 New G2S Elevators - 3500LBS@35FPM Elevator 1, 12 Floors
1331 2ND ST SE 20003   
04/05/18 
DC WATER / DAVE LEVINE
AH1800744 / CONSTRUCTION
After Hours work for structure excavation in support of DC Water, Corrman Construction 301-343-5417.
1300 4TH ST SE   
04/17/18 
null / DONNA G GRAHAM
AH1800863 / CONSTRUCTION
WR #3476633-WARD 6-20003-VAETH / BRUNO - PEPCO CREWS WILL BE WORKING THE 1200 - 1300 BLK OF 4TH ST SE - INSTALLING NETWORK TRANSFORMER AND INSTALLING PRIMARY CABLES - STARTING THURSDAY 4 / 19 / 18 UNTIL 5 / 19 / 18 - MONDAY THRU FRIDAYS AT 10PM UNTIL 10AM AND ON SATURDAY AND SUNDAYS FROM 6AM TIL 8PM.
1346 4TH ST SE   
04/10/18 
ALAN OWINGS / ROBERT HENRY
AH1800796 / CONSTRUCTION
After Hours Permit for 04 / 16 / 18 from 9AM to 7PM to perform facade, interior unit framing and drywall work, and interior Mechanical, Electrical, Plumbing and Sprinkler Rough-In.
1346 4TH ST ST SE 20003   
03/28/18 
FOREST CITY / TYLER D BARRON
AH1800712 / CONSTRUCTION
After hours for 4 / 13 / 18 to 5 / 12 / 18. Work that is to be done is quiet work of window deliveries at 5:30AM to 7:00AM by use of tower crane
82 I ST SE   
04/02/18 
GDVC EYE STREET LLC / null
FB1800055 / SUPPLEMENTAL
150 I ST SE   
03/28/18 
null
E1805313 / SUPPLEMENTAL
   
03/29/18 
null / JOHN THOMSON 3018645080
E1805337 / SUPPLEMENTAL
300 M ST SE 400   
04/09/18 
FEDERAL CENTER LP / null
M1801970 / SUPPLEMENTAL
300 M ST SE STE# 400 20024   
04/05/18 
CHARLES SMITH / EUGENE AHNS 3012811497
E1805597 / SUPPLEMENTAL
300 M ST SE STE# 400   
04/12/18 
FEDERAL CENTER LP / null
P1805161 / SUPPLEMENTAL
140 M ST SE   
03/26/18 
SQUARE 742 LLC / null
P1804630 / SUPPLEMENTAL
300 M ST SE   
03/26/18 
FEDERAL CENTER LP / JERRY BETHEA
M1801846 / SUPPLEMENTAL
401 M ST SE   
04/03/18 
TETRA TECH C/O DOEE / JESSICA REICHARD
AH1800767 / CONSTRUCTION
After hours permit for manhole access to complete inspections for DOEE Anacosta River Sediment clean up project, work hours between 7pm and 7am Monday thru Friday. Rolling work zones for all manhole access under permit # PA10374319-R1
800 NEW JERSEY AVE SE   
04/05/18 
SQUARE 737 LLC / null
P1804974 / SUPPLEMENTAL
   
04/09/18 
SQUARE 737 LLC / null
E1805700 / SUPPLEMENTAL
861 NEW JERSEY AVE SE   
04/02/18 
CONSOLIDATED RAIL CORPORATION / NA CSX TRANSPORTATION, INC.
AH1800715 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities.
   
04/11/18 
CONSOLIDATED RAIL CORPORATION / DEVIN MURDOCK
SB1800265 / CONSTRUCTION
Drill 8 borings to 40ft. Convert 4 borings into 1" temporary wells, collect groundwater from each well and abandon borings.
1100 NEW JERSEY AVE SE   
04/18/18 
null
E1805988 / SUPPLEMENTAL
1115 NEW JERSEY AVE SE   
04/17/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / GARY BRENT; BRENT
SG1800260 / CONSTRUCTION
Install 1 illuminated wall sign, 1 illuminated window sign and 1 window vinyl decal sign - Peets Coffee
1100 NEW JERSEY AVE SE 5TH FL   
04/19/18 
SQUARE 742 LLC / DOMINIC E TOTARO 301-725-1998
M1802089 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
04/13/18 
SQUARE 742 LLC / CLIFFORD DIXON
B1804348 / CONSTRUCTION
INTERIOR RENOVATIONS TO OFFICE SPACE ON THE 5TH FLOOR. **DEMOLITION, LEVEL 2 ALTERATION
   
04/19/18 
SQUARE 742 LLC / PEDRO C. CASTILLO 3019219056
E1806025 / SUPPLEMENTAL
   
04/19/18 
SQUARE 742 LLC / null
E1806015 / SUPPLEMENTAL
1115 NEW JERSEY AVE SE   
04/06/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / ACCUPERMIT LLC AS AGENT
B1803009 / CONSTRUCTION
Interior alterations for new tenant in existing commercial space to include partitions, mill work, electrical and plumbing fixtures, flooring and wall coverings, dining area furniture and kitchen equipment for a A-2 restaurant with 49 proposed occupancy.
125 O ST SE   
03/29/18 
DISTRICT OF COLUMBIA / JAMES M. HALLER
P1804624 / SUPPLEMENTAL
   
04/09/18 
DISTRICT OF COLUMBIA / TAMIKA STATON; OTIS
EN1801762 / SHOP DRAWING
I New G2S Elevator - 3500LBS @ 200FPM (7 Floors)
   
04/09/18 
DISTRICT OF COLUMBIA / TAMIKA STATON; OTIS
EN1801763 / SHOP DRAWING
Install 1 New G2S Elevator - 3500LBS @ 200FPM (6 Floors)
   
04/09/18 
DISTRICT OF COLUMBIA / TAMIKA STATON; OTIS
EN1801761 / SHOP DRAWING
Install 1 New G2S Elevators 4000LBS @ 200FPM (7 Floors)
71 POTOMAC AVE SE 20002   
04/19/18 
null / STEVE GRIFFIN
BP1802939 / POST CARD
71 POTOMAC AVE SE   
03/26/18 
FORIDA ROCK PROPERTIES INC / null
BCIV1800074 / CONSTRUCTION
This permit is for rough grading and erosion and sediment control civil work associated with the temporary parking lot, relocation of the dog park and construction staging area on the undeveloped portion of the lot.
   
04/17/18 
RIVERFRONT HOLDINGS I LLC / JUSTIN BELLOW
FD1800020 / CONSTRUCTION
Foundation only for new residential building
227 TINGEY ST SE   
03/28/18 
UNITED STATES OF AMERICA / ERICKA CLARK
AH1800760 / CONSTRUCTION
significant concrete pours and tower crane erection 5AM - 7AM and 7PM - 10:00PM
   
04/12/18 
UNITED STATES OF AMERICA / STEPHEN J. EXELBERT
P1805022 / SUPPLEMENTAL
300 TINGEY ST SE   
04/12/18 
MERCURY LLC / WILL TEASS
B1803433 / CONSTRUCTION
INTERIOR FIT-OUT / EXTENSION OF EXISTING TENANT SUITE (APPROVED UNDER B1605215) INCLUDING NEW MECHANICAL AND ELECTRICAL WORK. **LEVEL 2 ALTERATION
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.