Earlier this month, the team developing a planned mixed-income apartment building that is part of the Capper/Carollsburg redevelopment was one of 18 awardees named to share a $142 million pot* helping to fund affordable housing units in the city.
The building, as yet unnamed and generally just referred to by some variation of the oh-so-attractive "Square 769N Residential" moniker, is planned for the northern part of the block bounded by 2nd Place, 3rd, L, and M, next door to the recently discussed 250 M Street office building. It will be 11 stories, and will include 34 units of public housing in its 171 rental units. There will also be about 4,100 square feet of ground-floor retail. (The above image shows the block as seen from Canal Park, with the apartment building at left and 250 M at right.)
This funding is not enough to get the building's construction jump-started, but a) it's better than no funding at all and b) it probably helps move the process toward full funding forward.
It has already spent plenty of time in Zoning Land, having received its second-stage PUD approval back in 2009 followed by time extensions in 2011 and 2013.
This is one of four** large mixed-income apartment buildings still to be built as part of Capper's redevelopment, with two more planned for the other blocks along the east side of Canal Park plus one on the old trash transfer site at New Jersey and K.
* For sticklers, this award is part of the 2014 Notice of Funding Availability (NOFA) awards from the Housing Production Trust Fund.
** It could be five, since the Housing Authority is looking at splitting some units out from one planned mixed-income rental building (not this one!) into a second market-rate condo building. But there has been no public indication of movement one way or the other on that, and a planned Zoning hearing this fall has been pushed back to at least early 2015.
Comments (4)
   
 
 More About Capper New Apt Bldgs

JDLand.com Home

Comments

ZoolanderANDtheBoYz says: (10/24/14 1:58 PM)
It sounds like they won't start construction till 2020.

Off the topic. When the hell will DC water move the heck out from the future movie theater?


JD says: (10/24/14 2:27 PM)
There's a meeting coming on Nov. 20 for public comment on whether the city should declare that part of DC Water as "surplus property."

From the announcement (and I am planning to write more about this as the meeting gets a bit closer):

"Declaring a property surplus means that it is not required for a future public purpose; although in this case, such declaration will be conditioned on DC Water identifying, acquiring and relocating to suitable relocation site(s) as well as approval by an independent engineer of DC Water's operational plan during and after relocation."


202_cyclist says: (10/24/14 5:03 PM)
Perhaps not the most exciting news but there are new parking meters that have been installed on L St SE, between 2nd - 3rd St SE (they are at least new to me, since I never realized there were meters on this street).


JD says: (10/24/14 5:13 PM)
They are indeed new.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

CJBabyDaddy on Roundup of Some: @WestNorth: Methinks the proposed land swap involves/involved Navy Yard waterfr...
conngs0 on Roundup of Some: Cool news about the museum. It'll be interesting to see how it progresses from ...
Westnorth on Roundup of Some: Navy Museum is fundraising for a $450M new spot outside the Navy Yard gates, for...
VelocityChris on Roundup of Some: They're adding two floors to the top of the WeWork building.
GarfieldPark on Roundup of Some: Anyone know what is happening on First st outside of WeWork bldg? They are doing...
right-toe on Roundup of Some: Lots of little changes around: Sidewalk has opened up around the DDOT building,... [image]
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1200 B/O HALF ST SE   ROBBERY  10/21/20
UNIT B/O K ST SE   THEFT
Theft First Degree (all Other Larceny)
 10/20/20
900 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/15/20
600 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 10/13/20
UNIT B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/12/20
1000 B/O 1ST ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 10/12/20
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/09/20
1000 B/O 8TH ST SE   ROBBERY
Armed Carjacking
 10/09/20
400 B/O M ST SE   THEFT
Theft 2nd Degree - Felony (theft From Building)
 10/07/20
900 B/O M ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 10/01/20
1000 B/O 3RD ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 09/30/20
UNIT B/O K ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 09/29/20
1100 B/O 2ND PLACE SE   ROBBERY
Assault W/i To Commit Robbery (simple Assault)
 09/28/20
1000 B/O 4TH ST SE   ROBBERY
Carjacking
 09/26/20
1200 B/O HALF ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 09/22/20
600 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/21/20

Recent Issued Building Permits Archive  
1108 3RD ST SE   
10/06/20 
JULIANA DUFFY / null
E2100156 / SUPPLEMENTAL
915 5TH ST SE   
10/14/20 
RYAN DANIELS / FERNANDO A ANGULO; RYAN DANIELS
B2012669 / CONSTRUCTION
Partial floor joists replacement on first floor. replace 6 feet height wooden fence and gate. add protective coating to partial foundation wall.
1031 5TH ST SE   
09/30/20 
CLARICE GEE / null
P2009304 / SUPPLEMENTAL
150 I ST SE   
10/09/20 
SQUARE 737 LLC / JASON D DORRIS
AH2100047 / CONSTRUCTION
Construction of a new 13 story apartment building with three below grade parking levels, 1st floor retail and amenity areas; 373 units and 181 parking spaces. To include mechanical, electrical, plumbing, elevators and structural work.
   
10/15/20 
SQUARE 737 LLC / BOB BIROONAK; BOB BIROONAK
SG2000458 / CONSTRUCTION
one directional double face non illuminated sign
100 M ST SE   
09/25/20 
LHREV WASHINGTON M STREET LLC / THUY LE; NA
B2010745 / CONSTRUCTION
Suite 950 - Interior alteration. Work is to include minor change in MEP and Fire. No Structure.
139 N ST SE   
10/08/20 
null
SH2000028-EXT-1 / CONSTRUCTION
Original Permit expires 4 / 15 / 2021, 1st extension expires 10 / 15 / 2021
861 NEW JERSEY AVE SE   
10/13/20 
CXS TRANSPORTATION INC / null
P2100338 / SUPPLEMENTAL
125 O ST SE   
10/02/20 
DISTRICT OF COLUMBIA / null
M2100033 / SUPPLEMENTAL
71 POTOMAC AVE SE   
10/15/20 
RIVERFRONT HOLDINGS II, LLC / OLUSOLA PYNE
B2100519 / CONSTRUCTION
Shipping Container placement on lot for exterior use.
227 TINGEY ST SE   
09/30/20 
FC 227, LLC / BRIAN QUINN
B2011139 / CONSTRUCTION
Conversion of apartment unit to model unit.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.