The second public meeting about the Virginia Avenue Tunnel Final Environmental Impact Statement has now been scheduled for 6:30 pm on Thursday, July 31, at the Capitol Skyline hotel at South Capitol and I streets, SW.
The release from the tunnel folks says that this meeting "will include a presentation responsive to input by citizens from the public meeting held on July 1, 2014 with a question and answer period focused on the July 1 input."
This is the additional meeting sought by DC delegate Eleanor Holmes Norton, along with the extension of the comment period from 30 to 60 days.
The official web site has the presentation and boards from the July 1 meeting.
I already posted the video animation released to show how the construction would go, and now I see this additional video showing the completed east and west portals (entrances) to the tunnel, along with how Virginia Avenue is expected to look after construction is finished.
Comments (4)
   
 
 More About CSX/Virginia Ave. Tunnel

JDLand.com Home

Comments

MJM says: (7/16/14 2:59 PM)
Got people going the wrong way on the 4th but the biggest difference and probably to scale are the new trees. Really hope they can put the biggest trees to replace those current shade trees along Va Ave.


4thStNeighbor says: (7/22/14 11:51 AM)
So I street will now have two-way traffic, 5th will go all the way through, and 4th will be two-way traffic? Or was the person who made the video unfamiliar with the current traffic patterns?


JD says: (7/22/14 11:56 AM)
I do know that many years ago, when 4th was switched to one-way southbound, that DDOT told me it was eventually supposed to become two-way again. But these would be good questions for the July 31 meeting!

(Though I is already two way, and 5th already goes all the way through?)


crzy4fishy says: (8/11/14 12:29 PM)
We are brand new to 5th Street, and so of course we are only just now learning what CSX has planned. Has there already been discussion about:
1) The fact that I may have commuter traffic routed through the alleyway behind my house (or so I gather from the first video)?
2) Any chance in the world of CSX providing some sort of compensation to go pay for parking in a hotel garage while they get rid of parking for everyone nearby?
I saw that only the 'facing' residents will receive the monthly compensation, but since we are pretty much brand new to the topic, I was hoping for some information. I'm sure that this has been covered somehow, somewhere, and I doubt I will like the answer, but I wanted to ask! Thanks in advance!

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

dcgent on I'm Dreaming of: I posted the link partly because I'm a Detroiter. Folks in SE are championing De...
jdc on I'm Dreaming of: Love the grandma slices at Wise Guys. And being from MI too, I also love Buddy's...
VelocityChris on I'm Dreaming of: The description and picture of the Detroit-style pizza sounds/looks just like th...
JD on I'm Dreaming of: Longtime readers may remember the many trips with Mr JDLand to Michigan, where h...
dcgent on I'm Dreaming of: Detroit-style pizza coming to undisclosed navy yard location https://dc.eater.c...
Westnorth on I'm Dreaming of: XO sauce is fish-based, as with many Cantonese sauces: https://en.wikipedia.org/...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
No records added or modified in the past two weeks.

Recent Issued Building Permits Archive  
1402 1ST ST SE   
11/25/19 
UNITED STATES OF AMERICA / DAVID C POSTLEWAITE
SB1900412 / CONSTRUCTION
Parcel G2:WSP will complete four borings up to the deepest potential subgrade elevation (approx. 32 ft. bgs). The proposed boring locations would be in the four quadrants of Parcel G2 to check for spatial variability in contaminant concentrations. WSP will collect and analyze three soil samples from each boring from depths corresponding to potential subgrade elevations (i.e. 10-12 ft. bgs, 20-22 ...
1212 4TH ST SE   
11/25/19 
FC 1212 LLC / TAMIKA STATON; OTIS
ER2000409 / SHOP DRAWING
Replace governor car #2 - Part #: TBA20641H6 Replace hoist belts #1 and #4 - Part #: SB0003119
1300 4TH ST SE   
11/15/19 
ASANA PARTNERS / DEBRA MARSHALL; THE DONOHOE COMPANIES INC
B2001773 / CONSTRUCTION
ADD EXTERIOR DOOR, ADD INTERIOR DOOR , ANY RELAYED,ELECTRICAL,PLUMBING, RELOCATING UNBUILT APPROVED NON LOAD BEARING FIRE RATED PARTITIONS @ FIRST FLOOR APPROVED UNDER PERMIT #B1711970. ATTACHED
   
12/06/19 
ASANA PARTNERS / S.A. COMUNALE; S.A. COMUNALE
P2001954 / SUPPLEMENTAL
1346 4TH ST SE   
12/06/19 
KAITLYNN MATTEO / W. SAKIE - BHAR; W. SAKIE - BHAR; NA
SG2000117 / CONSTRUCTION
Install one set of non illuminated sign on to existing store front building
861 NEW JERSEY AVE SE   
11/15/19 
CSX TRANSPORTATION INC / ERICKA CLARK; DGS CONSTRUCTION
TC2000008 / CONSTRUCTION
(2) tower cranes
   
11/26/19 
GREYSTAR GP I I, LLC / KIM MITCHELL; KIM MITCHELL
FD1900040 / CONSTRUCTION
TWO BELOW GRADE PRKING LEVELS, CONCRETE FOUNDATION WALLS, SLAB ON GRADE, COLUMNS ELEVATED DECKS UP TO GRADE WITH UNDERGROUND UTILITIES (MECHANICAL, PLUMBING, ELECTRICAL)
   
12/05/19 
MIKE ALLEN / JANE MCCRAY
AH2000244 / CONSTRUCTION
WO# 1611441 - Mike Allen / P. Helgeson. Pepco to install network transformer
1111 NEW JERSEY AVE SE   
11/15/19 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / TANYA HILL; THYSSENKRUPP
ER2000366 / SHOP DRAWING
REPLACE EXISTING 8MM WORN HOIST CABLES WITH LIKE IN KIND ON ELEVATOR #4. WORK TO ALLOW UNIT TO BE RETURNED TO SERVICE.
1299 NEW JERSEY AVE SE   
11/12/19 
BROOKFIELD DEVELOPMENT / JUSTIN BELLOW
BP2000489 / POST CARD
125 O ST SE   
11/25/19 
DISTRICT OF COLUMBIA / DAVID C POSTLEWAITE
SB1900411 / CONSTRUCTION
WSP will complete three borings up to the deepest potential subgrade elevation (approx. 32 ft. bgs). WSP assumes that borings will not be installed inside the fleet maintenance facility due to access restrictions imposed by DC Water. The proposed boring locations form an ā€˜Lā€™ shape around the eastern and southern sides of the fleet maintenance facility. WSP will collect and analyze three soil samp...
71 POTOMAC AVE SE   
12/06/19 
MPR REALTY / BOB BIROONAK; BOB BIROONAK; ART DISPLAY CO
SG2000099 / CONSTRUCTION
One building name MAREN Two set of address numbers all signs are non-illuminated
201 TINGEY ST SE   
11/14/19 
BROOKFIELD PROPERTIES / DFM DEVELOPMENT SERVICES, LLC
AH2000197 / CONSTRUCTION
Afterhours work at Tingey Square Project. The work performed will be forming, prepping and paving at Tingey Square park. Friday and Saturday the 15th & 16th, from 7PM to midnight. If required, Sunday the 17th from 7AM to 3PM. ANC Support provided. Associated Permit Include PA328164-R1 and PA10760162.
227 TINGEY ST SE   
12/02/19 
FC 227 LLC / KAYLA SHATTUCK; BROOKFIELD PROPERTIES MANAGEMENT LLC.
RW1900122 / CONSTRUCTION
Construction of new retaining wall located between Canal Street St and Third Street, SE.
300 TINGEY ST SE   
12/04/19 
FC BOILERMAKER LLC / ROBERT S. WATTS; ROBERT S. WATTS
E2002289 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2019 JD.