On Sunday I ventured out for a long overdue survey of the 11th Street Bridges project. While I know that pictures of ramps and flyovers don't elicit quite the swooning that images of new residential buildings do, the changes at street level and above since this project began in 2009 are as wide-ranging as anything else in the area short of probably Nationals Park. Here's what I saw (click on photos to embiggen):
On 8th Street just north of Virginia Avenue, the new ramp to outbound I-695 (aka the 11th Street freeway bridge) looks pretty far along, as seen at right. This ramp has an "early spring" projected opening, and it doesn't appear to be too in danger of missing that.
The lanes to the left of this new freeway entrance carry the outbound I-695 traffic, while the ramp to the right that used to lead to the old outbound flyover and bridge will now be the new exit from the freeway to an intersection at 11th Street SE north of L. You can also see this new exit ramp from 8th and Virginia (below left), running next the footprint of the now-demolished old entrance ramp. The 11th Street interchange still has a ways to go (below right), but is projected to open in early summer.
I also finally checked out 12th Street, which no longer lives quite so deeply in the shadow of the ramp from the old inbound 11th Street Bridge to M Street. The in-water piers of the old bridge are still standing, as you see at left, but otherwise the ramp's footprint has been cleared. (I kind of miss the staircase, though.)
The 12th and O intersection still needs a lot of love even with the embankment gone, but it's at least somewhat less apocalyptic now (below left)--and it will be seeing more traffic with M Street east of 13th temporarily closed, which has also moved the Anacostia Riverwalk Trail route onto its "real" Water Street path. Meanwhile, one block to the north, there's about to be an actual intersection with N Street (below right), allowing for traffic to access 11th Street in either direction without having to go up to M. (You can see the rest of the new 12th and N angles and how they've changed, too.)
So many of the new 11th Street Bridges movements are finished--the bridges themselves, the new inbound and outbound flyovers, the two-way traffic up 11th Street from the local bridge, and the on- and off-ramps at M Street. This also means that the centipede-like old inbound flyover seen in the two photos below can now be demolished like three others before it (the RFK ramps and the outbound flyover), for one final change to the skyline above 11th Street.
It's pretty hard to pull together these changes into a single page, so if you really want to get a feeling for the progression over the past four-plus years, I'd dive into these parts of my photo archive:
* 12th and M, especially looking north and northwest;
* 11th and N, looking north and south; and
I know, it's exhausting. But for someone enamored of striking before-and-after shots, it's a goldmine.
Comments (11)
   
 
 More Recent News

JDLand.com Home

Comments

E. Masquinongy says: (3/10/14 12:16 PM)
JD: The exit ramp ending at 11th and L should help shunt traffic away from the 6th St exit, in the impending train tunnel work. My understanding during the train tunnel reconstruction, is that cars exiting on 6th St will be directed north, into neighborhood. The new exit will relieve some of this traffic pressure.


JD says: (3/10/14 12:19 PM)
Yes, on all counts.

And the new ramp really should be an improved way for Navy Yard commuters coming from the west, instead of getting off at 6th and Virginia and winding around to 11th and N or O.

Not to mention a nice new way for folks who live closer to 11th Street to get home, rather than via 6th.



MJM says: (3/10/14 12:51 PM)
The on-ramp onto the outbound leg at 8th looks like a confusing intersection with the light since it is offset from the light/intersection. I hope someone thought about what that intersection is gonna look like once it opens.


JD says: (3/10/14 1:02 PM)
(And I'm realizing that it needs to be mentioned again that one of the other impressive portions of this project is how this new ramp to 11th Street is being built on the massive piles of dirt that have filled in what used to be the west half of the sunken freeway. Eleventh Street itself isn't a bridge anymore!)


E. Masquinongy says: (3/11/14 9:46 AM)
JD: Any word when the 11th Street northbound lanes will reopen? They have been closed for like a year.


JD says: (3/11/14 3:16 PM)
Do you mean those lanes under the new freeway flyovers? I haven't heard a thing on them. If I were to go with 100% conjecture, I would say that DDOT/Skanska are trying desperately to avoid working on that side of 11th Street until they know what the plan is for SE Blvd. And given the level of opposition that the proposals unveiled a few months ago seem to have engendered, that might be a while.


Gamble Rogers says: (3/11/14 10:29 PM)
Look, I'm tired of all this proposed destruction. Everyone living within 500 yards of the old flyover bridge will be subjected to endless noise, increased traffic, and concrete dust for months. Months! I wanna know -- what's in it for me? I call on city fathers to support the "no demo!" plan now!


JD says: (3/11/14 10:43 PM)
Maybe they could just extend the Bridge Park onto this flyover.


Gamble Rogers says: (3/11/14 10:43 PM)
Seriously, MJM hit the nail on the head -- the new 8th Street ramp to eastbound I-695 (can't we just agree to call it "Southeast Freeway?") will be great for commuters but bad for pedestrians.

If a pedestrian is walking on the east sidewalk of Eighth Street by that ramp, they better stop and look behind them before crossing the walkway. Commuters love to haul you-know-what under the bridge. With a new highway ramp, it's doubtful commuters will look carefully for pedestrians before hitting the gas. So be careful out there!

One more thing: Virginia Avenue Dog Park fans should ask if the park will be expanded once the 11th Street ramp is built. The 11th Street exit ramp will supposedly (based on JD's previous maps) have three or four lanes onto 11th Street -- one to turn north, one to turn south, and perhaps two to drive straight onto the not-yet-built Southeast Boulevard. Even with three lanes, the park should extend all the way to 11th Street, which would give pups more room to roam. Right now, all the bridge workers park on a dirt lot. But will DDOT/NPS/DPR expand the park once the ramp is built?


E. Masquinongy says: (3/12/14 12:14 PM)
JD: yes, we are all waiting for some decisions on SE blvd. The first proposal was DOA, for good reason. Thanks for all your good work!


JD says: (3/14/14 11:47 AM)
No time is being wasted on getting rid of the old inbound flyover--there are lane closures on that stretch of 11th between K and M this weekend: "Temporarily narrowing the roadway will allow crews to begin demolition of the existing inbound bridge structure over 11th Street SE."

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Top News

kalicki on A Photo Tour: I generally like the style of this building, but man, the white lights on the fa...
conngs0 on A Photo Tour: Whoops! I don't know how I jumped to full replacement! Sorry! Regardless, kee...
JD on A Photo Tour: Not a hip replacement! Had to have the torn labrum repaired and the head of the ...
conngs0 on A Photo Tour: Thanks for the update, JD! I know you've been waiting for a cell phone store fo...
Message Board (beta)

  
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 02/22/18
400 B/O M ST SE   THEFT
Shoplifting
 02/21/18
UNIT B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 02/19/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/15/18
1000 B/O 3RD ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/07/18

Recent Issued Building Permits Archive  
1100 2ND PL SE   
02/21/18 
BAKER DC / CHRISTINE LONG
AH1800618 / CONSTRUCTION
An after hours permit is respectfully requested from 5AM to 9PM daily
1331 2ND ST SE 20003   
01/29/18 
DC WATER / DAVE LEVINE
AH1800505 / CONSTRUCTION
After hours work for structure exaction and support for B1311474 DC Water. Corman Construction 202-863-0052.
1016 3RD ST SE   
02/01/18 
ANAMARIA R MOTTOLA / DAVID L. HAHN
P1803348 / SUPPLEMENTAL
1346 4TH ST SE   
02/06/18 
ALAN OWINGS / ROBERT SEV HENRY
AH1800541 / CONSTRUCTION
After Hours Permit for 2 / 19 / 18 from 7AM to 7PM to perform concrete, framing, and utility operations.
   
02/06/18 
FC 1346 LLC / RICHARD V CAREY
P1803428 / SUPPLEMENTAL
150 I ST SE   
02/05/18 
WC SMITH / null
P1803402 / SUPPLEMENTAL
140 M ST SE   
02/07/18 
SPAULDING & SLYE/STE100 / null
E1803798 / SUPPLEMENTAL
110 M ST SE   
01/29/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / JAMES WEAVER
E1803534 / SUPPLEMENTAL
   
02/02/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
P1803361 / SUPPLEMENTAL
140 M ST SE 20032   
02/14/18 
SYLVIA LINDSEY / null
P1803641 / SUPPLEMENTAL
202 M ST SE   
01/29/18 
UNITED STATES OF AMERICA / NURI EROL
D1800281 / CONSTRUCTION
Remove Existing flooring. Remove some of the furnitures, equipment.
300 M ST SE 53533   
02/08/18 
FEDERAL CENTER LP / SPENCER TEEL
BP1801893 / POST CARD
300 M ST SE   
02/16/18 
FEDERAL CENTER LP / STEVEN MERCHANT
B1803279 / CONSTRUCTION
New Sprint store sustainable design tenant build-out in an existing building, partical first floor. Work will consist of building a new sales floor and back of the house. New work sill consist of display fixtures, ceiling, plumbing fixtures, mechanical ductwork to diffusers, interior partitions, floor finishes, outlets and new locations of electrical panels. **CHANGE IN USE, LEVEL 2 ALTERATION
401 M ST SE   
01/30/18 
DOEE C/O DEV MURALI / JESSICA REICHARD
AH1800507 / CONSTRUCTION
After hours permit to preform manhole inspections during off peak hours 7pm - 7am for all Manhole Locations covered under permit # PA10374319-R1 for DOEE Anacostia river sediment project.
861 NEW JERSEY AVE SE   
01/31/18 
CONSOLIDATED RAIL CORPORATION / NA CSX TRANSPORTATION, INC.
AH1800467 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities.***TO EXCLUDE LEGAL HOLIDAYS**
1100 NEW JERSEY AVE SE 2ND FL   
02/09/18 
SQUARE 742 LLC / null
P1803534 / SUPPLEMENTAL
   
02/14/18 
SQUARE 742 LLC / null
P1803681 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
02/15/18 
SQUARE 742 LLC / null
E1804057 / SUPPLEMENTAL
79 POTOMAC AVE SE   
02/21/18 
RIVERFRONT HOLDINGS I LLC / JUSTIN BELLOW
B1805358 / CONSTRUCTION
Address revision only for B1702971 from 25 Potomac Ave SE to 79 Potomac Ave SE.
640 SOUTH CAPITOL ST SE   
02/05/18 
JIM LATISIS ZAYO GROUP
B1707197 / CONSTRUCTION
Addition to existing concrete telecom building.
401 TINGEY ST SE   
01/30/18 
PEPCO / BARBARA ANN STEDMAN
AH1800520 / CONSTRUCTION
UG TRANSFORMER WORK TO BE PERFORMED ON THE 400 BLK OF TINGEY ST SE. MANHOLE ACCESS. WORK TO BE PERFORMED BETWEEN THE HOURS OF 7:30AM AND MIGHTNIGHT ON 1 / 30 / 18 AND 1 / 31 / 18.
227 TINGEY ST SE   
01/29/18 
UNITED STATES OF AMERICA / ERICKA CLARK
TC1800021 / CONSTRUCTION
2 tower cranes
   
01/30/18 
FOREST CITY WASHINGTON / MELISSA DIAZ
B1802750 / CONSTRUCTION
Revision to Permit SH1700028. Sheeting and shoring for Yards Parcel L-2 project. Revision includes 10-foot precut excavation and layback on Water Street, 3rd Street and northern L-1 elevations, and removal of upper tier of rakers at L-1 elevation and upper tier of tiebacks at the Water Street and 3rd Street elevations.
   
02/20/18 
FOREST CITY WASHINGTON / FOREST CITY WASHINGTON; DFM DEVELOPMENT SERVICES
FD1700057 / CONSTRUCTION
Yards parcel L-2. Construction of foundation and underground parking garage for new 11 story multi-family mixed used residential building at 227 Tingey Street SE as part of development of Parcel L at the Yards
325 VIRGINIA AVE SE 20003   
02/14/18 
JASON W GOLDSMITH / null
E1804039 / SUPPLEMENTAL
325 VIRGINIA AVE SE   
02/06/18 
JASON W GOLDSMITH / CRAIG HARTSOCK
B1804721 / CONSTRUCTION
Remove two non-structural walls on ground level of townhouse and re-frame in new configuration to create a full bathroom on ground floor.
   
02/07/18 
JASON W GOLDSMITH / MORIS O. OCHOA PINEDA
P1803462 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
1001 NEW JERSEY AV SE   12/28/17
$ 687,365
WHATS ON SECOND PROPERTIES LLC
 


Project Directory
Completed
Agora ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.