Last week DDOT announced the four teams that have been chosen to advance to the next round and battle it out for the grand prize of being able to design and build the new Douglass Bridge and its approaches as well as reconstruct the Suitland Parkway/I-295 interchange, a prize package worth at least $608 million.
These four teams will now have the opportunity to respond to DDOT's Request for Proposals on the project, which should be released at some point in the not-too-distant future.
The two reconstruction projects are officially known as Segments 1 and 2 in the two-phase/five-part South Capitol Street Corridor Project, which will also eventually extend the "grand boulevard" feel from a reconfigured M Street intersection north to the Southeast Freeway, build a new on-ramp there, and throw in some streetscape enhancements along New Jersey Avenue as well.
I missed out on a fair amount of discussion of this project last year, including the mayor "announcing the new design" of the bridge that was only marginally different than the design that's been on the boards for a number of years (though the announcement did include a cool video). The announcement was followed by some controversy over the size and necessity of the traffic ovals and even the bridge design itself. (But some cyclists seem okay with it.)
I also didn't get the chance to note that the position of the bridge has undergone some alteration, in that the new bridge's footprint is now designed to run completely parallel to the current bridge, instead of a more diagonal alignment from the original EIS, which you can see compared on pages 11 and 12 of this October 2013 project update.
In the fall, both the National Capital Planning Commission and the Commission of Fine Arts looked at the project, with the latter pooh-poohing the "uninspired" bridge design and calling for a the design-build process to come up with a "more innovative proposal" instead of the Memorial Bridge-like arched bascule design that DDOT has chosen. Both commissions are generally supportive of the two ovals, though NCPC's comments after a November review of the project notes that more discussions of the western oval (just southwest of Nationals Park) "will need to occur to help further the ideas of creating a vibrant destination."
While waiting for the RFP to be released and for the designs of the bridge and the ovals to be "refined" for NCPC/CFA approval, you can check out my Douglass Bridge project page, my South Capitol Street page, and the reams of words I've written about both over the years.
Comments (2)
   
 
 More About Douglass Bridge

JDLand.com Home

Comments

ZoolanderANDtheBoYz says: (2/2/14 11:56 AM)
What's going to happen to the cement factory on Potomac avenue (east of the Oval)?


monkeyrotica says: (2/3/14 11:59 AM)
What's an "inspired" bridge design? Ziplines and a rock climbing wall?
MAYBE NOT!

link

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

CJBabyDaddy on Roundup of Some: @WestNorth: Methinks the proposed land swap involves/involved Navy Yard waterfr...
conngs0 on Roundup of Some: Cool news about the museum. It'll be interesting to see how it progresses from ...
Westnorth on Roundup of Some: Navy Museum is fundraising for a $450M new spot outside the Navy Yard gates, for...
VelocityChris on Roundup of Some: They're adding two floors to the top of the WeWork building.
GarfieldPark on Roundup of Some: Anyone know what is happening on First st outside of WeWork bldg? They are doing...
right-toe on Roundup of Some: Lots of little changes around: Sidewalk has opened up around the DDOT building,... [image]
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
UNIT B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/12/20
1000 B/O 1ST ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 10/12/20
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/09/20
1000 B/O 8TH ST SE   ROBBERY
Armed Carjacking
 10/09/20
400 B/O M ST SE   THEFT
Theft 2nd Degree - Felony (theft From Building)
 10/07/20
900 B/O M ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 10/01/20
1000 B/O 3RD ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 09/30/20
UNIT B/O K ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 09/29/20
1100 B/O 2ND PLACE SE   ROBBERY
Assault W/i To Commit Robbery (simple Assault)
 09/28/20
1000 B/O 4TH ST SE   ROBBERY
Carjacking
 09/26/20
1200 B/O HALF ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 09/22/20
600 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/21/20
1200 B/O VAN ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/19/20
1000 B/O 1ST ST SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 09/16/20
100 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/16/20
200 B/O L ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 09/13/20
1000 B/O 3RD PLACE SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 09/13/20

Recent Issued Building Permits Archive  
1031 5TH ST SE   
09/30/20 
CLARICE GEE / null
P2009304 / SUPPLEMENTAL
100 M ST SE   
09/25/20 
LHREV WASHINGTON M STREET LLC / THUY LE; NA
B2010745 / CONSTRUCTION
Suite 950 - Interior alteration. Work is to include minor change in MEP and Fire. No Structure.
1275 NEW JERSEY AVE SE   
09/18/20 
BROOKFIELD PROPERTIES / TIM GOOD
AH2001915 / CONSTRUCTION
After hours to conduct work on 1275 New Jersey Ave SE on the upcoming holiday, Columbus Indigenous Peoples' Day, Monday, October 12th, 2020. Operations would include above grade concrete and mechanical, electrical and plumbing rough-in and exterior facade (Masonry, Glass & Glazing) activities with access limited to N Street. This permit would not include extended work hours beyond the normal 7am...
125 O ST SE   
09/23/20 
DISTRICT OF COLUMBIA / CHRISTOPHER J QUINN-BEAN; NA
B1903205 / CONSTRUCTION
Reinstate heating and ventilation systems at DC Water's O Street Pumping Station. Replace five fans and associated louvers, ducts, accessories and controls. Install louvers in existing openings. Infill floor plates with concrete. Replace lighting in the Stormwater Wet Well. Relocate selected controls for the odor control system. 125 O Street SE
   
10/02/20 
DISTRICT OF COLUMBIA / null
M2100033 / SUPPLEMENTAL
79 POTOMAC AVE SE APT 945   
09/18/20 
null / NA NA NA
EHOP20918703 / HOME OCCUPATION
227 TINGEY ST SE   
09/30/20 
FC 227, LLC / BRIAN QUINN
B2011139 / CONSTRUCTION
Conversion of apartment unit to model unit.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.