With the currently be-muraled former NGA building at 1st and M Street SE expected to be demolished early in 2014, Forest City Washington is making plans for temporary uses for that block while it works on longer-range plans to build office and retail space on the site, which is at the northwest corner of the Yards footprint.
To that end, the company has filed a request for the Zoning Commission's approval of a temporary (unfenced!) park/open space along M between New Jersey and 1st, as well as the relocation of the Trapeze School from its current location at 4th and Tingey to the northwest corner of New Jersey and N/Tingey.
There would also remain a parking lot on the site, but it would be shifted to just the southwest corner of the block, and would have 208 spaces instead of the 230 currently there. Access to the lot would be from N Street. (At the same time, because of DC Water's ongoing construction, the parking lot immediately to the south across N would be losing 50 spaces, down to 344.)
As you can (kind of) see in the site plan, there would be a path running from northeast to southwest across the park, making for a nice shortcut to the ballpark for fans coming out of the Metro at New Jersey and M. And it would give the four corners of this block a slightly different feel than the current vistas:
The filing says that the Trapeze School needs to be moved not only because the zoning order allowing it to be on its current site expires at the end of 2014, but also because development is planned for that 4th and Tingey site ("Parcel O") to be completed by 2016/2017. It also says that Parcel H, on the southeast corner of 1st and N where the Yards "tent" display and parking lot is, is expected to be developed beginning in 2015, and that an RFP process is currently underway to select an architect. This would be another residential building with street-level retail.
There is no timeline laid out for when this NGA block is expected to be fully developed, though it's always been expected to be part of the final phase of the Yard's planned 10-to-20-year timeline.
UPDATE: Speaking of the be-muraled building and the ArtYards project going on at this block, there will be a "Chalk Art Street Festival" at the site this weekend (Dec. 7 and 8). There will be hot chocolate and treats, along with lots of chalk for kids of all ages to create their own masterpieces on the parking lot.
Comments (3)
   
 
 More About Parcel A/Yards

JDLand.com Home

Comments

Alan says: (12/5/13 10:24 AM)
It's going to be so weird/awesome to come out of the metro and have a completely new view of the horizon.


JES says: (12/5/13 10:43 AM)
Allowing people to cut through that lot/park will provide some nice sidewalk relief on M... those sidewalks are waaaaay too narrow, especially on gameday.


Andrew in DC says: (12/5/13 10:58 AM)
+1 JES

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

keith18 on Wednesday Tidbits: I had a weird experience at Whaley's and never went back. My wife and I ordered ...
202_cyclist on Wednesday Tidbits: Dan— you won the Internet. This is the comment of the year on JD Land!
Dan on Wednesday Tidbits: The Rosé Garden is where one shouts nonsense and confesses to having had too muc...
Edna on Wednesday Tidbits: That would be great if the Ros&eacute garden continues. I always wanted to ...
jsh on Wednesday Tidbits: JDC- Montaditos closed because although their food was better than okay, their ...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1000 B/O 3RD ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 11/01/19
1000 B/O NEW JERSEY AVE SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 11/01/19
UNIT B/O I ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 11/01/19
400 B/O M ST SE   THEFT
Shoplifting
 10/30/19
200 B/O I ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 10/28/19
100 B/O H ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 10/28/19
900 B/O NEW JERSEY AVE SE   ROBBERY  10/28/19
100 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/27/19
300 B/O TINGEY ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/24/19
100 B/O H ST SE   ROBBERY  10/23/19

Recent Issued Building Permits Archive  
1331 2ND ST SE   
11/08/19 
DC WATER / CRAIG M COOK
B1907684 / CONSTRUCTION
Flood mitigation, seal openings, install brackets for stop logs, replace elevator shaft with concrete slab.
1300 4TH ST SE   
11/15/19 
ASANA PARTNERS / DEBRA MARSHALL; THE DONOHOE COMPANIES INC
B2001773 / CONSTRUCTION
ADD EXTERIOR DOOR, ADD INTERIOR DOOR , ANY RELAYED,ELECTRICAL,PLUMBING, RELOCATING UNBUILT APPROVED NON LOAD BEARING FIRE RATED PARTITIONS @ FIRST FLOOR APPROVED UNDER PERMIT #B1711970. ATTACHED
300 M ST SE SPACE B   
11/06/19 
FEDERAL CENTER LP / null
M2000403 / SUPPLEMENTAL
300 M ST SE   
11/06/19 
FEDERAL CENTER LP / RUBEN MOVSISYAN; RUBEN MOVSISYAN
E2001472 / SUPPLEMENTAL
   
11/11/19 
FEDERAL CENTER LP / null
P2001215 / SUPPLEMENTAL
861 NEW JERSEY AVE SE   
11/05/19 
809-853 NEW JERSEY AVENUE ACQUISITION, LLC / JAVIER A GRACIA; NA NA
SB2000011 / CONSTRUCTION
Drilling and installation of 3 inclinometers which will be extended to a depth of 25 below existing site grade as well as the installation of 4 settlement optical monitoring points which will be extended to depths ranging between 5 feet to 30 feet below existing site grades.
   
11/15/19 
CSX TRANSPORTATION INC / ERICKA CLARK; DGS CONSTRUCTION
TC2000008 / CONSTRUCTION
(2) tower cranes
1100 NEW JERSEY AVE SE 1ST   
11/04/19 
SQUARE 742 LLC / JAMES W. LASHER; JAMES W. LASHER
E2001381 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
11/01/19 
SQUARE 742 LLC / ;
P2000952 / SUPPLEMENTAL
   
11/05/19 
SQUARE 742 LLC / BETSY H MARINO; RICHARD PEPPER; BETSY H MARINO
SG2000062 / CONSTRUCTION
Remove Alion sign and replace with illuminated wall sign reading SERCO
1111 NEW JERSEY AVE SE   
11/15/19 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / TANYA HILL; THYSSENKRUPP
ER2000366 / SHOP DRAWING
REPLACE EXISTING 8MM WORN HOIST CABLES WITH LIKE IN KIND ON ELEVATOR #4. WORK TO ALLOW UNIT TO BE RETURNED TO SERVICE.
1299 NEW JERSEY AVE SE   
11/12/19 
BROOKFIELD DEVELOPMENT / JUSTIN BELLOW
BP2000489 / POST CARD
71 POTOMAC AVE SE   
11/08/19 
RIVERFRONT HOLDINGS II, LLC / JAMES VANEGAS
AH2000075 / CONSTRUCTION
Perform interior and exterior construction activities. New construction 14-story new residential multi-family building.
201 TINGEY ST SE   
11/14/19 
BROOKFIELD PROPERTIES / DFM DEVELOPMENT SERVICES, LLC
AH2000197 / CONSTRUCTION
Afterhours work at Tingey Square Project. The work performed will be forming, prepping and paving at Tingey Square park. Friday and Saturday the 15th & 16th, from 7PM to midnight. If required, Sunday the 17th from 7AM to 3PM. ANC Support provided. Associated Permit Include PA328164-R1 and PA10760162.
520 TINGEY ST SE   
10/30/19 
UNITED STATES OF AMERICA / JOHN WICKLIFFE; TBD
TN2000020 / CONSTRUCTION
Install 100ft x 90ft Tent No Cooking, No Propane, No Stages, No Smoking Installed Feb 9, 2020 - Aug 4, 2020 Events Daily 8:00 am - 10:00 pm
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2019 JD.