Since January, 2003
            
 Sliding from Before to After

For those in the neighborhood who have some concerns about the lovely Capitol Power Plant, which sits just north of the Southeast Freeway but which reaches down to I Street SE just west of 70/100 I, there is a public meeting Thursday, Jan. 24, hosted by Tommy Wells.
Withthe recent application by the Architect of the Capitol for changes to the plant's permits bringing renewed push-back from the community about the plant's continuing burning of coal, Wells has organized the meeting to "hear your concerns and discuss next steps." The District Department of the Environment will be there to present background information about the plant, and Wells is also intending to include a discussion of "strategies for addressing broader concerns about the power plant, particularly the ongoing use of coal as a fuel source."
The Architect of the Capitol has posted these responses to the questions raised about the permits. (Unfortunately, I can't suppress a snicker at the photo used to show the plant, taken on tulip-filled spring day from one of the parks along D Street SE, showing the plant in a fabulously bucolic setting. My photo might be a bit more realistic.)
The meeting is at 6:30 pm at United Methodist Church, 421 Seward Square SE (just south of Pennsylvania Avenue between 4th and 5th streets).
Comments (4)
   
 
 More About meetings
 All posts: meetings, powerplant

JDLand.com Home

Comments

JD says: (1/23/13 7:08 PM)
(Also, I should probably mention that power plant doings will most likely come under my semi-retirement banner, meaning I'm not following it real closely--unless they decide to demolish it. :-) )



straightoutof03 says: (1/24/13 9:35 AM)
You're right about that photo from the Architect of the Capitol. It's essentially a photo of something totally different with just a small portion of the plant being shown. Ridiculous.


jg says: (2/7/13 9:39 AM)
The photo selection is exactly what CSX does, only they choose photos highlight the gritty ends of the tunnel for their photos rather than the actual bucolic neighborhood.
ps - not meant to open a discussion on the csx project, just the photo selection/propaganda.


John Marson says: (2/10/13 11:59 PM)
Nice photo, you can see the coal pile. A lot of people would miss that from the street.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Top News

RMP on DDOT Unveils Planned: I support this change. I like the current Ciculator route in theory, but it take...
NavyYardGuy on Peet's Coffee Coming: @ JD..was that a hint..like Compass coffee is coming to Navy Yard too?
Ampersand on DDOT Unveils Planned: aaaaaaand now that I've posted that I see exactly such a route would also be cre...
JD on DDOT Unveils Planned: (That includes Eastern Market.)
JD on DDOT Unveils Planned: "Circulator service between Union Station, Barracks Row, and the Washington Navy...
Message Board (beta)

Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
900 B/O 5TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/15/17
1200 B/O 4TH ST SE   THEFT
Theft 2nd Degree (theft From Building)
 12/12/17
1200 B/O 4TH ST SE   THEFT
Theft 2nd Degree (theft From Building)
 12/11/17
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/11/17
1100 B/O 1ST ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/08/17
900 B/O NEW JERSEY AVE SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 12/08/17
1100 B/O NEW JERSEY AVE SE   THEFT
Shoplifting
 12/03/17
300 B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 12/02/17
500 B/O L ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 12/02/17
1100 5TH ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 12/01/17
400 B/O M ST SE   THEFT
Shoplifting
 11/29/17
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/28/17
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/27/17
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/26/17
1000 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/26/17
1000 B/O 8TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 11/24/17
1200 B/O NEW JERSEY AVE SE   THEFT
Theft First Degree (all Other Larceny)
 11/24/17
400 B/O M ST SE   THEFT
Shoplifting
 11/22/17
100 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 11/19/17
70 B/O I ST SE   BURGLARY
Burglary Two
 11/16/17

Recent Issued Building Permits Archive  
1100 2ND PL SE   
12/13/17 
BAKER DC / CHRISTINE LONG
AH1800290 / CONSTRUCTION
An after hours permit is respectfully requested from 5am thru 9pm daily
1331 2ND ST SE   
11/29/17 
DC WATER / DAVE LEVINE
AH1800282 / CONSTRUCTION
After Hours work for structure excavation and support for B1311474 DC Water. Corman Construction 301-343-5417
2 I ST SE   
11/29/17 
MCDONALDS CORPORATION / MICHAEL ERIC CAMPBELL
M1800603 / SUPPLEMENTAL
   
11/29/17 
MCDONALDS CORPORATION / DANIEL P. THOMPSON
P1801598 / SUPPLEMENTAL
   
12/01/17 
CRESCENT CAPITAL VIEW, LLC N/A / ERICKA CLARK
AH1800280 / CONSTRUCTION
Place and finish concrete. Minimal noise impact, and required for reduction on impact to traffic.
   
12/14/17 
CRESCENT CAPITAL VIEW, LLC N/A / ERICKA CLARK
AH1800324 / CONSTRUCTION
Place and finish concrete. Minimal noise impact, and required for reduction on impact to traffic.
70 I ST SE   
11/28/17 
DISTRICT OF COLUMBIA / OTIS ELEVATOR COMPANY; OTIS ELEVATOR COMPANY
ER1800447 / SHOP DRAWING
BODY OF WORK: Replace machine and recable elevator # 1.
337 L ST SE   
12/06/17 
JENNIFER LANCASTER / null
E1802092 / SUPPLEMENTAL
347 L ST SE   
12/07/17 
THOMAS PAQUIN / null
E1802129 / SUPPLEMENTAL
   
12/14/17 
THOMAS PAQUIN / BJORN FALK
SOL1800006 / CONSTRUCTION
Installation of a 5.4kW solar PV system. Parapet mounted, 15 panels
555 L ST SE   
11/27/17 
UNITED STATES OF AMERICA / CLIFFORD DIXON
B1714199 / CONSTRUCTION
DGS PROJECT This permit is for interior work only.SWING SPACE FOR WARD 6 CLINIC TO EXISTING VACANT JOY EVANS RECREATION CENTER TEMPORARILY FOR 12 TO 18 MONTHS
515 M ST SE   
12/11/17 
null / BLUE STAR DESIGN BUILD
BP1801085 / POST CARD
300 M ST SE STE# 402 20024   
12/13/17 
FEDERAL CENTER LP / null
P1802065 / SUPPLEMENTAL
100 M ST SE   
12/05/17 
CRANE SERVICE CO / CHRISTINE LONG
AH1800304 / CONSTRUCTION
An after hours permit is respectfully requested from 7AM Saturday thru 7PM Sunday
110 M ST SE   
12/13/17 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / THUY LE
TL1700234 / CONSTRUCTION
Interior alteration for new tenant, restaurant with 37 seats, 49 in occupancy load.
410 M ST SE   
11/20/17 
DC HOUSING / COLLINS ELEVATOR SERVICES INC.; COLLINS ELEVATOR SERVICES INC.
ER1800511 / SHOP DRAWING
BODY OF WORK: 1. Remove old piston. Replace & install jack on car # 1.
861 NEW JERSEY AVE SE   
12/14/17 
CSX TRANSPORTATION INC. / NA CSX TRANSPORTATION, INC.
AH1800330 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities.
1100 NEW JERSEY AVE SE 3RD FL   
11/22/17 
SQUARE 742 LLC / null
P1801490 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
11/20/17 
SQUARE 742 LLC / null
P1801410 / SUPPLEMENTAL
   
12/06/17 
SQUARE 742 LLC / DOMINIC E TOTARO
M1800664 / SUPPLEMENTAL
   
12/08/17 
SQUARE 742 LLC / SAM HOLLEN
B1801219 / CONSTRUCTION
INTERIOR RENOVATION TO 2ND FLOOR OFFICE SPACE. PARTITIONS, FURNITURE, MEP, LIFE SAFETY AND STRUCTURAL HANGING MOVABLE PARTITION. 25,226 SQUARE FEET. ALION SCIENCE AND TECHNOLOGY **LEVEL 2 ALTERATION
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2017 JD.