The next step in converting the sunken portion of the Southeast Freeway between 8th Street SE and Pennsylvania Avenue to the eventual at-grade "Southeast Boulevard" is coming, as DDOT has announced that on Jan. 31, "all eastbound lanes along this stretch will be closed to traffic for approximately 18-20 months while crews fill the roadway to restore it to the local street elevation."
This will be preceded by for a week or so beginning around noontime on Tuesday, Jan. 22, with the route being reduced to only one lane.
Not only are these closures to allow for the filling-in of much of the old roadway, but also to start construction of bridge piers for "a new bridge over the SE Freeway," which I believe will be the new three-lane flyover ramp from the freeway to the outbound 11th Street Bridge, replacing the current one (seen at top left in the photo).
If you're worked up about this closure because you're using the route to Pennsylvania Avenue to then use the left-turn-to-DC295, you should already be using the new exit ramp from the outbound 11th Street Bridge directly to northbound 295 anyway!
The work of bringing in lots and lots (and lots and lots) of dirt to build up the sunken route has already begun on the old westbound side of the road, as seen in this photo I took earlier this month, when I also updated the before and afters for the 11th Street & not-yet-Southeast-Blvd intersection.
If you haven't been following this project, which is part of the $90 million second phase of the 11th Street Bridges project, the filling-in is so there will be an at-grade signalized intersection at 11th Street, SE. Drivers will arrive at the new intersection from the SE Freeway (or Pennsylvania Avenue) and have the option of getting onto 11th Street, or continuing straight. There will also be a new stretch of 12th Street north of M to Southeast Blvd., so that drivers exiting the 11th Street freeway bridges can continue north across M to the new boulevard, instead of turning left onto M and then right onto 11th.
There is also supposed to be a new pedestrian/cycling trail alongside this new Southeast Blvd., creating another connection between Virginia Avenue Park and Barney Circle than using the currently-ripped-up-by-DC-Water M Street route.
This construction drawing shows all the new intersections, ramps, flyovers, and whatnot for both phases of the project on the west side of the river, if you need some help visualizing.
There are also supposed to be public meetings coming this year as part of studies now underway on how to remake the Barney Circle-not-yet-Southeast-Blvd interchange.
Comments (1)
   
 
 More About 11th Street Bridges

JDLand.com Home

Comments

strizhko says: (2/1/13 3:35 PM)
This project really baffles me. Why eliminate an overpass and create a new signalized intersection? Most cities/towns actually try to do the opposite to improve traffic flow. Is it’s the cities love of traffic lights. Recently the city made another baffling change as well. For years I have made a left from PA Ave onto 10th Street in the morning to escape the left turn congestion at 11th Street. So what does the city do… they signalize 10th street. Now traffic making a left there blocks the left lane on PA Ave waiting for the light to change, creating a real mess on Penn. I don’t know who makes these dumb decisions but sometimes I think they do it in a dark room with no windows, and never drive any road in the city. They really should be held accountable in some way.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Top News
  

RMP on Juice Laundry Coming: I guessed wrong. I talked to the Juice Laundry folks today and it sounds like th...
dude on Juice Laundry Coming: Ahh, refreshing nut milks.
RMP on Juice Laundry Coming: I wonder which retail space Juice Laundry will be getting at Arris. The one clos...
JD on Wednesday Tidbits: Andrew: Well, I was wrong and right and wrong and right. See UPDATE VERSION 2.0 ...

Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
300 B/O TINGEY ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/01/16
1100 B/O NEW JERSEY AVE SE   THEFT
 11/28/16
900 B/O POTOMAC AVE SE   THEFT F/AUTO
 11/27/16
500 B/O L ST SE   HOMICIDE
GUN
 11/27/16
1300 B/O WATER ST SE   MOTOR VEHICLE THEFT
 11/23/16
1200 B/O HALF ST SE   THEFT F/AUTO
 11/23/16
500 B/O M ST SE   THEFT
 11/22/16
100 B/O L ST SE   MOTOR VEHICLE THEFT
 11/22/16
1200 B/O HALF ST SE   THEFT
 11/21/16
1000 B/O 1ST ST SE   THEFT F/AUTO
 11/19/16
800 B/O L ST SE   THEFT F/AUTO
 11/18/16
300 B/O TINGEY ST SE   THEFT
 11/18/16
1000 B/O 8TH ST SE   ASSAULT W/DANGEROUS WEAPON
KNIFE
 11/18/16
1100 B/O 10TH ST SE   THEFT F/AUTO
 11/18/16
250 B/O L ST SE   THEFT F/AUTO
 11/17/16
1000 B/O 2ND PLACE SE   THEFT F/AUTO
 11/14/16
800 B/O L ST SE   THEFT F/AUTO
 11/13/16
1000 B/O 5TH ST SE   THEFT
 11/12/16
300 B/O L ST SE   ROBBERY
GUN
 11/11/16
1100 B/O 1ST ST SE   THEFT F/AUTO
 11/10/16
50 B/O K ST SE   THEFT F/AUTO
 11/10/16
1200 B/O 1ST ST SE   THEFT
 11/10/16
700 B/O L ST SE   THEFT
 11/09/16
400 B/O M ST SE   THEFT
 11/08/16
900 B/O NEW JERSEY AVE SE   THEFT
 11/07/16
1200 B/O 1ST ST SE   THEFT
 11/07/16
1100 B/O NEW JERSEY AVE SE   ROBBERY
 11/06/16
200 B/O M ST SE   THEFT
 11/06/16
1000 B/O 2ND PLACE SE   THEFT
 11/04/16
1230 SOUTH CAPITOL ST SE   BURGLARY
Burglary Two
 11/04/16

Recent Issued Building Permits Archive  
1233 1ST ST SE   
11/14/16 
NA BALLPARK HOTEL LLC / NA BALLPARK HOTEL LLC; ECONO SIGN INC; N/A
SG1700062 / CONSTRUCTION
Revision on Existing Approved Permit - SG1600390 Reduction in the depth of the Approved Blade Sign
1022 3RD PL SE   
11/15/16 
M JACOBS / M JACOBS; LIGGETT; RYAN MCNEILL; DANIEL PALOUSEK
SOL1600840 / CONSTRUCTION
install 8 panel solar modules to roof of single family residence
   
11/17/16 
WILLIAM E JACOBS / JOHN C. BRADLEY
E1701381 / SUPPLEMENTAL
1310 10TH ST SE 20374   
11/17/16 
OCTAVIA TERRANCE / MICHAEL MOORE
B1511736 / CONSTRUCTION
Federal Government project to construct Stormwater Management BMPs at the Washington Navy Yard.
1220 12TH ST SE 2   
11/17/16 
WASHINGTON GAS LIGHT CO / JOE C PANCIONE
E1701376 / SUPPLEMENTAL
1220 12TH ST SE 2ND FLOOR   
11/17/16 
WASHINGTON GAS LIGHT CO / JAY W LIPP
P1701319 / SUPPLEMENTAL
1220 12TH ST SE   
11/16/16 
WASHINGTON GAS LIGHT CO / null
P1701283 / SUPPLEMENTAL
2 I ST SE   
11/17/16 
MCDONALDS CORPORATION / BEN BEDDO
D1700078 / CONSTRUCTION
REMOVE ALL EXTERIOR SIGNAGE, REMOVE CIRCUITS FOR ALL EXTERIOR SIGNS.
300 M ST SE   
11/14/16 
FEDERAL CENTER LP / null
P1701209 / SUPPLEMENTAL
400 M ST SE   
11/18/16 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / REBECCA KIRBY; DISTRICT OF COLUMBIA HOUSING AUTHORITY; PAUL WARREN
E96316142 / SUPPLEMENTAL
1333 M ST SE   
11/15/16 
1333 M STREET SE LLC / 1333 M STREET SE LLC; ECS MID-ATLANTIC LLC
SB1700027 / CONSTRUCTION
ECS Will install at total of 18 soil borings to a maximum depth of 40 feet below ground surface. Borings will be completed with a geoprobe drill rig using duel tube technology. Following boring installation each boring will be grouted with the approved DOEE grout mix.
   
11/15/16 
NA 1333 M STREET SE LLC / NA 1333 M STREET SE LLC; NA ECS MID-ATLANTIC, LLC
SB1700040 / CONSTRUCTION
ECS will install a total of 3 hand geoprobe soil borings to a max depth of 10 feet below ground surface. Borings will be completed by hand at each location as detailed in Figure 1. Following boring installation each boring will be grouted with approved DOEE grout mix
   
11/15/16 
NA 1333 M STREET SE LLC / NA 1333 M STREET SE LLC; ECS MID-ATLANTIC, LLC
SB1700041 / CONSTRUCTION
Installation of five monitoring wells at the above address. Figure 1 shows the location of each well. These wells will be installed with a hollow-stem auger rig. Wells will be installed into the shallow aquifer only, 10 feet of screen will be used which will have sand installed two feet above the screen with a bentonite seal tow feet above the sand. A 60-40 mix of grout will be used to complet...
1100 NEW JERSEY AVE SE   
11/14/16 
SQUARE 742 LLC / OTIS ELEVATOR COMPANY
ER1700438 / SHOP DRAWING
Replace hoist ropes and governor ropes on al 6 elevators Estimated Cost of Work: $12,000.00
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Capitol ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2016 JD.