Since January, 2003

Advertise on JDLand
 (a random before-and-after moment)
April 23, 2004
October 23, 2011
4th at K, Looking North (see more)

Within the past few days, readers have sent tweets with photos of brewing equipment being delivered to soon-to-be-Gordon Biersch at 100 M and inside the space at the Boilermaker Shops that will become Bluejacket.
No official timeframe on when either of these restaurants will open, though a Biersch employee told the Post that he "expects the new Biersch branch to be operating in time for the Craft Brewers Conference in March and the Nats' home opener in April."
As for the other beer joint on tap for the neighborhood (see what I did there?), there doesn't appear to be any action so far in the Willie's Brew and 'Que space at the Boilermaker Shops, but with owner Xavier Cervera's long-in-the-works redo of the Hawk 'n' Dove reportedly about to debut, perhaps he'll then be able to shift resources both to Willie's and to the Park Tavern at Canal Park.
UPDATE, 1/17: This Esquire interview with Bluejacket bigshot Greg Engert says that the bar will open "in May."
Comments (8)
   
 
 More About Retail

JDLand.com Home

Comments

ZoolanderANDtheBoYz says: (1/15/13 12:44 PM)
I walked by Gorden Biersch last night and they already installed their brewing equipment.


JES says: (1/15/13 1:21 PM)
Is Cervera still deciding whether or not to sell his restaurant group? Or is that saga over at this point? Wondered if that was behind part of the delay in getting the local joints open.


conngs0 says: (1/15/13 1:24 PM)
Great question, JES. It looks like the Park Tavern could be open tomorrow if there was a desire to do so. I was operating on the (completely unsubstantiated) assumption that Cervera put everything on hold because of the possible sale. With a fairly healthy turnout on the ice skating rink this winter, it sure seems like the Park Tavern has missed out on a lot of potential customers.


JD says: (1/15/13 1:29 PM)
Yeah, I should have mentioned that potential sale in the post itself, at least in terms of whether Willie's will see any action (I would think Park Tavern could open soon, as you said). But there's been no news on it one way or the other.


NatsFan says: (1/15/13 2:09 PM)
I was told by an employee at the Skate Park that Cervera did infact sell his restaurant group. I havent found any confirmation of this online though and its complete word of mouth. However it seems to make sense due to the delay in openings.



David Garber says: (1/15/13 2:27 PM)
The word I have re: Park Tavern is that Xavier is still waiting on some permit issues to be resolved, and that they weren't able to open earlier because the certificate of occupancy for the entire building had to be received before pulling restaurant permits. Although this has been the answer since November, I was told yesterday they hope to open in about three weeks. Just the messenger... :)


JD says: (1/17/13 11:18 AM)
Just as a follow up to David... The BID passed to me the certificates of occupancy dated Nov. 15 for all three blocks of the park, including the Park Tavern building. (Skaters wouldn't be able to use the restrooms in the building if it didn't have the C of O.) There may be other permitting issues for the restaurant, but they aren't related to the occupancy.

Also, apparently the sale to the restaurant group has gone through, though Cervera is still involved and part of the new ownership.



David Garber says: (1/17/13 1:17 PM)
Right. Didn't mean to infer that the C of O wasn't received in November, just that they didn't start on some of the other required permits until after that time. As yet another update, Cervera told The Hill is Home that "He estimates that the opening date should be about one month away.." link Now that Hawk N' Dove opens tonight, I'm hopeful for a priority shift down to our neighborhood!

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed

See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2015!
 Top News
  
Section314 on Due South Opening: First thing back, you can go take pictures of the construction starting at 99 M....
JD on Due South Opening: Me too! :-) I'll be back in the saddle next week, and well refreshed too, wit...
willinrm on Due South Opening: This comment section has become my new source of news!! lol
JES on Due South Opening: No building permits filed for any kind of work there? I was wondering why they c...



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
500 B/O L ST SE   THEFT
Theft 1 (Theft F/Building)
 08/08/15
UNIT B/O I ST SE   BURGLARY
2nd Degree Burglary (Armed Or Otherwise)
 08/07/15
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2 (Theft F/Building)
 07/29/15
400 B/O M ST SE   THEFT
Theft 1 (Theft F/Building)
 07/28/15
1200 B/O 1ST ST SE   THEFT
Theft 2 (Theft F/Building)
 07/25/15
700 B/O L ST SE   ROBBERY
Robbery Snatch Or Pursesnatch
 07/23/15

Recent Issued Building Permits Archive  
1277 1ST ST SE   
08/06/15 
MILLER?LONG MILLER?LONG
AH1500660 / CONSTRUCTION
AFTERHOURS TO POUR CONCRETE ON JOBSITE FROM 4AM TO 9PM
   
08/11/15 
BALLPARK RESIDENTIAL LLC / RICHARD V CAREY
P1508164 / SUPPLEMENTAL
1331 2ND ST SE   
08/03/15 
DC WATER DC WATER / CORMAN CONSTRUC CORMAN CONSTRUCTION
AH1500648 / CONSTRUCTION
TUNNEL BORING MACHINE / EQUIPMENT
1016 3RD ST SE   
07/31/15 
ANAMARIA R MOTTOLA / DONALD V. ELLENBERGER
M1502813 / SUPPLEMENTAL
1331 4TH ST SE   
08/07/15 
FC 1331 LLC / MARK A DORSEY
EN1502823 / SHOP DRAWING
TYPE OF ELEVATOR ONE (1) TRACTION / STEEL / CENTRAL / VERTRICAL TRANSPORTATION (11TH FLOOR). ELEVATOR #1.
921 5TH ST SE   
08/05/15 
JORDAN NELSON
B1511099 / CONSTRUCTION
FLAT ROOFING REPAIR TO REMOVE AND REPLACE MEMBRANE USING 5 SQUARES OF LIKE TYPE MATERIAL
1000 5TH ST SE   
07/29/15 
N/A DC HOUSING
B1510526 / CONSTRUCTION
INSTALLATION OF NEW FIRE ALARM SYSTEM FOR ARTHUR CAPPER COMMUNITY CENTER
1150 5TH ST SE   
08/04/15 
DISTRICT OF COLUMBIA / WHITING TURNER; DEPARTMENT OF G SERVICES; GSA
BCIV1500153 / CONSTRUCTION
ROUGH GRADING AND TO REMOVE AN DISPOSE OF EXISTING HARD SURFACE. ALSO TO REMOVE EXISTING FENCE REMOVE OF RETAINING WALLS TREES AND PLANTER BOXES.
   
08/04/15 
DEPARTMENT OF GENERAL SERVICES DC PUBLIC SCHOOL / DOUGLAS FOSTER
AH1500655 / CONSTRUCTION
AFTER HOURS PERMIT FOR THE RENOVATION OF VAN NESS ELEMENTARY SCHOOL FROM 7:00AM TO 12:00AM MONDAY THOUGH SUNDAY TO START JULY 20 2015 TO SEPTEMBER 30 2015 AS PER MR. ROGER MOFFATT CHAIRMAN ANC 6D.
   
08/07/15 
ALAN J PHELPS / JOHN HOMICK
E1508228 / SUPPLEMENTAL
   
08/10/15 
DEPARTMENT OF GENERAL SERVICES DC PUBLIC SCHOOL / DEPARTMENT OF G DC PUBLIC SCHOOL
B1511234 / CONSTRUCTION
REVISION TO B1511107 TO CORRECT QUADANT ON ADDRESS FROM 1150 5TH STREET N.E. TO 1150 5TH STREET S.E. TO UPGRADE THE ELECTRICAL SERVICES OF A DISTRICT OF COLUMBIA PUBLIC SCHOOL FROM 1200AMP TO 3 000 AMP.
   
08/11/15 
PEPCO PEPCO
AH1500668 / CONSTRUCTION
INSTALLATION OF CABLE AND METERS
1220 12TH ST SE   
08/13/15 
WASHINGTON GAS LIGHT CO / JOHN GIUSEPPE-RAMCO
B1509350 / CONSTRUCTION
RENOVATIONS TO EXISTING 3RD FLOOR OFFICE SPACE EXELIS AS SHOWN ON THE ATTACHED MECH. PLUMB. ELECT. FIRE PROTECTION DEMOLITION AND ARCH. DWGS. INTERIOR WORK ONLY. NO CHANGE IN US. NO STRUCT. WORK.
909 HALF ST SE   
08/13/15 
BAKER DC LLC / CHRISTINE LONG
AH1500677 / CONSTRUCTION
AN AFTER HOURS PERMIT IS RESPECTFULLY REQUESTED FROM 11:00PM FRIDAY THRU 11:00PM SATURDAY
1015 HALF ST SE   
08/04/15 
WSP / PARSONS BRINCKERHOFF / DAMON ELLIS
B1508624 / CONSTRUCTION
INTERIOR RENOVATION OF TENANT SUITE ON THE 6TH FLOOR TO INCLUDE THE FOLLOWING ELECTRICAL FIRE MECHANICAL PLUMBING AND GREEN. INSTALLATION OF SYSTEM FURNITURE NO CHANGE OF USE OR STRUCTURAL WORK
   
08/13/15 
HALF ST SE LLC / GREGORY E LIGON
E1508399 / SUPPLEMENTAL
   
08/05/15 
HALF ST SE LLC / DAVID FLEMING
P1507999 / SUPPLEMENTAL
   
08/06/15 
HALF ST SE LLC / ROBERT L HUNTER
M1502897 / SUPPLEMENTAL
   
08/06/15 
WSP PARSON / ANDREW ARNTSON; WSP PARSON; ANDREW ARNTSON
P13301503 / SUPPLEMENTAL
   
08/07/15 
HALF ST SE LLC / JOSEPH J FLYNN
E1508225 / SUPPLEMENTAL
1201 HALF ST SE   
07/27/15 
WEST HALF RESIDENTIAL II LLC / ECS MID-ATLANTIC LLC C/O DON SESER
SB1500398 / CONSTRUCTION
WE WILL PERFORM A TOTAL OF THREE SOIL BORINGS ON THE PROPOSED SITE. THE BORINGS WILL BE ADVANCED TO A DEPTH OF 60 TO 100 FEET BELOW EXISTING SITE GRADES AND WILL BE LOCATED WITHIN THE BOUNDS OF THE PRIVATE PROPERTY. THE BORINGS WILL BE DRILLED UTILIZING 3.25-INCH HOLLOW STEM CONTINUOUS FLIGHT AUGERS. THE BORINGS WILL BE PERFORMED UTILIZING AN ATV-MOUNTED DRILL RIG AND WILL GENERATE AN APPROXIMATE ...
1220 HALF ST SE   
07/31/15 
BUFFALO WILD WINGS / DANIEL RUDE; BUFFALO WILD WINGS; DANIEL RUDE
P66073039 / SUPPLEMENTAL
   
07/31/15 
BUFFALO WILD WINGS / DANIEL RUDE; BUFFALO WILD WINGS; DANIEL RUDE
G33633628 / SUPPLEMENTAL
   
08/12/15 
BUFFALO WILD WINGS / NICOLE WHITE; BUFFALO WILD WINGS; GREG CONCANNON
AR49901357 / SUPPLEMENTAL
   
08/13/15 
BUFFALO WILD WINGS / BELA X-PEDITERS PLUS INC.
AH1500681 / CONSTRUCTION
WORK AFTER HOURS 7PM-7AM. 8 / 13 / 2015 TO 9 / 13 / 2015
82 I ST SE   
08/04/15 
GREYSTAR DEVELOPMENT GREYSTAR DEVELOMENT / MICHAEL GROSE; GREYSTAR DEVELO GREYSTAR DEVELOMENT; MITCH PERMUY
E15667852 / SUPPLEMENTAL
55 K ST SE   
07/30/15 
BAKER DC LLC / CHRISTINE LONG
AH1500643 / CONSTRUCTION
AN AFTER HOURS PERMIT IS RESPECTFULLY REQUESTED FROM 12:01AM SATURDAY THRU 11:59PM SUNDAY
50 M ST SE   
08/03/15 
PEPCO PEPCO
AH1500644 / CONSTRUCTION
AFTER HOURS WORK FOR THE FOLLOWING LOCATIONS: 50 M ST. SE 100 15TH ST. SE 2ND ? H ST. SE 1054 31ST ST. NW 500 WATER ST. SW 1000 WATER ST. SW 7TH ? H ST. NE WISCONSIN AVE ? Q ST. 1331 4TH ST SW 13TH ? 14TH ST. BETWEEN G ST AND EYE ST. NW 2124 EYE ST. NW
   
08/04/15 
KCG 50 M LLC / JOSEPH E RICHARDS
E1508097 / SUPPLEMENTAL
   
08/11/15 
MILLER?LONG
TC1500036 / CONSTRUCTION
TOWER CRANE FOR JOB SITE USE
   
08/13/15 
MILLER?LONG MILLER?LONG
AH1500674 / CONSTRUCTION
AFTERHOURS TO PUT UP TOWERCRANE WITH 200 TON MOBILE CRANE SATURDAY 8 / 15 / 2015 AND 8 / 16 / 2015 FROM 5AM TO 9PM
55 M ST SE   
07/27/15 
HINES GLOBAL REIT 55 M STREET LLC / ANTHONY G SAMBURG
E1507875 / SUPPLEMENTAL
800 NEW JERSEY AVE SE   
07/29/15 
BAKER DC LLC / BAKER DC LLC; CHRISTINE LONG
AH1500569 / CONSTRUCTION
AN AFTER HOURS PERMIT IS RESPECTFULLY REQUESTED FROM 7PM THRU 7AM MONDAY THRU SUNDAY
1100 NEW JERSEY AVE SE   
08/11/15 
CHRISTOPHER CONDON
PC69159304 / POST CARD
INTERIOR DEMOLITION OF NON-BEARING ELEMENTS IN A SPACE UP TO 5 000 SQUARE FEET (464.5 SQUARE METERS)
1111 NEW JERSEY AVE SE   
07/29/15 
GREGORY R. GOSNELL
P1507817 / SUPPLEMENTAL
125 O ST SE   
08/07/15 
DISTRICT OF COLUMBIA / PERRY HUGEE
M1502918 / SUPPLEMENTAL
1500 SOUTH CAPITOL ST SE   
07/28/15 
LERNER MANAGEMENT / GERARD MULLEN; LERNER MANAGEMENT; SCOTT BROADBENT
E69613955 / SUPPLEMENTAL
   
07/28/15 
NATIONALS PARK / GERARD MULLEN; NATIONALS PARK; SCOTT BROADBENT
E91113810 / SUPPLEMENTAL
301 TINGEY ST SE   
07/29/15 
NA NA NA
EHOP1590795 / HOME OCCUPATION
301 WATER ST SE   
08/12/15 
LUMBER SHED LIC / ROBERT WATTS; LUMBER SHED LIC; ROBERT WATTS
E99575145 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory




     © Copyright 2015 JD.