Since January, 2003
            
 (a random before-and-after moment)
April 2, 2006
March 29, 2015
South Capitol at P, Looking East-Southeast (see more)

There's a lot going on over yonder at 11th Street these days, as the initial 11th Street Bridges project continues toward its expected completion next year while the now-funded Phase 2 work is starting to get underway.
I was able to arrange a tour last week (thank you, bridge folks!), and have put together a photo gallery of the most interesting shots.
However, there's a lot going on and so I'm going to break out some of the information here as well. (But go look at the gallery too!)
New Ramps from/to 11th Street Local Bridge
By the end of the month (or maybe even by the end of the week), two new ramps on the 11th Street Local Bridge will open, providing access to southbound I-295 from the local bridge and to the local bridge from northbound DC-295. There are signalized intersections at both ramps, with turns allowed in each direction. And, once construction is finished to make 11th Street two-way from O Street northward, commuters driving north on 295 will be able to use the new ramp to the local bridge to then arrive directly at the Navy Yard's entrance gate at 11th and N.
Southeast Blvd., and Outbound Freeway Traffic
This week saw the first of the lane closures that within a few months will signal the end of the SE Freeway east of 8th Street. Once all lanes are closed, traffic taking the old two-lane flyover to outbound I-695 will be temporarily routed onto the completed-but-not-opened inbound flyover connecting I-695 and I-395. This will allow for the razing of the old outbound flyover, and construction of a new three-lane flyover in the gap between the old and new ones. The filling of the old sunken freeway will also begin, for the new at-grade Southeast Blvd.
Old Outbound Bridge Demolition
The old outbound 11th Street Bridge is now little more than a bunch of old girders, which are starting to be removed. Soon, all that will be left will be the river piers, though two of those will be used to create viewing platforms that will be accessed via walkways from the new 11th Street Local pedestrian path. (And can be reused if anyone ever decides to pony up the millions needed to create the 11th Street Recreation Bridge.) In the meantime, work continues on the downriver edge of the new local bridge, to get it to its full four-lane-plus-ped-path width.
But there's more than just these items and photos. There's photos of the under-construction ramp that in about three months will take traffic from outbound I-695 to northbound DC-295, plus the big piles of dirt waiting to be used to fill in the eastern part of the Southeast Freeway, and the work on the ramp from 11th Street to westbound I-395, and more. So go look at the entire gallery. (I've also incorporated some of the new photos into my 11th Street Bridges project page, to go with the before-and-afters.) I also wrote in more detail about the Phase 2 projects a few months back.
Comments (6)
   
 
 More Recent News

JDLand.com Home

Comments

KLB says: (9/19/12 9:35 AM)
From the "entire gallery" page, "However, once the sunken freeway lanes are closed, traffic currently running to outbound I-695 on the ramp seen at far left will be diverted onto this new flyover, which allows for the demolition of the old two-lane outbound flyover and construction of a new three-lane one."

Will the inbound and outbound traffic share the new inbound ramp, or will it just be outbound traffic until the new outbound flyover is completed?


JD says: (9/19/12 9:39 AM)
Dangit, why did you ask the one question I specifically hoped no one would ask, since I forgot to ask myself? :-) My initial guess is that it would just be outbound traffic until the new flyover is finished, but I honestly don't know. I'll see what I can find out, or maybe before long they'll release actual construction documents instead of the concept ones.


bkt says: (9/19/12 9:56 AM)
JD, Do you know what the plans are for the northbound exit onto 295/695 from Howard Road? I take 295 North from Bolling to Rt 50 and the traffic merging from the right side has to merge over 2 lanes very quickly to the left exits for 695 which leads to complete congestion chaos at rush hour. This seems like a fail to me, but maybe there's another phase coming with a 'fix'???


JD says: (9/19/12 10:57 AM)
@bkt, I have to admit that I don't pay as close attention to the design and issues on the east side of the river, so I don't know specifically in terms of the current 11th Street Bridge construction.

Long term, the real solution is probably the huge new *real* interstate interchange at 295/South Capitol Street/Suitland Parkway, to be built with the new Douglass Bridge.

Short term, I do think that they're hoping the new exit about to open to the 11th Street Local Bridge will at least take traffic going to the Navy Yard out of the two left lanes, which I assume would include some of that Howard Road ramp traffic.

Also, there's going to be a ramp from the east side of the 11th Street Bridge to northbound DC-295 (ramp C-2 on the link below) so that maybe some of the local Anacostia traffic wouldn't be trying to get on at Howard Road, but instead there?

link




Maelstrom says: (9/19/12 11:13 AM)
@KLB - beat me to the question. Personally, I think they could fit everyone on the new flyover without losing capacity, but I don't think they will only do that if they need to tear out the old inbound flyover for the sake of the fill work below. Consider that once you close the old inbound flyover, you have no exits between M street and D street SW on 695/395N. I am somewhat suprised by the announcement that the outbound traffic will be diverted onto the new flyover. It was one of the options I had anticipated, but it's an ugly one because they will have to tear out the shiny new bridge edge that they built between the inbound and outbound freeway bridges and the pile of rocks in between the bridges to divert the traffic. More than the re-purposing of the fill for the off ramp from SE/SW @11th, this is a case where new work will need to be ripped out and re-done later.


terpsichorean says: (9/21/12 9:29 AM)
Hi, I live on upper NE side of the Hill (practically Rosedale). I work in Crystal City, and until Monday I took 17th St and made a left onto the Barney Circle/RFK entrance to get to work every morning. Each day this week I have tried a different route to attempt to cut across the Hill to get to the 3rd St SE entrance, but there seems to be no efficient way to do this (traffic, lights, etc). Does anyone have a recommendation for us NE Hill folks? Should I just start taking 295 to get to 395, and avoid the Hill until the 11th St bridge opens? This has drastically changed my once beautifully short commute. So frustrating...Help!

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2016!
 Top News

walt on Due South Working: That Honeycombs box is truly vintage!
NavyYardGuy on Due South Working: HUNGRY HOWIES. Hands Down---it changed my life,seriously. [image]
JES on Due South Working: Oh god, green lantern. I lived a friend in Clawson for a year, we used to walk t...
JD on Due South Working: As for Detroit pizza, I need to add Cloverleaf in Eastpointe, in addition to the...
  
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1400 B/O SOUTH CAPITOL ST   THEFT
Theft 2nd Degree (all Other Larceny)
 05/26/16
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 05/24/16
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (theft From Building)
 05/21/16
800 899 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 05/16/16
1000 B/O 1ST ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 05/15/16
1400 B/O SOUTH CAPITOL ST   THEFT
Theft 2nd Degree (all Other Larceny)
 05/15/16
1400 B/O SOUTH CAPITOL ST   THEFT
Theft 2nd Degree (all Other Larceny)
 05/15/16
1200 B/O 4TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 05/12/16
300 B/O TINGEY ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 05/11/16
1200 B/O I ST SE   ROBBERY  05/08/16
900 B/O 1ST ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 05/08/16
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 05/06/16
1220 HALF ST SE   THEFT
Theft 2nd Degree (theft From Building)
 05/05/16
1100 B/O 1ST ST SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 05/04/16
300 K ST SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 05/04/16
70 B/O I ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 05/02/16
UNIT B/O I ST SE   ROBBERY  04/29/16
1100 B/O 5TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 04/27/16

Recent Issued Building Permits Archive  
1233 1ST ST SE   
05/10/16 
null / KONE INC
EN1602126 / SHOP DRAWING
Type of Elevator : Two (2) Electrical / steel / center / passenger / 3 floors Elevator 5 & 6 Condition : Application for Modification of Construction Code MVQ1600083 & MVQ1600084 See : B1403486 and TL1600011
   
05/23/16 
null / KONE INC
EN1602096 / SHOP DRAWING
Type of Elevator : Two (2) Electrical / steel / center / passenger / 16 floors
   
05/23/16 
null / KONE INC
EN1602097 / SHOP DRAWING
Type of Elevator : One (1) Electrical / steel / center / passenger / 16 floors (elevator #2)
   
05/23/16 
null / KONE INC
EN1602098 / SHOP DRAWING
Type of Elevator : One (1) Electrical / steel / center / passenger / 16 floors (elevator #3)
   
05/24/16 
BALLPARK HOTEL LLC / RICHARD V CAREY
P1606451 / SUPPLEMENTAL
1277 1ST ST SE   
05/23/16 
PEPCO PEPCO
AH1600711 / CONSTRUCTION
CABLE SPLICING & MISC EQUIPMENT - MH ACCESS PEPCO BOND #017026121
1108 2ND ST SE   
05/19/16 
NA DISTRICT OF COLUMBIA HOUSING AUTHORITY / NA DISTRICT OF COLUMBIA HOUSING AUTHORITY; ECS MID-ATLANTIC LLC
SB1600233 / CONSTRUCTION
Three borings will be completed utilizing a geoprobe direct push drill rig using a duel tube sampling device. the borings will create a 2.25 inch anulus. The geoprobe will advance all 3 borings to a depth of 30 feet below ground surface or until refusal or dense clay is encountered. following completion of the soil borings holes will be tremme grouted from the bottom to the top using a mixture of ...
1331 2ND ST SE   
05/16/16 
DC WATER / DC WATER; CORMAN CONSTRUCTION
AH1600698 / CONSTRUCTION
After Hours work for structure excavation and support for B1311474 & B1605659 DC Water, Corman Construction 202-863-0052
1005 3RD PL SE   
05/12/16 
PETER D TRIFU / JOSE M. MORALES
P1606192 / SUPPLEMENTAL
1300 4TH ST SE   
05/10/16 
LOU FOREST CITY - WASHINGTON / GEORGE MORETRENCH AMERICAN CORP.
SB1600070 / CONSTRUCTION
To drill and install 18 deep wells with 12" diameter of borehole and 6" well casing, and 4 observation wells with 6" diameter of borehole and 2" well casing to 80 feet via Mud Rotary drilling for the temporary construction dewatering of the proposed below grade construction. All drill spoils will be contained and disposed of according to federal and District of Columbia regulations.
1000 5TH ST SE   
05/25/16 
KIM MITCHELL, CDKM CONSULTING, LLC / OMAR BIAGAS; KIM MITCHELL, CDKM CONSULTING, LLC; JOHN BIAGAS
E94700028 / SUPPLEMENTAL
This supplemental permit was issued online. Use the Online Permit View application on DCRA Intranet to view the details and print a copy of the permit. Alternatively, you can copy and paste the following URL into an internet browser. https: / / ospi.dcra.dc.gov / ospi / PrintPermit.aspx?param = zI8IgGJEIleDWgjMbZfwro4FBxVFy8Px
1220 12TH ST SE 200   
05/11/16 
WASHINGTON GAS LIGHT CO / RALPH THREATT
E1606272 / SUPPLEMENTAL
1220 12TH ST SE   
05/11/16 
CORPORATE OFFICE PROPERTIES TRUST / KELLY WALSH; CORPORATE OFFICE PROPERTIES TRUST; THOMAS DVORAK
E74440979 / SUPPLEMENTAL
This supplemental permit was issued online. Use the Online Permit View application on DCRA Intranet to view the details and print a copy of the permit. Alternatively, you can copy and paste the following URL into an internet browser. https: / / ospi.dcra.dc.gov / ospi / PrintPermit.aspx?param = zI8IgGJEIldFWRC67V1mkMF%2fVBuW5xWq
70 I ST SE 832   
05/17/16 
null / NA NA NA
EHOP1690678 / HOME OCCUPATION
10 I ST SE   
05/19/16 
TIMOTHY TEMPLE- CAPITAL HILL RACQUET CLUB / TIMOTHY TEMPLE- CAPITAL HILL RACQUET CLUB; ECS MID-ATLANTIC LLC
SB1600232 / CONSTRUCTION
Five borings will be completed utilizing a geoprobe direct push drill rig using a duel tube sampling device. the borings will create a 2.25 inch anulus. The geoprobe will advance all 5 borings to a depth of 30 feet below ground surface or until refusal or dense clay is encountered. following completion of the soil borings holes will be tremme grouted from the bottom to the top using a mixture of p...
   
05/24/16 
CAPITAL HILL RACQUET CLUB C/O HUNTER DAWKINS, JOHNSON DEVELOPMEN / CAPITAL HILL RACQUET CLUB C/O HUNTER DAWKINS, JOH; ECS MID-ATLANTIC, LLC C/O REBECCA RUSCHMAN
SB1600235 / CONSTRUCTION
We will perform three borings on this property to a depth of 60 feet below the existing site grades. The borings will be drilled utilizing a 3.25-inch, hollow-stem, continuous flight auger and will generate an approximately 6 inch annulus. After geotechnical exploration is complete, the borings will be backfilled with bentonite slurry consisting of 2 lbs bentonite powder to 1 gallon of water ratio...
201 L ST SE   
05/19/16 
NA DISTRICT OF COLUMBIA HOUSING AUTHORITY / NA DISTRICT OF COLUMBIA HOUSING AUTHORITY; ECS MID-ATLANTIC LLC
SB1600234 / CONSTRUCTION
Two borings will be completed utilizing a geoprobe direct push drill rig using a duel tube sampling device. the borings will create a 2.25 inch anulus. The geoprobe will advance both borings to a depth of 30 feet below ground surface or until refusal or dense clay is encountered. following completion of the soil borings holes will be tremme grouted from the bottom to the top using a mixture of pow...
14 M ST SE   
05/16/16 
ANDREW ROYALS
B1608241 / CONSTRUCTION
repair and replacement of window and frame
50 M ST SE   
05/18/16 
KCG 50 M LLC ENGLEWOOD LLC / TIEVY; KCG 50 M LLC ENGLEWOOD LLC; TRACIE CLAXTON-RAMOS
SG1600300 / CONSTRUCTION
2 Signs Channel Letters Illuminated 2 Blade Signs illuminated
100 M ST SE FLOOR 7   
05/24/16 
SQUARE 743 INC / DAVID FLEMING
P1606462 / SUPPLEMENTAL
100 M ST SE   
05/19/16 
SQUARE 743 INC AND 100 M ST SE LLC / LHREV WASHINGTON M STREET LLC A DELAWARE LLC; KIM MITCHELL CDKM CONSULTING LLC
B1605938 / CONSTRUCTION
APPROX 7938 SF TENANT FIT OUT - CURRENTLY SHELL CONDITION - FLOORING, DOORS, AND HARDWARE, DRYWALL, CEILILNG, LIGHTS, MECHANICAL, SPRINKLER AND PLUMBING TO BE ADDED. ALL WORK TO BE DONE ON 7TH FLOOR
   
05/24/16 
RICHARD ELLIS / DAVID HUDGENS; RICHARD ELLIS; DAVID HUDGENS
P10155121 / SUPPLEMENTAL
This supplemental permit was issued online. Use the Online Permit View application on DCRA Intranet to view the details and print a copy of the permit. Alternatively, you can copy and paste the following URL into an internet browser. https: / / ospi.dcra.dc.gov / ospi / PrintPermit.aspx?param = zI8IgGJEIleDWgjMbZfwrvBRHQhIHx5f
800 NEW JERSEY AVE SE   
05/10/16 
SQUARE 737 LLC / KONE INC
EN1602094 / SHOP DRAWING
Type of Elevator : Two (2) Electrical / steel / center / passenger / 3 floors Condition: Application for Modification of construction code MVQ1600091 & MVQ160092
   
05/10/16 
SQUARE 737 LLC / KONE INC
EN1602095 / SHOP DRAWING
Type of Elevator : Three (3) Electrical / steel / center / passenger / 3 floors Elevator : G1, G2, G3 Condition: Application for Modification of construction code MVQ1600090 & MVQ160089 & MVQ1600088
   
05/10/16 
SQUARE 737 LLC / KONE INC
EN1602107 / SHOP DRAWING
Type of Elevator : One (1) Electrical / steel / center / passenger / 2 floors Elevator : G6, Condition: Application for Modification of construction code MVQ1600093
861 NEW JERSEY AVE SE   
05/18/16 
NA CSX TRANSPORTATION, INC.
AH1600719 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities. Activities will occur at the following areas: between 2nd Street SE and 3rd Street SE along Virginia Avenue SE, intersection of 3rd Street SE and Virginia Avenue SE, between 3rd Street SE and 4th Street SE along Virginia Avenue SE, intersection of...
880 NEW JERSEY AVE SE   
05/19/16 
880 NEW JERSEY AVENUE LLC / 880 NEW JERSEY AVENUE LLC; BRUCE PADDOCK SWIMMING POOL COMPANY
SP1600027 / CONSTRUCTION
1st, 2nd 3rd, and 4th extension to permit SP1300053 to expire 6 / 18 / 2016
1200 NEW JERSEY AVE SE 20024   
05/26/16 
JBG COMPANIES / JBG COMPANIES; KRISTINA DELGADO
B1605873 / CONSTRUCTION
Renovations to office space on 3rd floor. Approx. 2000SF.
300 TINGEY ST SE 1ST/2ND   
05/11/16 
FC BOILERMAKER LLC / WILLIAM P SAUREST
P1606136 / SUPPLEMENTAL
300 TINGEY ST SE 202   
05/11/16 
FC BOILERMAKER LLC / WILLIAM P SAUREST
P1606138 / SUPPLEMENTAL
300 TINGEY ST SE   
05/11/16 
FC BOILERMAKER LLC / ALBERT E. WILLIAMS
M1602037 / SUPPLEMENTAL
   
05/11/16 
FC BOILERMAKER LLC / ALBERT E. WILLIAMS
M1602039 / SUPPLEMENTAL
355 WATER ST SE   
05/18/16 
PAUL GRUBER NEW BELGIUM BREWING COMPANY
TN1600129 / CONSTRUCTION
Special Event Tour de Fat 1 36x24 stage 5 20x20 tents 1 20x20 hexagon tent No generators
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Capitol ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2016 JD.