I mentioned a few weeks ago that it would be happening soon, and indeed, L Street through Canal Park at 2nd Street SE is now open, with the sidewalk on the south side of the street available for pedestrians.
With this access available, K Street has now been temporarily closed to complete its streetscape. Since the park is still on schedule to open in November, it's likely that K Street will reopen by then.
I'd post pictures of the new vistas on L, but I can't stand any more cloudy-day shots of that location (such as this one from my visit inside the fences in late July), so it'll have to wait for the sun to come out.

Comments (8)
   
 
 More About Canal Park
 All posts: Canal Park

JDLand.com Home

Comments

Erik says: (8/21/12 8:02 AM)
The park would be so much safer for families and pets, and more relaxing if we were to keep K & L streets closed to automobile traffic.


conngs0 says: (8/21/12 1:26 PM)
My understanding is that both K and L Streets will be engineered to slow the flow of traffic. Is that correct? I absolutely appreciate the point that motor vehicle traffic can be hazardous to pedestrians and pets, but perhaps this is worth a try for now in order to avoid some of the negative consequences of closing them down altogether. I'd hate to see the park become a three-block-long barrier to people moving through the neighborhood in order to get to residential buildings and other establishments (including the Park Tavern). In the meantime, Teague Park will also be an option for people to bring their kids and pets in the event they are concerned about traffic (just make sure your Labrador doesn't take a running leap into the Anacostia!).


JD says: (8/21/12 1:42 PM)
You can already see how L Street within the park is much narrower than on either side, and how the streetscape is slightly raised and paved with paving blocks rather than asphalt, all of which are to give drivers the visual heads up to slow down. The fact that cars can't park on K or L within the park will also clear the line of sight for cars to see where people might be waiting to cross.

But, that said, pedestrians will always need to cross carefully.

It's unrealistic to have both streets permanently closed in that spot, forcing all cross-neighborhood traffic onto either I or M.


conngs0 says: (8/21/12 2:45 PM)
Thanks, JD!

I really love that a bar/restaurant will be incorporated into the southern end of the park too. The Park Tavern's existence should keep foot traffic flowing in the park well into the evening hours, which should hopefully cultivate a lively atmosphere in the neighborhood as well as maintain safety. Hopefully it takes off.

But you can't deny that the northern end of Canal Park is going to be pretty sleepy for a couple of years until some of those planned apartment and mixed-use buildings are up and running. That will be nice in the daytime, as some people will want to enjoy some peace and quiet. But hopefully the cross-neighborhood traffic will help keep things illuminated at night (or at least provide the police with better access during patrols).


JD says: (8/21/12 2:48 PM)
Don't forget that the new official entrance for 225 Virginia/200 I is going to be right across from the park's north end, coming this fall. So there will be foot traffic in terms of the office workers and the four DC agencies that will be moving there. And probably security officers guarding that entrance who might also look across the street once in a while. :-)



JES says: (8/22/12 9:57 AM)
I'm kind of on the fence on opening those roads to traffic. Whenever you let traffic into some place, it's very rare to then revoke that vehicle access after the fact, so I'd almost be inclined to leave it pedestrian-only for a while, at least until some of the other buildings are built over there. It seems like people have managed just fine without those roads for a while, right? Why not try to keep it going, and if it doesn't work out once more buildings come online, change it then?


Maelstrom says: (8/22/12 3:45 PM)
I am annoyed that inside of those nice marble curbs on the west side of 2nd place SE they just filled in a bunch of asphalt. Did they run out of paving stones or something? It's ugly >_<! Anyone else notice this? I hope they only did it because they expect it to be torn up for the buildings on between 2nd PL and 3rd St.


David Garber says: (8/23/12 9:54 AM)
The asphalt sidewalks are "temporary" -- that is, until the blocks east of Canal Park are developed. Redevelopment of those blocks by DC Housing and their future development partners would damage or force-replace any fancier paving that might have been installed now, hence the asphalt. The tree pits and light poles will stay.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

caphillguy on Some Details on: Walked by Dacha today and the park in front was being torn up. Is that going to...
jdc on Some Details on: The short walls around the former GSA warehouse are coming down/are down, so I g...
JD on Some Details on: I think Splash is staying open going forward until they aren't. I believe that t...
NavyYardNittany on Some Details on: "Lambau88 says: (2/19/19 1:38 PM) The person behind the counter at Splash ...
VelocityChris on Some Details on: I'll take it! (Wells Fargo ATM)
RMP on Some Details on: My guess is that an "Express Center" is a room with ATMs and no humans...
  
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1300 B/O WATER ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/18/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/17/19
400 B/O 2ND ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 02/16/19
70 B/O I ST SE   ASSAULT WITH A DANGEROUS WEAPON  02/15/19
500 B/O L ST SE   ROBBERY  02/14/19
1400 B/O SOUTH CAPITOL ST   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 02/13/19
1100 B/O 2ND PLACE SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 02/13/19
200 B/O I ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 02/13/19
200 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/11/19
100 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/10/19
500 B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 02/09/19
1200 B/O HALF ST SE   THEFT
Theft First Degree (theft From Building)
 02/07/19
300 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 02/07/19
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/05/19
1000 B/O 8TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 02/04/19
1100 B/O 1ST ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 02/02/19
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 01/25/19
900 B/O M ST SE   ROBBERY  01/25/19
100 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 01/24/19
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 01/24/19

Recent Issued Building Permits Archive  
4 I ST SE   
01/31/19 
USGBF WATERFRONT STATION LLC / TAMIKA STATON; OTIS
EN1900813 / SHOP DRAWING
Install 2 New Elevators - 3500LBS @ 350FPM
   
01/31/19 
USGBF WATERFRONT STATION LLC / TAMIKA STATON; OTIS
EN1900814 / SHOP DRAWING
Install 1 New Elevator - 4000LBS @ 350FPM
2 I ST SE   
01/28/19 
MCDONALDS CORPORATION / ROGER LEE MOORE
M1901295 / SUPPLEMENTAL
   
01/30/19 
MCDONALDS CORPORATION / null
E1903887 / SUPPLEMENTAL
150 I ST SE   
01/31/19 
WILLIAM C SMITH CO / TAMIKA STATON; OTIS
EN1900205 / SHOP DRAWING
Install 1 New Elevator - 3500LBS @ 350FPM
   
01/31/19 
WILLIAM C SMITH CO / TAMIKA STATON; OTIS
EN1900206 / SHOP DRAWING
Install 2 New Elevators - 3500LBS @ 350FPM
   
01/31/19 
WILLIAM C SMITH CO / TAMIKA STATON; OTIS
EN1900207 / SHOP DRAWING
Install 1 New Elevator - 3500LBS @ 350FPM
   
01/31/19 
WILLIAM C SMITH CO / TAMIKA STATON; OTIS
EN1900208 / SHOP DRAWING
Install 1 New Elevator - 4000LBS @ 350FPM
   
01/31/19 
WILLIAM C SMITH CO / TAMIKA STATON; OTIS
EN1900209 / SHOP DRAWING
Install 1 New Elevator - 3500LBS @ 200FPM
   
02/04/19 
SQUARE 737 LLC / RUSSELL M COX
B1904148 / CONSTRUCTION
THIS PERMIT SERVES AS A REVISION TO B1709058 FOR ELEVATOR REVIEW ONLY
   
02/19/19 
SQUARE 737 LLC / DANIEL R. RUDE
P1903909 / SUPPLEMENTAL
(4) Fire pits (1) Water Coolers (4) Rooftop units Sanitary piping, Storm piping
   
02/21/19 
WILLIAM C SMITH CO / null
E1904635 / SUPPLEMENTAL
250 M ST SE   
01/29/19 
SQ 769 LLC / ILAKKIYA THAMBI
AH1900470 / CONSTRUCTION
Requesting after hour permit to CCTV the sewers
   
02/01/19 
SQ 769 LLC / ILAKKIYA THAMBI
AH1900481 / CONSTRUCTION
After hour permit to CCTV the sewers
   
02/15/19 
SQUARE 769 LLC / STEVEN CHEN
AH1900542 / CONSTRUCTION
After Hours Permit - Drilling of Piles
   
02/15/19 
SQUARE 769 LLC / JENSEN HUGHES
MVQ1900481 / CONSTRUCTION
NFPA 20 2010 EDITION, SECTION 4.12.2.1.1 AS REFERENCED BY 2012 IBC CODE SECTION 913.1. BUILDING PERMIT B1813732
   
02/21/19 
SQUARE 769 LLC / BRIAN C STROTT
B1813732 / CONSTRUCTION
9 story office building with 3 levels below grade. 188,000 gross sqft
861 NEW JERSEY AVE SE   
02/05/19 
CONSOLIDATED RAIL CORPORATION / THOMAS M. KESSLER
P1903515 / SUPPLEMENTAL
(2) Gas generators
880 NEW JERSEY AVE SE   
02/21/19 
880 NEW JERSEY AVENUE LLC / CLYDE HURST; CHRISTOPHER P COWIE
B1901729 / CONSTRUCTION
alterations to an existing 688 SF vacant space to add mechanical, plumbing and electrical fixtures to accommodate a future tenant. Future tenant fit out will be provided under a separate permit. This permit is for the landlord work only. The existing space is recently constructed building shell that has not been occupied by a previous tenant.
520 TINGEY ST SE   
02/01/19 
BROOKFIELD PROPERTIES / MAHMOUD KHACHAN
SB1900114 / CONSTRUCTION
Three soil borings, six-inch diameter, 25 feet deep.
227 TINGEY ST SE   
01/31/19 
FOREST CITY WASHINGTON / TAMIKA STATON; OTIS
EN1900809 / SHOP DRAWING
Install 1 New Elevator - 3500LBS @ 350FPM
   
01/31/19 
UNITED STATES OF AMERICA / TAMIKA STATON; OTIS
EN1900802 / SHOP DRAWING
Install 1 New Elevator - 3500LBS @ 350FPM
   
01/31/19 
UNITED STATES OF AMERICA / TAMIKA STATON; OTIS
EN1900803 / SHOP DRAWING
Install 1 New Elevator - 3500LBS @ 350FPM
   
01/31/19 
FOREST CITY WASHINGTON / TAMIKA STATON; OTIS
EN1900807 / SHOP DRAWING
Install 1 New Elevator - 3500LBS @ 350FPM
   
01/31/19 
UNITED STATES OF AMERICA / TAMIKA STATON; OTIS
EN1900808 / SHOP DRAWING
Install New Elevator - 4000LBS @ 350FPM
   
01/31/19 
UNITED STATES OF AMERICA / TAMIKA STATON; OTIS
EN1900799 / SHOP DRAWING
Install 1 New Elevator - 3500LBS @ 200FPM
   
01/31/19 
UNITED STATES OF AMERICA / TAMIKA STATON; OTIS
EN1900800 / SHOP DRAWING
Install 1 New Elevator - 3500LBS @ 200FPM
   
01/31/19 
FOREST CITY WASHINGTON / TAMIKA STATON; OTIS
EN1900806 / SHOP DRAWING
Install 2 New Elevators - 3500LBS @ 200FPM
   
02/08/19 
UNITED STATES OF AMERICA / DFM DEVELOPMENT SERVICES, LLC
B1901392 / CONSTRUCTION
Yards Parcel L1 - Revision to Building Permit # B1801074 to add build-out of hotel restaurants and bars, and to incorporate changes required by DC Water. Includes 1st floor restaurant with 132 indoor seats and 48-seat Summer Garden;1st floor bar with 59 seats and 24-seat Summer Garden; Rooftop Bar with 48 indoor seats; Rooftop restaurant with 67 indoor seats and 48-seat Summer Garden. TPR
   
02/08/19 
FOREST CITY WASHINGTON / DFM DEVELOPMENT SERVICES, LLC
AH1900513 / CONSTRUCTION
Yards Parcel L-2. Afterhours permit for the purpose of dismantling the tower crane on private property. Work to take place Friday, 2 / 8 / 19 and Saturday 2 / 9 / 19 between 7pm-10pm as well as Sunday, 2 / 10 / 19 between 10am-7pm.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
1117 3RD ST SE   12/06/18
$ 5,000,000
SQUARE 769 LLC WILLIAM C SMITH & CO INC
 


Project Directory
Completed
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2019 JD.