At Monday's ANC 6D meeting, representatives of MRP Realty made a presentation showing the updates to the RiverFront on the Anacostia project (aka Florida Rock) that they will be taking to the Zoning Commission later this year.
These designs are part of the quest to make changes to the original design approved by the commission in 2008, chief of which is to switch the first phase of the 1.1-million-square-foot mixed-use project from an office building to a 300ish-unit apartment building at 1st Street and Potomac Avenue, along with a series of other changes that I've written about previously. (Dear heavens, don't make me write it all again.)
Here are the slides that were presented by the developers, which should be of interest even without the accompanying narration. The renderings are much more detailed and "showier" than those given to the Zoning Commission back in February, which was part of what the developers were tasked with providing in their next go-round with the ZC.
Most obviously, the developers appear to have gotten the "more retail!" message that had been delivered pretty clearly at the last two zoning commission sessions on the new design, with 18,650 square feet of retail now covering most of the first floor of the Phase I residential building, bumped up from 12,520 sf in the previous version (some of which the developers had been wanting to mark off for "temporary resident uses" until the market for retail in the area could be proven). The entire site is now designed to have 48,360 sf of retail, but this is still down from the 64,200 sf that was in the plans approved by the Zoning Commission back in 2008. (This increase in retail also means that the "four red doors" facing Potomac Avenue that sent zoning commissioner Michael Turnbull through the roof back in February are now gone.)
There was also much time spent on the designs for the public spaces that span the 5.5-acre site. With large lawns, wetlands-type areas that would actually be bio-filtration mechanisms, quieter tree-covered spaces, and a marina that could potentially have 40-50 slips, the additions could be seen as echoing the Yards Park a couple blocks to the east.. But there are also some "beach" areas where sand would be placed, and a large sculpture could be included in the "Riverfront Plaza" at the foot of 1st Street. The esplanade is still a major part of the design, but there is no longer a separate bike path--pedestrians and cyclists would share the boardwalk as it runs through the entire site, from South Capitol Street to Diamond Teague Park. And there may even be locations where some of the concrete blocks from the old concrete plant site would be incorporated into the public spaces.
I could write more about the specifics, but since the project will be back in front of ANC 6D looking for a resolution of support in July, and then at the Zoning Commission on Sept. 20, I'd prefer to save some words for the presentations to come.
I've added some of the renderings from this presentation to my Florida Rock project page. And, when looking at all of this, remember that the western two buildings (phases 3 and 4, an office building and a hotel), are not be able to be built until the new South Capitol Street/Douglass Bridge is built a bit to the south of the current bridge, which now runs directly through the Florida Rock footprint. And there's as yet no timeline for that new bridge.
Comments (3)
   
 
 More About ANC News

JDLand.com Home

Comments

ZoolanderANDtheBoYz says: (5/16/12 11:30 AM)
This looks way much better than the first rendered design. I love the whole idea of beach and volley ball.
Is there any time table when they are going to start working on the new South Capitol Street/Douglass Bridge?


JD says: (5/16/12 11:42 AM)
As soon as they get the money. Altogether, with all of the additional work they want to do at the same time (new ramps/connections to both the SE/SW Freeway and to I-295), it's about a $800 million project. link



Sophia Monster says: (5/16/12 3:56 PM)
Sand from wall to wall. I know a great sand guy, we'll get it at price.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Top News
  

JD on Willow Opening on: Oh dear God, people, dial it back....
goldfish on Willow Opening on: CJ -- if you want to start a fight, an ethnic slur is perfect for the job. It on...
202_cyclist on Willow Opening on: Fair enough-- BANANA works. "Build Absolutely Nothing Anywhere Near Anythi...
CJBabyDaddy on Willow Opening on: One should not use ethnic slurs — even rarely. On the other hand, cuss up a blu...
goldfish on Willow Opening on: I'm with Walt. And I think the word "NIMBY" is pejorative and should be used rar...
Message Board (beta)

Get JDLand Updates In Your Inbox!


Thousands and thousands of photos showing the neighborhood changing. More than 150 buildings no longer with us. All the news, since 2003. Photos from various archives showing the neighborhood in the more distant past. Maps from the early 1900s. Overhead Photo Comparisons: 1949, 1988, 2002-2008. All Blog Entries, 2003 - Present Major Events, 1799 - Present A series of blog entries looking at the neighborhood's history.
Near Southeast's Rearview Mirror


City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
70 B/O I ST SE   BURGLARY
Burglary Two
 11/16/17
1200 HALF ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/15/17
1100 B/O 1ST ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 11/14/17
1100 B/O NEW JERSEY AVE SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 11/13/17
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (theft From Building)
 11/12/17
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/12/17
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/09/17
1100 B/O NEW JERSEY AVE SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 11/06/17
1200 SOUTH CAPITOL ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/05/17
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/05/17
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (theft From Building)
 11/01/17
100 B/O K ST SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 10/30/17
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 10/29/17
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/27/17
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/25/17
100 B/O K ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/21/17
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/19/17
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 10/19/17
1400 B/O SOUTH CAPITOL ST   ROBBERY  10/18/17

Recent Issued Building Permits Archive  
1100 2ND PL SE   
10/26/17 
null / KENNETH J. LEMERE
E1800879 / SUPPLEMENTAL
   
11/02/17 
BAKER DC / CHRISTINE LONG
AH1800167 / CONSTRUCTION
An after hours permit is respectfully requested from 5AM to 8PM daily
1331 2ND ST SE 20003   
10/30/17 
DC WATER / DAVE LEVINE
AH1800128 / CONSTRUCTION
After Hours work for structure excavation and support for B1311474 DC Water, Corman Construction 301-343-5417.
1331 4TH ST SE CU   
11/02/17 
FC 1331 LLC / null
E1801120 / SUPPLEMENTAL
1023 4TH ST SE   
11/06/17 
MATTHEW E WEINER
BP1800535 / POST CARD
1331 4TH ST SE   
11/14/17 
FC 1331 LLC / PAUL E WARREN
E1801475 / SUPPLEMENTAL
1346 4TH ST SE   
11/07/17 
ALAN OWINGS / ROBERT HENRY
AH1800169 / CONSTRUCTION
After Hours Permit for 11 / 10 / 17 from 7am to 7pm to perform concrete operations.
1015 HALF ST SE 7TH FL   
10/31/17 
HALF STREET SE LLC / null
P1800798 / SUPPLEMENTAL
1015 HALF ST SE   
10/23/17 
HALF STREET SE LLC / null
E1800739 / SUPPLEMENTAL
   
10/23/17 
HALF STREET SE LLC / null
M1800233 / SUPPLEMENTAL
   
10/23/17 
HALF STREET SE LLC / null
P1800599 / SUPPLEMENTAL
303 K ST SE   
10/22/17 
JONATHAN HERSHEY / null
P1800573 / SUPPLEMENTAL
555 L ST SE   
10/31/17 
UNITED STATES OF AMERICA / EDUARDO L. LOPEZ
E1801004 / SUPPLEMENTAL
   
11/08/17 
UNITED STATES OF AMERICA / null
P1801050 / SUPPLEMENTAL
   
11/08/17 
UNITED STATES OF AMERICA / null
M1800409 / SUPPLEMENTAL
80 M ST SE #110 20003   
11/03/17 
WELLS REIT II 80 M STREET LLC / null
P1800898 / SUPPLEMENTAL
300 M ST SE 402   
10/30/17 
FEDERAL CENTER LP / null
E1800973 / SUPPLEMENTAL
300 M ST SE STE# 402   
11/01/17 
FEDERAL CENTER LP / BERNARD CHAPPELL
E1801037 / SUPPLEMENTAL
110 M ST SE   
11/10/17 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / JIM RILEY
BP1800623 / POST CARD
922 M ST SE   
10/27/17 
MAIFEDI EQUITY LLC / FRED LATIMORE
E1800926 / SUPPLEMENTAL
1333 M ST SE   
11/03/17 
1333 M STREET SE LLC / JUSTIN BELLOW
B1801393 / CONSTRUCTION
Installation of duct bank and light pole on private property
800 NEW JERSEY AVE SE   
11/13/17 
SQUARE 737 LLC / N/A; BOB BIROONAK
SG1800066 / CONSTRUCTION
one apartment id sign illuminated
861 NEW JERSEY AVE SE   
10/30/17 
CSX TRANSPORTATION, INC. / NA CSX TRANSPORTATION, INC.
AH1800132 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Reconstruction Project LOD for utility, demolition, and concrete structure construction activities.
1000 NEW JERSEY AVE SE   
10/26/17 
null / NA NA NA
EHOP17919268 / HOME OCCUPATION
1100 NEW JERSEY AVE SE   
11/03/17 
SQUARE 742 LLC / null
E1801147 / SUPPLEMENTAL
   
11/08/17 
SQUARE 742 LLC / null
E1801323 / SUPPLEMENTAL
1244 SOUTH CAPITOL ST SE 20003   
11/02/17 
THE JBG COMPANIES / CODY LANG
AH1800140 / CONSTRUCTION
The location for the project is at the corner of South Capitol Street, SE and N Street, SE, to the North of Parking Lot B for the Washington Nationals Stadium. The permit numbers to reference are B1600228, PA10464330, PA115172-R2, and PA202883. These permits are attached for reference. In order to maintain our contractual requirements and progress with critical path interior finishes, rooftop bu...
1244 SOUTH CAPITOL ST SE   
10/31/17 
THE JBG COMPANIES / GLENNWOOD ROGERS
FB1800009 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2017 JD.