Moving from the "P" portion of Monday's ANC 6D meeting (pylons and parking) to the "C"s:
* Canal Park: Chris Vanarsdale of the Canal Park Development Association gave an update on construction, the bottom line of which has not changed from what's been mentioned the past few months, that because of unexpected issues, the park's opening has been delayed until November. Unmapped utilities that required a redesign of the stormwater management system have been a big stumbling block, but Vanarsdale also mentioned the soil-related difficulties when building on the site of an old canal. Construction is now 60 percent complete, and the work on the pavilion is almost done. Here are the presentation slides, and you can also check out the official web site for more details (along with my project page). Oh, and they're thinking about offering Zamboni driving lessons!
* Community Center: The DC Housing Authority has filed a request with the Zoning Commission for an extension for construction of the planned Capper Community Center, which already received one extension back in 2010 that 6D supported. DCHA has apparently requested that the Zoning Commission act within 30 days on the request, news of which the ANC received on Monday. So the commissioners voted unanimously to send a letter urging postponement of the zoning case so that the ANC can address the request and form a response with a vote at next month's meeting. Commissioners Litsky and McBee also both commented that the project shouldn't be getting another extension.
UPDATE: Here is the letter sent on behalf of DCHA to the Zoning Commission asking for the extension: it would be for two years, requiring building permits by July 1, 2014 and construction underway by July 1, 2015.
* CSX/Virginia Avenue Tunnel: The commissioners voted 6-0-1 to send this letter to the appropriate parties laying out the ANC's opinion on the plans to reconfigure the Virginia Avenue Tunnel. After listing the various ways that the proposed construction "would put people, homes, businesses, and fragile historic resources at risk," the letter states: "[W]e strongly believe that the best options for our community are for CSX to either leave the Virginia Avenue Tunnel in its current state (Concept 1) -- with the suggestion that if this option were chosen that the tunnel would be fully maintained for the safety of both the trains below and the communities above, or to reroute additional train traffic outside the District of Columbia [...] instead of in an expanded Virginia Avenue Tunnel." But, if the construction does occur, "it is absolutely imperative that the health and safety of our many residents, the economic and physical well-being of our businesses, parks, religious institutions, homes, and historic buildings, and the north-south access for all existing modes of transportation be preserved and enhanced." A number of Capitol Quarter residents in attendance also spoke in support of the ANC's support. The next public meeting on the plans for the tunnel will be May 21 at 6:30 pm at Nats Park.
One more recap post to go, probably tomorrow.
Comments (6)
   
 
 More About Canal Park

JDLand.com Home

Comments

Alex B. says: (5/15/12 1:48 PM)
160,000,000
4,000,000,000


Alex B. says: (5/15/12 1:48 PM)
160,000,000
4,000,000,000


Alex B. says: (5/15/12 1:51 PM)
Whoops! Apologies for the erroneous posts.

Just wanted to compare the costs of replacing the VA Ave tunnel in place (CSX estimated those at $160 million in 2010) and the costs of one of NCPC's bypass options (range $3.2-5.3 billion - split the difference and call it ~$4 billion).

$160,000,000
$4,000,000,000

That's a big difference.



JD says: (5/15/12 1:52 PM)
Whew, I thought you were being really snippy about a typo or something!


JES says: (5/15/12 2:20 PM)
Anyone else not realize until now how friggin' huge that ice rink is gonna be?


The Hoff says: (5/16/12 7:35 PM)
I'm with you, JES. I guess I figured that with a rink management company lined up it was going to be big enough to need it but I could never really picture it. It's going to be pretty great when it's all said and done.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Top News
  

kalicki on A Photo Tour: I generally like the style of this building, but man, the white lights on the fa...
conngs0 on A Photo Tour: Whoops! I don't know how I jumped to full replacement! Sorry! Regardless, kee...
JD on A Photo Tour: Not a hip replacement! Had to have the torn labrum repaired and the head of the ...
conngs0 on A Photo Tour: Thanks for the update, JD! I know you've been waiting for a cell phone store fo...
Message Board (beta)

Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 02/22/18
400 B/O M ST SE   THEFT
Shoplifting
 02/21/18
UNIT B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 02/19/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/15/18
1000 B/O 3RD ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/07/18

Recent Issued Building Permits Archive  
1100 2ND PL SE   
02/21/18 
BAKER DC / CHRISTINE LONG
AH1800618 / CONSTRUCTION
An after hours permit is respectfully requested from 5AM to 9PM daily
1331 2ND ST SE 20003   
01/29/18 
DC WATER / DAVE LEVINE
AH1800505 / CONSTRUCTION
After hours work for structure exaction and support for B1311474 DC Water. Corman Construction 202-863-0052.
1016 3RD ST SE   
02/01/18 
ANAMARIA R MOTTOLA / DAVID L. HAHN
P1803348 / SUPPLEMENTAL
1346 4TH ST SE   
02/06/18 
ALAN OWINGS / ROBERT SEV HENRY
AH1800541 / CONSTRUCTION
After Hours Permit for 2 / 19 / 18 from 7AM to 7PM to perform concrete, framing, and utility operations.
   
02/06/18 
FC 1346 LLC / RICHARD V CAREY
P1803428 / SUPPLEMENTAL
150 I ST SE   
02/05/18 
WC SMITH / null
P1803402 / SUPPLEMENTAL
140 M ST SE   
02/07/18 
SPAULDING & SLYE/STE100 / null
E1803798 / SUPPLEMENTAL
110 M ST SE   
01/29/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / JAMES WEAVER
E1803534 / SUPPLEMENTAL
   
02/02/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
P1803361 / SUPPLEMENTAL
140 M ST SE 20032   
02/14/18 
SYLVIA LINDSEY / null
P1803641 / SUPPLEMENTAL
202 M ST SE   
01/29/18 
UNITED STATES OF AMERICA / NURI EROL
D1800281 / CONSTRUCTION
Remove Existing flooring. Remove some of the furnitures, equipment.
300 M ST SE 53533   
02/08/18 
FEDERAL CENTER LP / SPENCER TEEL
BP1801893 / POST CARD
300 M ST SE   
02/16/18 
FEDERAL CENTER LP / STEVEN MERCHANT
B1803279 / CONSTRUCTION
New Sprint store sustainable design tenant build-out in an existing building, partical first floor. Work will consist of building a new sales floor and back of the house. New work sill consist of display fixtures, ceiling, plumbing fixtures, mechanical ductwork to diffusers, interior partitions, floor finishes, outlets and new locations of electrical panels. **CHANGE IN USE, LEVEL 2 ALTERATION
401 M ST SE   
01/30/18 
DOEE C/O DEV MURALI / JESSICA REICHARD
AH1800507 / CONSTRUCTION
After hours permit to preform manhole inspections during off peak hours 7pm - 7am for all Manhole Locations covered under permit # PA10374319-R1 for DOEE Anacostia river sediment project.
861 NEW JERSEY AVE SE   
01/31/18 
CONSOLIDATED RAIL CORPORATION / NA CSX TRANSPORTATION, INC.
AH1800467 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities.***TO EXCLUDE LEGAL HOLIDAYS**
1100 NEW JERSEY AVE SE 2ND FL   
02/09/18 
SQUARE 742 LLC / null
P1803534 / SUPPLEMENTAL
   
02/14/18 
SQUARE 742 LLC / null
P1803681 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
02/15/18 
SQUARE 742 LLC / null
E1804057 / SUPPLEMENTAL
79 POTOMAC AVE SE   
02/21/18 
RIVERFRONT HOLDINGS I LLC / JUSTIN BELLOW
B1805358 / CONSTRUCTION
Address revision only for B1702971 from 25 Potomac Ave SE to 79 Potomac Ave SE.
640 SOUTH CAPITOL ST SE   
02/05/18 
JIM LATISIS ZAYO GROUP
B1707197 / CONSTRUCTION
Addition to existing concrete telecom building.
401 TINGEY ST SE   
01/30/18 
PEPCO / BARBARA ANN STEDMAN
AH1800520 / CONSTRUCTION
UG TRANSFORMER WORK TO BE PERFORMED ON THE 400 BLK OF TINGEY ST SE. MANHOLE ACCESS. WORK TO BE PERFORMED BETWEEN THE HOURS OF 7:30AM AND MIGHTNIGHT ON 1 / 30 / 18 AND 1 / 31 / 18.
227 TINGEY ST SE   
01/29/18 
UNITED STATES OF AMERICA / ERICKA CLARK
TC1800021 / CONSTRUCTION
2 tower cranes
   
01/30/18 
FOREST CITY WASHINGTON / MELISSA DIAZ
B1802750 / CONSTRUCTION
Revision to Permit SH1700028. Sheeting and shoring for Yards Parcel L-2 project. Revision includes 10-foot precut excavation and layback on Water Street, 3rd Street and northern L-1 elevations, and removal of upper tier of rakers at L-1 elevation and upper tier of tiebacks at the Water Street and 3rd Street elevations.
   
02/20/18 
FOREST CITY WASHINGTON / FOREST CITY WASHINGTON; DFM DEVELOPMENT SERVICES
FD1700057 / CONSTRUCTION
Yards parcel L-2. Construction of foundation and underground parking garage for new 11 story multi-family mixed used residential building at 227 Tingey Street SE as part of development of Parcel L at the Yards
325 VIRGINIA AVE SE 20003   
02/14/18 
JASON W GOLDSMITH / null
E1804039 / SUPPLEMENTAL
325 VIRGINIA AVE SE   
02/06/18 
JASON W GOLDSMITH / CRAIG HARTSOCK
B1804721 / CONSTRUCTION
Remove two non-structural walls on ground level of townhouse and re-frame in new configuration to create a full bathroom on ground floor.
   
02/07/18 
JASON W GOLDSMITH / MORIS O. OCHOA PINEDA
P1803462 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
1001 NEW JERSEY AV SE   12/28/17
$ 687,365
WHATS ON SECOND PROPERTIES LLC
 


Project Directory
Completed
Agora ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.