The Marine Corps will be getting the wheels moving again in what has been a stalled quest to build a new barracks and associated support space, putting the word out Wednesday via the project web site and a newsletter that it will be using the National Environmental Policy Act (NEPA) process "to continue the dialogue with the community of stakeholders" going forward. However, it's also now clear that "federal land acquisition will be unavoidable as a result of recent unforeseen changes in policy and a less favorable funding outlook."
In other words, the potential for a public-private development partnership as discussed in the 2010 series of public meetings is falling by the wayside, and the federal government will have to own the land that the new barracks is built on. (Though the Marines say they "will continue to investigate opportunities to collaborate with the District of Columbia to minimize impacts to the local tax base and pursue all viable options[.]")
During 2010, the site selection process had narrowed the slate down to three potential locations: the site of the Bachelor Enlisted Quarters/MBW Annex at 7th and Virginia, the former Exxon site at 11th and M on Square 976, and "Squares 929/930," the two blocks bounded by 8th, Virginia, 9th, and Potomac controlled by multiple landowners, including a joint venture between Madison Marquette and ICP Partners. Wednesday's newsletter, posted by the Washington Business Journal, says that squares 929, 930, and 976 will be analyzed in the environmental impact statement, but that the Annex site is now ruled out for the required 100,000 square feet of housing, though it could be used for the needed 60,000 square feet of "support space."
However, given that there's also mention of analysis of "any additional sites that are identified within 2,000 feet of the MBW Main Post at 8th and I," one wonders if some of the sites ruled out in the original CIMP process might come back to the table, such as the old Capper Seniors site at 7th and M ("Square 882") that the Marines coveted so much given its location just to the south of the Annex, even though the DC Housing Authority officially requested in May 2010 that the Marines stop looking at it. The Virginia Avenue Park would also fall within that 2,000-foot perimeter, but the park's devotees mobilized pretty successfully two years ago when the Marines initially eyed their turf, as did the parents at Tyler Elementary when its playing field was on the original site list.
The Marines do say they are still committed to many aspects of the original CIMP, including working "collaboratively with the community and stakeholders" (and the city), and also to the concept of "[r]educed security standoff distances for the urban environment."
Expect a formal announcement in "late summer" of the NEPA process.
If you haven't been following along (or weren't around in 2010), this site search has all come to pass because Building 20, the fortress just north of the freeway at 8th St. SE, suffers from "serious antiterrorism/force protection and quality of life deficiencies," with reuse of the site ruled out because of the expanded "standoff distances" now required in this War on Terror era. It's those new-era requirements, though, that have many in the area concerned about what sort of negative impacts a new barracks could have on its surroundings. Feel free to browse back through my many posts on the process for more details.
Comments (1)
   
 
 More About Barracks
 All posts: Barracks, Development News

JDLand.com Home

Comments

IMGoph says: (5/4/12 4:35 PM)
please, please, please, don't let the securicrat mentality win. build urban!

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts
  

202_cyclist on Tidbit Roundup: Bom dia! We recently returned from a vacation in Portugal where the beers were ...
RMP on Tidbit Roundup: Ice Cream Jubilee is making a 100-foot long Sundae on July 21st. https://www.eve...
RMP on Tidbit Roundup: Opening night at Schilling was overall very good. They have some kinks to work o...
jdc on Tidbit Roundup: I saw the pricing - seems extraordinarily high, even if the food is very good.
CJBabyDaddy on Tidbit Roundup: Dined at Shilling tonight. If the oysters, gnocchi, soft shell crab and corn ca...
Ampersand on Tidbit Roundup: Last Friday my girlfriend and I were walking past Shilling on our way to Conte's...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
100 B/O H ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 07/14/19
300 B/O TINGEY ST SE   ASSAULT WITH A DANGEROUS WEAPON  07/14/19
900 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (theft From Building)
 07/09/19
300 B/O TINGEY ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/09/19
1100 B/O NEW JERSEY AVE SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 07/08/19
300 B/O K ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/05/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 07/03/19
1200 B/O VAN ST SE   THEFT
Theft First Degree (all Other Larceny)
 07/02/19
700 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/02/19
54 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 06/28/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 06/24/19
300 B/O K ST SE   HOMICIDE
Murder I
 06/22/19
50 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 06/21/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 06/21/19
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 06/20/19
100 B/O H ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 06/19/19
400 B/O M ST SE   THEFT
Shoplifting
 06/19/19
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (theft From Building)
 06/18/19
400 B/O M ST SE   THEFT
Shoplifting
 06/17/19
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (theft From Building)
 06/16/19
50 B/O M ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 06/16/19

Recent Issued Building Permits Archive  
1100 2ND PL SE   
06/25/19 
SQUARE 769N OWNER LLC / THANOS VOREAS
EG1903573 / POST CARD
1212 4TH ST SE   
06/27/19 
FC 1212 LLC / MARK J. RHOTON
E1908902 / SUPPLEMENTAL
1000 5TH ST SE   
07/10/19 
JW ELECTRIC SERVICE / null
E1909222 / SUPPLEMENTAL
   
07/03/19 
UNITED STATES OF AMERICA / TANYA HILL; ALI NAIM
B1911904 / CONSTRUCTION
INSTALL NEW PARTITION AND DOOR IN EXISTING CLASSROOM TO MAKE TWO CLASSROOMS.
100 M ST SE   
06/19/19 
PARSONS / KENNY MERINO; NA
B1908795 / CONSTRUCTION
Interior Demolition and Renovation to 684 Sq Ft of work in order to reduce suite space.
   
07/12/19 
SQUARE 743 INC / KIM MITCHELL
D1900787 / CONSTRUCTION
INTERIOR DEMOLITION WITHIN AN OFFICE SPACE ON THE 9TH FLOOR (MULTI-TENANT FLOOR) IN AN EXISTING OFFICE BUILDING
250 M ST SE   
06/26/19 
BAKER DC LLC / CHRISTINE LONG
AH1901008 / CONSTRUCTION
An after hours permit is respectfully requested from 3AM to 7AM daily
139 N ST SE 20024   
07/12/19 
UNITED STATES OF AMERICA / PAUL E WARREN; PAUL E WARREN
E1909292 / SUPPLEMENTAL
640 SOUTH CAPITOL ST SE   
07/12/19 
CONSOLIDATED RAIL CORPORATION / HARIF BALOGUN; GEOCAPITAL ENGINEERING LLC GEOCAPITAL ENGINEERING
SB1900354 / CONSTRUCTION
We propose drilling six (6), six-inch diameter geotechnical test borings (B-1 to B-6) using the hollow stem auger method to evaluate the subsurface conditions. The proposed test boring depths will be 85 feet below the existing ground surface. If a confining unit is encountered, outer casing will be installed which will extend 10 feet into the top of the confining unit or to the top of bedrock.
300 TINGEY ST SE 170   
07/09/19 
FC BOILERMAKER LLC / GERALD ROPER
B1814633 / CONSTRUCTION
INTERIOR DEMOLITION AND RENOVATION ONLY. DEMOLITION TO INCLUDE REMOVAL OF EXISTING PARTITIONS, KITCHEN EQUIPMENT, AND FINISHES. NEW WORK TO INCLUDE NEW PARTITIONS, MILLWORK, FINISHES, KITCHEN EQUIPMENT (INCLUDING 1 NEW HOOD), AS WELL AS MINOR INTERIOR-ONLY MECHANICAL AND ELECTRICAL MODIFICATIONS. HVAC EQUIPMENT ON EXISTING OUTDOOR MECHANICAL MEZZANINE TO REMAIN. NO MODIFICATIONS TO EXISTING HISTO...
300 TINGEY ST SE   
06/26/19 
FC BOILERMAKER LLC / ADAM C. MARSON
M1903231 / SUPPLEMENTAL
   
07/12/19 
FC BOILERMAKER LLC / DOMINIC E TOTARO; DOMINIC E TOTARO
M1903450 / SUPPLEMENTAL
355 WATER ST SE   
07/10/19 
UNITED STATES OF AMERICA / JOHANNA DELONY
TN1900122 / CONSTRUCTION
Sterne Kessler Crab Feast--1 40'x 100' tent, with 372' of white picket fencing; no generators.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2019 JD.