February 16, 2006
January 31, 2015
Van at M, Looking North-Northeast (see more)

The Marine Corps will be getting the wheels moving again in what has been a stalled quest to build a new barracks and associated support space, putting the word out Wednesday via the project web site and a newsletter that it will be using the National Environmental Policy Act (NEPA) process "to continue the dialogue with the community of stakeholders" going forward. However, it's also now clear that "federal land acquisition will be unavoidable as a result of recent unforeseen changes in policy and a less favorable funding outlook."
In other words, the potential for a public-private development partnership as discussed in the 2010 series of public meetings is falling by the wayside, and the federal government will have to own the land that the new barracks is built on. (Though the Marines say they "will continue to investigate opportunities to collaborate with the District of Columbia to minimize impacts to the local tax base and pursue all viable options[.]")
During 2010, the site selection process had narrowed the slate down to three potential locations: the site of the Bachelor Enlisted Quarters/MBW Annex at 7th and Virginia, the former Exxon site at 11th and M on Square 976, and "Squares 929/930," the two blocks bounded by 8th, Virginia, 9th, and Potomac controlled by multiple landowners, including a joint venture between Madison Marquette and ICP Partners. Wednesday's newsletter, posted by the Washington Business Journal, says that squares 929, 930, and 976 will be analyzed in the environmental impact statement, but that the Annex site is now ruled out for the required 100,000 square feet of housing, though it could be used for the needed 60,000 square feet of "support space."
However, given that there's also mention of analysis of "any additional sites that are identified within 2,000 feet of the MBW Main Post at 8th and I," one wonders if some of the sites ruled out in the original CIMP process might come back to the table, such as the old Capper Seniors site at 7th and M ("Square 882") that the Marines coveted so much given its location just to the south of the Annex, even though the DC Housing Authority officially requested in May 2010 that the Marines stop looking at it. The Virginia Avenue Park would also fall within that 2,000-foot perimeter, but the park's devotees mobilized pretty successfully two years ago when the Marines initially eyed their turf, as did the parents at Tyler Elementary when its playing field was on the original site list.
The Marines do say they are still committed to many aspects of the original CIMP, including working "collaboratively with the community and stakeholders" (and the city), and also to the concept of "[r]educed security standoff distances for the urban environment."
Expect a formal announcement in "late summer" of the NEPA process.
If you haven't been following along (or weren't around in 2010), this site search has all come to pass because Building 20, the fortress just north of the freeway at 8th St. SE, suffers from "serious antiterrorism/force protection and quality of life deficiencies," with reuse of the site ruled out because of the expanded "standoff distances" now required in this War on Terror era. It's those new-era requirements, though, that have many in the area concerned about what sort of negative impacts a new barracks could have on its surroundings. Feel free to browse back through my many posts on the process for more details.
Comments (1)
 
 More About Barracks
 All posts: Barracks, Development News

JDLand.com Home

Comments

IMGoph says: (5/4/12 4:35 PM)
please, please, please, don't let the securicrat mentality win. build urban!

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed

See All Current News Items | Full Blog Archive

 
 Top News
  
Recent Comments:  
conngs0 on Capper 'Flexibility' Gets: Alex B, I think you've correctly framed the discussion - especially the competin...
Alex B. on Capper 'Flexibility' Gets: <i>A true mixed community with people of different backgrounds, socio-econ...
tspaquin on Capper 'Flexibility' Gets: And it's not the appearance or upkeep of the building that's the greatest concer...
tspaquin on Capper 'Flexibility' Gets: @JHUGrad -- I would give it 15 to 20 years, but of course it will be too late to...



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1000 B/O 5TH ST SE   THEFT F/AUTO
Theft From Auto 1
 02/28/15
400 B/O M ST SE   THEFT
2nd Degree
 02/28/15
100 B/O K ST SE   THEFT F/AUTO
Theft From Auto 1
 02/27/15
1000 B/O 4TH ST SE   THEFT F/AUTO
 02/27/15
100 B/O CANAL ST SE   THEFT
2nd Degree
 02/24/15
1300 B/O 4TH ST SE   THEFT
Theft 1 (Theft F/Building)
 02/19/15
1000 B/O 2ND ST SE   THEFT F/AUTO
 02/18/15
100 B/O K ST SE   THEFT F/AUTO
 02/06/15
UNIT B/O K ST SE   THEFT F/AUTO
 02/01/15

Active Public Space Permits Archive  
No records added or modified in the past two weeks.

Recent Issued Building Permits Archive  
1011 1ST ST SE   
02/12/15 
COLIN CLARK / MICHAEL BIANCO; COLIN CLARK; MITCH PERMUY
E98099105 / SUPPLEMENTAL
1265 1ST ST SE   
02/10/15 
CAPITAL RIVERFRONT HOTEL LLC / JOHN HOMICK
E1502866 / SUPPLEMENTAL
1000 5TH ST SE   
02/24/15 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / KIM MITCHELL CDKM CONSULTING LLC
B1412422 / CONSTRUCTION
NEW BUILDING PERMIT FOR NEW COMMUNITY CENTER INCLUDING STEEL STRUCTURE BRICK AND MASONRY BACKUP
1240 12TH ST SE   
02/19/15 
WASHINGTON GAS LIGHT CO / CARLTON W ROBINSON
E1503465 / SUPPLEMENTAL
909 HALF ST SE   
02/25/15 
23 I LLC C/O RELATED COMPANIES / DAVID MILLER
SB1500157 / CONSTRUCTION
INSTALLATION AND MONITORING OF 8 INCLINOMETER MONITORING SYSTEMS. THREE INCLINOMETER CASINGS TO BE INSTALLED ALONG THE K STREET BORDER OF THE PROJECT. THREE CASINGS TO BE INSTALLED ALONG THE I STREET BORDER OF THE PROJECT. TWO CASINGS TO BE INSTALLED ALONG THE HALF STREET BORDER OF THE PROJECT.
   
02/23/15 
23 I LLC C/O RELATED COMPANIES / 23 I LLC C/O RELATED COMPANIES; ANDREW DANCE
SB1500132 / CONSTRUCTION
A HOLLOW STEM AUGER WILL INSTALL UP TO 30 TEMPORARY DEWATERING WELLS BY ADVANCING A 12 OD / 8 1 / 4 ID BOREHOLE TO A DEPTH OF 65 FEET. AT DEPTH A 4 INCH PVC FLUSH JOINT THREADED WELL ASSEMBLY WILL BE SET AND SELECT FILTER PLACED. INTO EACH WELL WILL BE INSTALLED A 1 HP TURBINE SUBMERSIBLE PUMP. EFFLUENT WILL BE DIRECTED THROUGH A COMMON MANIFOLD TO A BAFFLED SETTLING TANK AND DISCHARGED TO THE LO...
1015 HALF ST SE   
02/09/15 
HALF ST SE LLC /
P1503333 / SUPPLEMENTAL
   
02/12/15 
THOMAS AN / THOMAS AN; HYH ELECTRIC CO. INC.
SG1500156 / CONSTRUCTION
INSTALL ONE SINGLE FACE BUILDING SIGN AND ONE DOUBLE FACE BLADE SIGN
   
02/10/15 
EVAN OBRIEN / JOSEPH ABRESCH; EVAN OBRIEN; ROBERT HUNSBERGER
E74054014 / SUPPLEMENTAL
   
02/18/15 
HALF ST SE LLC / STEPHEN R. HOLMAN
P1503532 / SUPPLEMENTAL
82 I ST SE   
02/09/15 
GREYSTAR RCP DEVELOPMENT / KIM MITCHELL CDKM CONSULTING LLC
SH1400084 / CONSTRUCTION
SHEETING & SHORING WORK FOR NEW 13-STORY RESIDENTIAL PROJECT AT EYE STREET AND NEW JERSEY AVE SE
50 M ST SE   
02/18/15 
ENGLEWOOD LLC / FVI2020
FD1500010 / CONSTRUCTION
FOUNDATION OF GRADE RELATED TO CONSTRUCTION OF A NEW HOTEL
55 M ST SE   
02/24/15 
HINES GLOBAL REIT 55 M STREET LLC / ANDREW P CARAYIANNIS
M1501184 / SUPPLEMENTAL
100 M ST SE   
02/11/15 
SQUARE 743 INC. / JOHN GIUSEPPE-RAMCO
TL1500062 / CONSTRUCTION
FIRST TIME TENANT TO BUILDOUT AND OCCUPY TENANT SPACE ON PART OF THE 7TH FLOOR THE TRUST FOR PUBLIC LAND AS SHOWN ON THE ATTACHED THIRD PARTY REVIEWED AND APPROVED MECH. .PLUMB. ELECT. FIRE PROTECTION AND ARCHITECTURAL PLANS BY KTA. INTERIOR WORK ONLY. NO CHANGE IN USE. NO STRUCTURAL WORK INVOLVED.
   
02/13/15 
SQUARE 743 INC / RONNIE E WRIGHT
E1503331 / SUPPLEMENTAL
   
02/13/15 
SQUARE 743 INC / DAVID FLEMING
P1503495 / SUPPLEMENTAL
   
02/19/15 
SQUARE 743 INC / DAVID FLEMING
P1503597 / SUPPLEMENTAL
   
02/20/15 
SQUARE 743 INC / GREGORY E LIGON
E1503498 / SUPPLEMENTAL
   
02/23/15 
SQUARE 743 INC / ANTHONY G SAMBURG
E1503518 / SUPPLEMENTAL
901 M ST SE   
02/19/15 
US GOVERNMENT NAVY PWC / SUMMIT CONSTRUCTION AND ES
B1504570 / CONSTRUCTION
REQUEST AND E&S PERMIT FOR WORK ON FEDERAL INSTALLATION. INSTALLING FOOTINGS AND SLAB WITH PORTCH SUPPORTS. MINOR GRADING AND SEEDING. BUILDING FOOTPRINT IS UNDER 700SF. LAND DISTURBANCE INCLUDING GRADING AND SEEDING IS UNDER 2 500SF.
100 M ST SE   
02/19/15 
SQUARE 743 INC / JOHN H THOMSON
E1503464 / SUPPLEMENTAL
   
02/20/15 
SQUARE 743 INC / DAVID RAINE; SQUARE 743 INC; DAVID RAINE
P38575591 / SUPPLEMENTAL
300 M ST SE   
02/11/15 
FEDERAL CENTER LP / SAM HOLLEN RAMCO OF DC INC.
B1504255 / CONSTRUCTION
INTERIOR RENOVATION TO 2ND FLOOR CONFERENCE ROOM. PARTITIONS FINISHES MECHANICAL ELECTRICAL AND LIFE SAFETY. ICI SERVICES
1201 M ST SE   
02/11/15 
CSC / DAMON ELLIS
B1503731 / CONSTRUCTION
SCOPE OF WORK AREA IS 800SQFT TO INCLUDE MECHANICAL PLUMBING ELECTRICAL AND FIRE. NO CHANGE OF USE OR STRUCTURAL WORK BEING DONE
800 NEW JERSEY AVE SE   
02/24/15 
NEW JERSEY AT H LLC / JOHN H THOMSON
E1503556 / SUPPLEMENTAL
   
02/13/15 
BAKER DC / CHRISTINE LONG
AH1500246 / CONSTRUCTION
AN AFTER HOURS PERMIT IS RESPECTFULLY REQUESTED FROM 7:00PM THRU 7:00AM
909 NEW JERSEY AVE SE   
02/26/15 
909 NEW JERSEY AVENUE ACQUISITION LLC / DAVID L. HAHN
P1503815 / SUPPLEMENTAL
1000 NEW JERSEY AVE SE   
02/23/15 
CAPITOL HILL TOWER HOUSING COOPERATIVE INCF / SHAWN ALEX HELLER
HO1500118 / HOME OCCUPATION
HOME OFFICE (LAW OFFICE).
300 TINGEY ST SE   
02/13/15 
RICHARD CERVERA / NATHANIEL GILL
B1504014 / CONSTRUCTION
NEW SUMMER GARDEN
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory




     © Copyright 2015 JD.