It's a real milestone in the redevelopment of Near Southeast to report that the entire stock of townhouses for sale at Capitol Quarter has now sold out.
The first reservations for units were taken in October 2006 (remember the people camping out?), construction began in summer 2008, Phase 1 finished construction and Phase 2 reservations began in 2010, and now, with construction underway on the last group of houses on L between 3rd and 4th, the finish line for the project is not far away.
The development has been the third phase of the Hope VI redevelopment of the old Capper/Carrollsburg public housing project, replacing the old housing with nearly seven blocks of brightly painted rowhouses, containing not only 130ish market-rate townhouses (a few of which have broken the $1 million barrier) but also 90ish special workforce-rate houses for smaller incomes, in addition to nearly 90 subsidized rental units.
Those units, combined with the 300 built at Capper Seniors #1 and 400 M Street, mean that more than half of the 700 units in the old Capper have now been replaced. The rest are slated to come in five mixed-income apartment buildings, located on the west side of 3rd Street, on L Street south of the Marine Bachelor Enlisted Quarters, and on the DPW/trash transfer station site at New Jersey and K. No timelines have been announced for any of the remaining buildings, but you can see on my main Capper page a map with estimated unit counts for each.
I've taken a lot (a LOT) of photos of the Capper footprint since 2003: my Capitol Quarter Phase 2 and Phase 1 pages give a good overview, or you can just pick a spot along 3rd, 4th, or 5th Streets in my Photo Archive and take a look.
Comments (5)
   
 
 More About Capper

JDLand.com Home

Comments

Maelstrom says: (3/29/12 1:26 PM)
I like how they deepened the blue in the sky when they re-developed Capper/Carrolsburg. Just look between the Nov 17th 2004 and Jul 31st 2011 pictures at 3rd and I (in article) - those sky-painters have been hard at work restoring the rich-ness of color up there.


kribbles says: (3/29/12 1:44 PM)
I've been in the new homes and I admit that they look nice. Not that there's much down there to do right now.


F says: (3/29/12 3:36 PM)
With "No timelines...announced for any of the remaining buildings," it will porbably look like this for many years to come.



Bruce says: (3/29/12 3:43 PM)
I was an overnight camper back in 2006. That group spend the night sitting around in chairs and got to know each other.
We truly were pioneers as we sat around in chairs as the last Capper homes were still standing down the block toward 3rd and L.
Fun to watch the area take shape over the last six years (although it took nearly 3 to close!)...
Made some good friends from that outing!
It is weird to see homes going up where the trailor used to be..


PJY03 says: (3/30/12 11:44 AM)
@Kribbles
really? not much to do down there? You're a ten minute walk to Eastern Market/Barracks Row, a 10-15 minute walk to the Nats, and a 5-10 minute walk to Yards Park (which will be full of retail within the next 18 months). Canal Park will be coming within the year and is 5 minutes away.

I lived in Cleveland Park, considered one of the standard "convenient" neighborhoods of NW. There's nothing I did up there that you can't do living in these townhouses. I'd actually argue that with the ballpark so close, and a walkable farmer's market, there's considerably more "to do" in Capitol Quarter. If you're talking about shopping and retail? Well, if what fills in over the next two years is according to schedule and plans, these townhomes will be 1.2 mill when there actually "is something to do".


Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Top News

Snacks on A Photo Tour: Have been to one soccer game for DC United. It was a fun time, had great weather...
202_cyclist on A Photo Tour: JD- I hope your recovery continues apace and you'll be off the 60-day disabled ...
dude on A Photo Tour: @202, yes you could say that about 70I. Also, I'm not a huge soccer fan (I thin...
spiritequality on Tuesday Tidbits: @cjbabydaddy Thanks for the tip in where to look for movie theater info. Hope th...
Message Board (beta)

Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/15/18
1000 B/O 3RD ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/07/18
1300 B/O 4TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 01/21/18

Recent Issued Building Permits Archive  
1331 2ND ST SE 20003   
01/29/18 
DC WATER / DAVE LEVINE
AH1800505 / CONSTRUCTION
After hours work for structure exaction and support for B1311474 DC Water. Corman Construction 202-863-0052.
1016 3RD ST SE   
02/01/18 
ANAMARIA R MOTTOLA / DAVID L. HAHN
P1803348 / SUPPLEMENTAL
1346 4TH ST SE   
02/06/18 
ALAN OWINGS / ROBERT SEV HENRY
AH1800541 / CONSTRUCTION
After Hours Permit for 2 / 19 / 18 from 7AM to 7PM to perform concrete, framing, and utility operations.
   
02/06/18 
FC 1346 LLC / RICHARD V CAREY
P1803428 / SUPPLEMENTAL
150 I ST SE   
02/05/18 
WC SMITH / null
P1803402 / SUPPLEMENTAL
140 M ST SE   
02/07/18 
SPAULDING & SLYE/STE100 / null
E1803798 / SUPPLEMENTAL
110 M ST SE   
01/29/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / JAMES WEAVER
E1803534 / SUPPLEMENTAL
   
02/02/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
P1803361 / SUPPLEMENTAL
140 M ST SE 20032   
02/14/18 
SYLVIA LINDSEY / null
P1803641 / SUPPLEMENTAL
202 M ST SE   
01/29/18 
UNITED STATES OF AMERICA / NURI EROL
D1800281 / CONSTRUCTION
Remove Existing flooring. Remove some of the furnitures, equipment.
300 M ST SE 53533   
02/08/18 
FEDERAL CENTER LP / SPENCER TEEL
BP1801893 / POST CARD
401 M ST SE   
01/30/18 
DOEE C/O DEV MURALI / JESSICA REICHARD
AH1800507 / CONSTRUCTION
After hours permit to preform manhole inspections during off peak hours 7pm - 7am for all Manhole Locations covered under permit # PA10374319-R1 for DOEE Anacostia river sediment project.
861 NEW JERSEY AVE SE   
01/21/18 
CONSOLIDATED RAIL CORPORATION / null
P1802976 / SUPPLEMENTAL
   
01/31/18 
CONSOLIDATED RAIL CORPORATION / NA CSX TRANSPORTATION, INC.
AH1800467 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities.***TO EXCLUDE LEGAL HOLIDAYS**
1100 NEW JERSEY AVE SE 2ND FL   
02/09/18 
SQUARE 742 LLC / null
P1803534 / SUPPLEMENTAL
   
02/14/18 
SQUARE 742 LLC / null
P1803681 / SUPPLEMENTAL
79 POTOMAC AVE SE   
01/22/18 
RIVERFRONT HOLDINGS I LLC / JUSTIN BELLOW
TL1800010 / CONSTRUCTION
1st time tenant layout for restaurant with 212 indoor seats and 350- indoors occupant load. 338 outdoor seats 550 outdoors occupant load.
640 SOUTH CAPITOL ST SE   
02/05/18 
JIM LATISIS ZAYO GROUP
B1707197 / CONSTRUCTION
Addition to existing concrete telecom building.
401 TINGEY ST SE   
01/30/18 
PEPCO / BARBARA ANN STEDMAN
AH1800520 / CONSTRUCTION
UG TRANSFORMER WORK TO BE PERFORMED ON THE 400 BLK OF TINGEY ST SE. MANHOLE ACCESS. WORK TO BE PERFORMED BETWEEN THE HOURS OF 7:30AM AND MIGHTNIGHT ON 1 / 30 / 18 AND 1 / 31 / 18.
227 TINGEY ST SE   
01/29/18 
UNITED STATES OF AMERICA / ERICKA CLARK
TC1800021 / CONSTRUCTION
2 tower cranes
   
01/30/18 
FOREST CITY WASHINGTON / MELISSA DIAZ
B1802750 / CONSTRUCTION
Revision to Permit SH1700028. Sheeting and shoring for Yards Parcel L-2 project. Revision includes 10-foot precut excavation and layback on Water Street, 3rd Street and northern L-1 elevations, and removal of upper tier of rakers at L-1 elevation and upper tier of tiebacks at the Water Street and 3rd Street elevations.
325 VIRGINIA AVE SE 20003   
02/14/18 
JASON W GOLDSMITH / null
E1804039 / SUPPLEMENTAL
325 VIRGINIA AVE SE   
02/06/18 
JASON W GOLDSMITH / CRAIG HARTSOCK
B1804721 / CONSTRUCTION
Remove two non-structural walls on ground level of townhouse and re-frame in new configuration to create a full bathroom on ground floor.
   
02/07/18 
JASON W GOLDSMITH / MORIS O. OCHOA PINEDA
P1803462 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
1001 NEW JERSEY AV SE   12/28/17
$ 687,365
WHATS ON SECOND PROPERTIES LLC
 


Project Directory
Completed
Agora ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.