There's been a lot of positive news in the neighborhood of late, but news today from Canal Park will be disappointing to many residents and observers: Because of "major underground obstacles" that weren't found until workers started digging, the park's underground storm water system is having to be completely redesigned and then approved by DC Water.
According to Chris Vanarsdale of the Canal Park Development Association, this has bumped the schedule by about four months, and November 1 is now the expected completion date. (Just in time for ice skating!)
Canal Park is of course also where Xavier Cevera's Park Tavern restaurant is anticipated to open, which means that its opening would be pushed back as well.
Comments (18)
   
 
 More About Canal Park
 All posts: Canal Park

JDLand.com Home

Comments

lefabe says: (3/8/12 3:53 PM)
NOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO!!!!!!!


ValveetaChz says: (3/8/12 4:08 PM)
Bah humbug!


Alan says: (3/8/12 4:36 PM)
Can't win 'em all.


bleeper1 says: (3/8/12 4:48 PM)
I can't say I'm surprised, I've been observing the progress (or lack thereof) for the past couple weeks.


PJY03 says: (3/8/12 5:34 PM)
Shame, but this is the nature of the construction game. Honestly, construction delays don't concern me that much. Financing delays do. I'm disappointed, but will get over it. I would be surprised if the Boilermaker shops finish on time.


TheJCG says: (3/8/12 10:10 PM)
Considering how poorly run DC has been for the last 40-50 years, it's no surprise things are buried under the streets that nobody is aware of. This is a minor hiccup that I suspect several projects will encounter over the coming years of improvement.


ConsumerAdvocate says: (3/9/12 9:12 AM)
Inquiring minds want to know, just what was under the streets anyway?


Rahnod says: (3/9/12 10:16 AM)
Silver Lining....we won't expect much snow this year so at least we'll have ice skating by Christmas. There are always delays in construction and things happen that our out of control and I for one would rather have it done right or not done at all.


We'll be fine as long as the delay isn't because of....zombies.


Sophia Monster says: (3/9/12 11:17 AM)
*tear*


Eric says: (3/9/12 11:55 AM)
TheYards said their rough estimate for Kruba is some time in latish June. I was hoping earlier.

The is heart-breaking news. When's Willie's BBQ supposed to be done?


JD says: (3/9/12 12:16 PM)
Xavier is saying fall for Willie's, but until you see fixtures going into a space, expected opening dates should be looked at very skeptically. As we've just seen.


G Street says: (3/9/12 2:32 PM)
That rendering of future restaurant / tavern is great -- it will be like Close Encounters of the Third Kind or Field of Dreams ... with people coming to stare at it. (-:


JD says: (3/9/12 2:36 PM)
Did someone say Close Encounters?

link





DAK4Blizzard says: (3/11/12 10:20 PM)
To me, the real surprise is that it's still targeted for completion THIS year. We'll see if it holds up.


B in DC says: (3/12/12 10:51 AM)
Speaking of construction delays, it's been like two weeks since anything has been done on the Harris Teeter lot. There was lots of action right at first, then suddenly nada. Hope it's nothing major!


MJM says: (3/12/12 2:21 PM)
UXOs were rumored to have been found there


B in DC says: (3/13/12 2:38 PM)
What's a UXO?


JD says: (3/13/12 2:40 PM)
Unexploded ordnance. There was one found a few months back (Navy Yard staff were alerted to it).

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2016!
 Top News

Chaifetz10 on Two-Year Change in: Have a random question for anyone and everyone here as 1) It's technically outsi...
JD on Signs and Wonders: {pointed silence}
202_cyclist on Signs and Wonders: Another blog has a post about the 11th Street bridge park ( ). I think this is ...
jdc on Signs and Wonders: @snakegriffin - that's fascinating. I wonder how the sound chamber created by th...

Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1200 B/O 4TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/17/16
1000 B/O HALF ST SE   THEFT
Theft First Degree (all Other Larceny)
 08/16/16
700 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/15/16
1400 B/O SOUTH CAPITOL ST   THEFT
Theft 2nd Degree (all Other Larceny)
 08/14/16
16 B/O M ST SE   ROBBERY  08/12/16
1000 B/O 5TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/09/16
1200 B/O 1ST ST SE   THEFT
Theft First Degree (shoplifting)
 08/08/16
50 B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 08/02/16
600 B/O I ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/02/16
700 B/O L ST SE   ROBBERY  08/01/16
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/29/16
700 B/O L ST SE   ROBBERY  07/28/16

Recent Issued Building Permits Archive  
1150 5TH ST SE 20002   
08/11/16 
ALAN J PHELPS / DOUGLAS FOSTER
B1509540 / CONSTRUCTION
1. Renovation of existing first and second floor of the academic wing of the Van Ness building. 2. Square footage is approximately 26,000 SF ,For phase 1 3. Cost of construction is 11.5M 4. Scope of work details a. Convert existing space in to 6 new classroom space. These classrooms will be two PreK -3, two prek-4, and two Kindergarten classes. Also for phase 1,...
1150 5TH ST SE   
08/12/16 
DISTRICT OF COLUMBIA / JOHN HOMICK
E1609156 / SUPPLEMENTAL
   
08/12/16 
DISTRICT OF COLUMBIA / MATT LOSIGNOR
P1608656 / SUPPLEMENTAL
   
08/12/16 
DISTRICT OF COLUMBIA / ORLANDO M CATANA
E1609149 / SUPPLEMENTAL
82 I ST SE   
08/15/16 
GDCV EYE STREET LLC / GDCV EYE STREET LLC; KIM MITCHELL CDKM CONSULTING LLC
B1611941 / CONSTRUCTION
FIRST EXTENSION TO PERMIT B1507990 TO EXPIRE ON 3 / 17 / 17
   
08/15/16 
CSX TRANSPORTATION INC / BEDCO MOBILITY INC.
EN1602806 / SHOP DRAWING
Type of Elevator : One (1) vertical wheel-chair lift / steel / garage level 2 / handicap lift (13th floor)
125 L ST SE   
08/11/16 
CRANE SERVICE CO / CRANE SERVICE CO; CHRISTINE LONG
AH1600945 / CONSTRUCTION
An after hours permit is respectfully requested from 4AM Saturday thru 9PM Sunday
80 M ST SE 1   
08/10/16 
WELLS REIT II 80 M STREET LLC / THOMAS B. STEG
P1608566 / SUPPLEMENTAL
80 M ST SE 2   
08/10/16 
WELLS REIT II 80 M STREET LLC / THOMAS B. STEG
P1608568 / SUPPLEMENTAL
80 M ST SE 3   
08/10/16 
WELLS REIT II 80 M STREET LLC / THOMAS B. STEG
P1608569 / SUPPLEMENTAL
100 M ST SE PT OF 4TH   
08/11/16 
QUARE 743 INC . / QUARE 743 INC .; JOHN GIUSEPPE-RAMCO
B1611810 / CONSTRUCTION
renovation to parts of an existing 4th floor office space, tech marine business as shown on the attached mech., plumb., elect., fire protection, demolition, and arch. dwgs. interior work only. no change in use. no struct. work. 800 sf.
300 M ST SE   
08/06/16 
FGSF TEST
PC92978992 / POST CARD
Installation of 1 temporary construction trailer on private property.
   
08/06/16 
SDS SDSDS / LAVANYA SIKHINAM; SDS SDSDS; ENRIQUE LYON
E90011839 / SUPPLEMENTAL
   
08/07/16 
XVB XVBX / FSGVSF SFGS; XVB XVBX; DAVID FARMER
E77515115 / SUPPLEMENTAL
909 NEW JERSEY AVE SE 1311   
08/11/16 
null / NA NA NA
EHOP1690902 / HOME OCCUPATION
861 NEW JERSEY AVE SE   
08/09/16 
NA CSX TRANSPORTATION, INC.
AH1600944 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities.
1111 NEW JERSEY AVE SE   
08/11/16 
null / THOMAS P MCGUIRE
E1609117 / SUPPLEMENTAL
385 WATER ST SE   
08/12/16 
FC 385 WATER LLC / STEPHEN J. EXELBERT
P1608654 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Capitol ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2016 JD.