There's been a lot of positive news in the neighborhood of late, but news today from Canal Park will be disappointing to many residents and observers: Because of "major underground obstacles" that weren't found until workers started digging, the park's underground storm water system is having to be completely redesigned and then approved by DC Water.
According to Chris Vanarsdale of the Canal Park Development Association, this has bumped the schedule by about four months, and November 1 is now the expected completion date. (Just in time for ice skating!)
Canal Park is of course also where Xavier Cevera's Park Tavern restaurant is anticipated to open, which means that its opening would be pushed back as well.
Comments (18)
 
 More About Canal Park
 All posts: Canal Park

JDLand.com Home

Comments

lefabe says: (3/8/12 3:53 PM)
NOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO!!!!!!!


ValveetaChz says: (3/8/12 4:08 PM)
Bah humbug!


Alan says: (3/8/12 4:36 PM)
Can't win 'em all.


bleeper1 says: (3/8/12 4:48 PM)
I can't say I'm surprised, I've been observing the progress (or lack thereof) for the past couple weeks.


PJY03 says: (3/8/12 5:34 PM)
Shame, but this is the nature of the construction game. Honestly, construction delays don't concern me that much. Financing delays do. I'm disappointed, but will get over it. I would be surprised if the Boilermaker shops finish on time.


TheJCG says: (3/8/12 10:10 PM)
Considering how poorly run DC has been for the last 40-50 years, it's no surprise things are buried under the streets that nobody is aware of. This is a minor hiccup that I suspect several projects will encounter over the coming years of improvement.


ConsumerAdvocate says: (3/9/12 9:12 AM)
Inquiring minds want to know, just what was under the streets anyway?


Rahnod says: (3/9/12 10:16 AM)
Silver Lining....we won't expect much snow this year so at least we'll have ice skating by Christmas. There are always delays in construction and things happen that our out of control and I for one would rather have it done right or not done at all.


We'll be fine as long as the delay isn't because of....zombies.


Sophia Monster says: (3/9/12 11:17 AM)
*tear*


Eric says: (3/9/12 11:55 AM)
TheYards said their rough estimate for Kruba is some time in latish June. I was hoping earlier.

The is heart-breaking news. When's Willie's BBQ supposed to be done?


JD says: (3/9/12 12:16 PM)
Xavier is saying fall for Willie's, but until you see fixtures going into a space, expected opening dates should be looked at very skeptically. As we've just seen.


G Street says: (3/9/12 2:32 PM)
That rendering of future restaurant / tavern is great -- it will be like Close Encounters of the Third Kind or Field of Dreams ... with people coming to stare at it. (-:


JD says: (3/9/12 2:36 PM)
Did someone say Close Encounters?

link





DAK4Blizzard says: (3/11/12 10:20 PM)
To me, the real surprise is that it's still targeted for completion THIS year. We'll see if it holds up.


B in DC says: (3/12/12 10:51 AM)
Speaking of construction delays, it's been like two weeks since anything has been done on the Harris Teeter lot. There was lots of action right at first, then suddenly nada. Hope it's nothing major!


MJM says: (3/12/12 2:21 PM)
UXOs were rumored to have been found there


B in DC says: (3/13/12 2:38 PM)
What's a UXO?


JD says: (3/13/12 2:40 PM)
Unexploded ordnance. There was one found a few months back (Navy Yard staff were alerted to it).

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed

See All Current News Items | Full Blog Archive

 
 Top News
  
Recent Comments:  
Chococar on Tidbits: I see the obstructionists are still trying to block the CSX tunnel. The narrow o...
Edna on Tidbits: Well said, JD, on Jair Lynch. What a bunch of developer nonsense-talk!
JES on Tidbits: Well, last time, we made a bit of a hasty exit..... who knows how the latter rou...
JD on Tidbits: I think that's how it ended up working out last time, that despite all the sturm...



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1100 B/O 10TH ST SE   THEFT F/AUTO /  09/08/14
400 B/O K ST SE   THEFT F/AUTO /  09/08/14
1000 B/O 4TH ST SE   THEFT F/AUTO /  09/05/14
300 B/O M ST SE   ROBBERY /  09/03/14
900 B/O 1ST ST SE   THEFT F/AUTO /  09/03/14
1000 B/O 1ST ST SE   THEFT /  09/03/14
1200 B/O 4TH ST SE   THEFT F/AUTO /  09/02/14
200 B/O M ST SE   THEFT /  09/02/14
300 B/O M ST SE   THEFT /  09/02/14
1100 B/O NEW JERSEY AVE SE   THEFT /  09/01/14
300 B/O K ST SE   THEFT F/AUTO /  08/31/14
1100 B/O 10TH ST SE   THEFT F/AUTO /  08/31/14
300 B/O I ST SE   MOTOR VEHICLE THEFT /  08/30/14
1400 B/O 1ST ST SE   THEFT /  08/29/14
300 B/O WATER ST SE   MOTOR VEHICLE THEFT /  08/27/14
3RD ST SE AND WATER ST SE   THEFT F/AUTO /  08/26/14
100 B/O K ST SE   THEFT F/AUTO /  08/25/14
400 B/O M ST SE   MOTOR VEHICLE THEFT /  08/23/14
1000 B/O NEW JERSEY AVE SE   THEFT /  08/22/14
200 B/O I ST SE   THEFT /  08/22/14
900 B/O HALF ST SE   MOTOR VEHICLE THEFT /  08/22/14

Active Public Space Permits Archive  
1331 2ND ST SE    Carlton Ray 
Assigned
paving; streetfixture; excavation  
 02/10/14
to
02/09/15
908 3RD ST SE    Rachel Frankel 
Issued
streetfixture; new  
 07/24/14
to
09/21/14
1331 4TH ST SE    Forest City Forest City 
Issued
excavation; new  
 01/10/14
to
02/10/15
880 NEW JERSEY AVE SE    WASHINGTON GAS 
Issued
excavation; new  
 07/28/14
to
09/26/14
301 TINGEY ST SE    Potbelly Sandwich Works LLC 
Issued
new  
 03/21/12
to
11/27/14

Recent Issued Building Permits Archive  
1011 1ST ST SE   
09/03/14 
TOLL DC LP / MILLENNIUM POOL
SP1400019 / CONSTRUCTION
INSTALL STAINLESS STEEL POOL ON ROOFTOP OF THE 13-FLOOR APARTMENT BUILDING.
1200 1ST ST SE   
09/05/14 
UNITED STATES OF AMERICA / FVI2020
EX1400033 / CONSTRUCTION
EXCAVATION SITE GRADING ONLY
1020 3RD ST SE   
09/03/14 
MAYIAK LLC / SMK AND ASSOCIATES LLC
B1411577 / CONSTRUCTION
REPAIR OR REPLACE IN KIND KITCHEN CABINETS TILE ON KITCHEN FLOORS. REPLACE FLOORS THROUGHOUT REPLACE BATHROOM VANITY TOILET TUB . PAINT EXTERIOR WINDOW LEDGES AND FRONT PORCH
1212 4TH ST SE   
09/09/14 
FC 1212 LLC /
FB1400131 / SUPPLEMENTAL
   
09/09/14 
FC 1212 LLC / WENDELL D. NIXON
M1403160 / SUPPLEMENTAL
1331 4TH ST SE   
09/09/14 
UNITED STATES OF AMERICA /
P1407907 / SUPPLEMENTAL
1103 9TH ST SE   
09/16/14 
ICP PARTNERS POTOMAC 810 LLC / FRANKLIN T GAINES
P1408621 / SUPPLEMENTAL
1220 12TH ST SE   
09/18/14 
WASHINGTON GAS LIGHT CO / GREGORY E LIGON
E1409179 / SUPPLEMENTAL
1200 13TH ST SE   
09/03/14 
WASHINGTON GAS LIGHT COMPANY / CHRIS WILLETT URS CORPORATION
SB1400412 / CONSTRUCTION
DCCR PROPOSES TO DRILL TWO GEOTECHNICAL BOARINGS MS-MW-02D & MS-MW-02S LOCATED AT 1200 13TH ST SE. BOTH BOARINGS WILL BE 6 INCHES IN DIAMETER 02D WILL BE 36 FEET DEEP WIOTH A 10 FOOT SCREENED INTERVAL STARTING AT 25 FEET DEEP AND 02S WILL BE 23 FEET DEEP WITH A 10 FOOT SCREENED INTERVAL STARTING AT 13 FEET DEEP. BOTH WILL BE DIRLLED WITH HOLLOW STEM AUGER. NO PERMANENT CASING WILL BE INSTALLED. SE...
   
09/03/14 
WASHINGTON GAS LIGHT COMPANY / CHRIS WILLETT URS CORPORATION
SB1400413 / CONSTRUCTION
DCCR PROPOSES TO DRILL ONE GEOTECHNICAL BORING MS-MW 01 LOCATED IN 1200 13TH ST SE. THE BORING WILL BE 6 INCHES IN DIAMETER AND 200 FEET BGS WITH A SCREENED INTERVAL FROM 135 TO 195 FEET BGS DRILLED BY MUD ROTARY. PERMANENT STELL CASING WILL INSTALLED AND BE SOCKETED 10 FEET INTO P / A AND GROUTED BEFORE DRILLING INTO THE PTX. MSDS FOR DRILLING MUD ADDITIVES ATTACHED. SEE IDW MANAGEMENT PLAN AND A...
1015 HALF ST SE   
09/04/14 
HALF ST SE LLC /
P1408319 / SUPPLEMENTAL
601 L ST SE   
09/02/14 
V ? V CONSTRUCTION / STEPHANIE DELCA TRAFFIC ENGINEERING SERVCIES LLC
TC1400023 / CONSTRUCTION
TO ERECT TOWER CRANE AS PER PLANS.
   
09/16/14 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / EDUARDO L. LOPEZ
E1409105 / SUPPLEMENTAL
   
09/18/14 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / RICHARD V CAREY
P1408678 / SUPPLEMENTAL
20 M ST SE   
09/08/14 
SOUTHEAST REALTY LLC / WESLEY R. DAVIS
E1408797 / SUPPLEMENTAL
55 M ST SE   
09/11/14 
HINES GLOBAL REIT 55 M STREET LLC / DANIEL O WHITE
E1408953 / SUPPLEMENTAL
100 M ST SE   
09/15/14 
SQUARE 743 INC. / SAM HOLLEN RAMCO OF DC INC.
TL1400150 / CONSTRUCTION
INTERIOR TENANT LAYOUT OF 6TH FLOOR OFFICE SPACE. PARTITIONS FURNITURE MEP AND LIFE SAFETY. REGUS 2429
901 M ST SE   
09/12/14 
CARLTON RAY
AH1400687 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
1201 M ST SE   
09/12/14 
CARLTON RAY
AH1400686 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
0 N ST SE   
09/10/14 
SNALLYGASTER / ERIK BERGMAN
TN1400195 / CONSTRUCTION
SPECIAL EVENT SNALLYGASTER 1 10X40 TENT 1 20X90 TENT 2 20X160 TENT 1 30X15 STAGE TENT TEMPORARY GENERATOR
   
09/10/14 
DISTRICT OF COLUMBIA / JAMES A. WILLIAMS
E1408914 / SUPPLEMENTAL
800 NEW JERSEY AVE SE   
09/17/14 
NEW JERSEY AT H LLC / COLIN CLARK
B1408553 / CONSTRUCTION
CONSTRUCTION OF A 11 STORY 336 UNIT APARTMENT BUILDING WITH FIRST FLOOR RETAIL AND THREE BELOW GRADE LEVELS FOR PARKING GARAGE PER BZA # 18619 GRANTED ON 9 / 24 / 13 WITH CONDITION: SCREENING OF THE PARKING ADJACENT TO H ST.--- SPECIFICALLY SHEETS 6 AND 7 OF EXHIBIT 23 - PLANS TO INCLUDE MECHANICAL PLUMBING AND ELECTRICAL WORK.
25 POTOMAC AVE SE   
09/09/14 
GRIFFIN STEPHEN
PC60869040 / POST CARD
INSTALLATION OF 1 TEMPORARY CONSTRUCTION TRAILER ON PRIVATE PROPERTY.
1500 SOUTH CAPITOL ST SE   
09/09/14 
COMCAST CABLE / MICHAEL SONESEN
AH1400678 / CONSTRUCTION
PLACING INNERDUCT IN EXISITING VERIZON MANHOLES SEPTEMEBR 5TH 2014 - OCTOBER 5TH 2014 EVENINGS ? SATRUDAYS 7PM TO 2AM
300 TINGEY ST SE   
09/11/14 
FC BOILERMAKER LLC / CHRIS WING
B1407179 / CONSTRUCTION
INTERIOR ALTERATION FOR NEW UNLEASHED BY PETCO STORE.
   
09/05/14 
FC BOILERMAKER LLC
B1411671 / CONSTRUCTION
INSTALL FIRE SUPPRESSION SYSTEM TO EXHAUST HOOD.
   
09/13/14 
FC BOILERMAKER LIC FC BOILERMAKER LIC / DENNIS STUBBS; FC BOILERMAKER FC BOILERMAKER LIC; DENNIS STUBBS
P24303627 / SUPPLEMENTAL
   
09/18/14 
FC BOILERMAKER LLC /
P1408685 / SUPPLEMENTAL
   
09/18/14 
CHRIS WING / SHANDI COBB; CHRIS WING; CHARLES CLYNES
AR65033933 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory




Blog/Home
Project Directory
Photo Archive
Event Photos
 
Nats Park
Food Map
What's New
History

 
Demolished Buildings
Historic Photos
Satellite Images
Timeline
 
About JDLand
Message JD
Advertise
Photo Use
 
     © Copyright 2014 JD.