Since January, 2003
            
 Page Through from Before to After

New Jersey Avenue, south of the freeway, looking east, before and after the clearing of brush and trees that happened late last week:
A slightly different angle, looking south-southeast:
This appears to be the work that William C. Smith mentioned would be coming, as part of their preparations for infrastructure work in advance of their 880 New Jersey Avenue apartment project. More before-and-afters here.
(That's 225 Virginia/200 I in the background, if you're bewildered at what you're seeing in this new view.)
(This is the first in what will be an avalanche of new photos over the next few days, after I drove around for about two hours grabbing scads of shots that I have been guilt ridden about not getting to. Rather than trying to put them up in one overwhelming post, I'll be passing them along in manageable bites.)
Comments (4)
   
 
 More Recent News

JDLand.com Home

Comments

rdotis says: (1/8/12 5:41 PM)
No one seems to be concerned that this building will eliminate Canal Street and thus will be built across the original path of L'Enfant's canal. Since L'Enfant's plan is listed on the National Register, shouldn't this building be precluded from building across a significant part of the plan? Also, part of the apparent logic for allowing Canal Street to be closed (and thus create a full square block) is that the developer will "re-open" I Street SE. From any map I've been able to review, the area was always an open & undeveloped space with the exception of the canal - I Street doesn't appear to have actually existed. "Restoring" the grid pattern, eliminating the angular Canal Street, and building one more block sized monster of a building will do nothing but continue the dull urban environment created by all the other new block sized buildings of near SE - a generational opportunity lost.


JD says: (1/8/12 5:48 PM)
Just one point of clarification--it's not going to be a block-sized building. They are planning four buildings on Square 737.



MJM says: (1/9/12 12:40 PM)
What about James Creek Canal? The Washington City Canal was a failure. There is nothing left of the canal. I think if they were going to declare anything historical it would have been where Canal Park is but there was no canal to be found. After the sewer pit was filled in there were railroad tracks along with a larger trash transfer footprint in that area....


ConsumerAdvocate says: (1/26/12 11:22 AM)
Did anyone notice or care about the demise of the lovely Southern Magnolia at the trash transfer station. Sad they couldn't just have moved and bagged it for transplant.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

CJ1 on Inching from Quarantining: Oh wow... I live at Ore82 and didn't know about any of this.
GarfieldPark on Inching from Quarantining: @JD: Apparently, ORE will be eliminating (or making them smaller) some of it's ...
JD on Inching from Quarantining: Some interesting design notes found in the approved building permit for the thre...
KEWEE on Inching from Quarantining: Jeni's Splendid Ice Creams is coming to the retail space located at The Bower co...
CJBabyDaddy on Inching from Quarantining: Serious workplace accident on the ground this morning at the Chemonics construct...
MJM on Inching from Quarantining: Welcome to the neighborhood Pivot Physical Therapy. Its located behind Sprint (w...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
400 B/O K ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 07/06/20
1200 B/O HALF ST SE   THEFT
Theft First Degree (all Other Larceny)
 07/05/20
100 B/O H ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/03/20
100 B/O O ST SE   ROBBERY  07/03/20
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 06/28/20
1200 B/O 1ST ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 06/25/20
1200 B/O SOUTH CAPITOL ST SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 06/23/20
1200 B/O NEW JERSEY AVE SE   ASSAULT WITH A DANGEROUS WEAPON
Assault W/i To Kill
 06/20/20
1000 B/O 3RD PLACE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 06/18/20
800 B/O SOUTH CAPITOL ST SE   ASSAULT WITH A DANGEROUS WEAPON  06/14/20
400 B/O M ST SE   THEFT
Shoplifting
 06/12/20
1000 B/O M ST SE   ROBBERY
Unarmed Carjacking
 06/09/20
UNIT B/O M ST SE   ASSAULT WITH A DANGEROUS WEAPON  06/07/20

Recent Issued Building Permits Archive  
1300 4TH ST SE RU-2   
06/18/20 
AP BOWER RETAIL LLC / MELISSA BRENT
SG2000335 / CONSTRUCTION
Install 1 illuminated wall sign & 1 illuminated blade sign - JENIs ICE CREAM
150 I ST SE   
06/15/20 
SQUARE 737 LLC / BOB BIROONAK; NA; NA
SG2000323 / CONSTRUCTION
two illuminated building sign
151 M ST SE   
06/18/20 
BROOKFIELD PROPERTIES / CHRIS CRESCI; NA
SB2000292 / CONSTRUCTION
WSP will be advancing approximately 50 soil borings to 30 feet, and an additional 8 borings to 4 feet via direct push. A water sample will be collected from 3 of the deep borings. All borings will be abandoned via bentonite grout mix. Investigation derived waste will be stored in DOT 55-gallon steel drums. Private and public utility locating will take place prior to the work beginning
250 M ST SE   
06/19/20 
WILLIAM C SMITH / null
E2008622 / SUPPLEMENTAL
   
06/24/20 
SQUARE 769 LLC / null
M2002834 / SUPPLEMENTAL
   
06/24/20 
SQUARE 769 LLC / null
P2006931 / SUPPLEMENTAL
300 M ST SE   
06/16/20 
FEDERAL CENTER LP / null
E2008501 / SUPPLEMENTAL
   
06/18/20 
FEDERAL CENTER LP / null
E2008587 / SUPPLEMENTAL
111 N ST SE   
06/16/20 
BROOKFIELD PROPERTIES / NA; CHRIS CRESCI
SB2000293 / CONSTRUCTION
WSP will advance 22 soil borings to 25 feet and 8 soil borings to 4 feet via direst push. A groundwater sample will be collected from 2 of the deep borings by installing a temporary well to be in the ground for just a couple hours. Borings will be backfilled with bentonite / grout mix. IDW will be stored in DOT 55-gallon drums. A private and public utility mark out will be completed prior to b...
861 NEW JERSEY AVE SE   
06/10/20 
CXS TRANSPORTATION INC / ;
P2006604 / SUPPLEMENTAL
   
06/19/20 
CXS TRANSPORTATION INC / ;
P2006843 / SUPPLEMENTAL
   
06/22/20 
GREYSTAR GP LLC / KIM MITCHELL
B1903035 / CONSTRUCTION
The proposed project is three structures which are connected by a shared below-grade garage, which is one story deep on the east half of the site and two stories deep on the west half of the site. Two structures will be residential, with a total of 756 units, and the third will be a 225-key hotel. The west residential structure (Building 3) is planned to be 13 stories with ground and roof level am...
   
06/25/20 
CXS TRANSPORTATION INC / ;
P2006972 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
06/10/20 
SQUARE 742 LLC, C/O SPAULDING & SLYE/STE 100, / PAUL WHITLEY
AN1900284 / CONSTRUCTION
PROJECT CONSISTS OF: REMOVING: (2) EXISTING EQUIPMENT CABINETS, (3) EXISTING ANTENNA'S, (1) EXISTING RRU'S AND ANCILLARY EQUIPMENT / CABLE AND INSTALLING: (6) PROPOSED ANTENNA'S, (3) PROPOSED RRU'S, AND(2) PROPOSED EQUIPMENT CABINETS ON AN EXISTING TELECOM FACILITY
1111 NEW JERSEY AVE SE   
06/12/20 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / TRACIE CLAXTON; NA; NA
SG2000257 / CONSTRUCTION
One Wall Mounted Sign illuminated
   
06/24/20 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
P2006938 / SUPPLEMENTAL
401 WATER ST SE   
06/18/20 
BROOKFIELD PROPERTIES / CHRIS CRESCI
SB2000294 / CONSTRUCTION
WSP will advance 23 soil borings to 30 feet and 8 additional borings to 4 feet using direct push. A groundwater sample will be collected from 2 of the deep borings by installing a temporary well. Soil boirngs will be abandoned with bentonite / grout mix. IDW will be stored for disposal in DOT 55-gallon drums. A private and public utility mark out will be completed priot to starting intrusive w...
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.