I almost can't bring myself to write the words, but the owners of the Florida Rock site just south of Nationals Park have filed with the Zoning Commission for not only the previously reported plan to change the planned first phase office building to a residential one, but also to revisit parts of the site plan for the three subsequent phases. (For those of you versed in zoning speak, they are requesting to "revert Phases II, III, and IV to First Stage Approvals with modifications.")
This is going to be a lengthy process, with hearings at the Zoning Commission, reports from the Office of Planning and others, and presentations to the ANC (starting with one this coming Monday night, Dec. 12). So I'm going to avoid getting into the weeds too much too early, and will just give some bullet points of what changes they are looking for. (You're free to read these 57 pages of the filing for more detail.)
* The new Phase 1 building, at the far east end of the site (next to Diamond Teague Park) will now be the aforementioned residential building, a nine-story U-shaped design oriented toward the river with 300-350 units and 286 below-grade parking spaces. There will still be 12,500 square feet of retail, though they are asking that 7,000 of it be "flex space" that "may alternatively be dedicated to residential amenity space" until retail gets going. There will be a private courtyard within the "U", but there will also be the open space on the buildings' east side, now dubbed Anacostia Plaza, that will be open enough to maintain open views from First Street and the stadium's Grand Staircase to the river but will also provide "passive recreation space."
* The esplanade that has always been such a big part of the site plan remains, acting as the portion of the Anacostia Riverwalk Trail connecting South Capitol Street to Teague Park, the new pedestrian bridge, and the Yards Park. The Esplanade will "relate" to the "design vernacular" of the newly constructed boardwalks, and will also have a lot of stormwater management and bio-filtration offerings.
* On the building's west side will be the "Mews," which they call a pedestrian boulevard separating the Phase 1 building from the planned Phase 2 residential building. This path will also provide access to parking and loading for the first two phases, but "a dynamic paving design . . . will help distinguish this area as an urban space that privileges pedestrians over vehicles."
* The filing says they anticipate construction to begin in the second quarter of 2013, with first move-ins in early 2015 and the entire phase completed by summer 2015.
As for overall changes, here's what seem to be the most interesting changes from the previously approved design that the developers are looking for:
* The new plan would bring 1,164,640 square feet of gross floor area (4.6 FAR), up from 1,115,400 sq ft/4.4 FAR in the last plan. The other three phases' uses would remain unchanged (residential, office, hotel).
* Building heights of 130 feet for Phase 2-4 are being requested, compared to 130/112/130 last time around.
* Below-grade parking spaces would go from 1,010 to 1,144.
Plus, though It's hard to tell from one small site plan concept drawing, a lot of the public space design, especially to the east of the Phase 3 and 4 buildings, looks scaled back from the 2008 design. (UPDATE: Here's a graphic put together from another part of the filing that compares the 2008 site plan with the current one.)
The filing also says that "the Applicant would like the flexibility to provide interim uses on Phases, II, III, IV so that the site will not simply lay dormant pending construction," and lists a park, a farmers market, or other "simple, temporary retail uses" as examples.
And, just as in the previous plans, development of phases 3 and 4 are completely dependent on the construction of a new South Capitol Street Bridge, since the current bridge bisects the property where those buildings are planned.
Again, this is early in this new process, and there will be plenty of filings and presentations to come for all the additional detail you're going to be clamoring for. For now, the takeaway is that FRP/MRP want to get started on a residential building at 1st and Potomac in the spring of 2013, and still want to move forward on the rest of the site with a design similar to what was approved 3 1/2 years ago, but with some modifications.
This project first began its zoning quest in 1998, and went through a four-year process ending in 2008 to get its second-stage approvals. I should also note that Davis Buckley Architects, who worked on the project throughout that 10-year ordeal, is no longer part of the design team; SK&I is now on board, with Oculus as the landscape design firm. The site's owners, FRP Development/Florida Rock Properties, announced their partnership with MRP Realty earlier this year.
(As for the concrete plant currently on site, I haven't looked lately, but demolition is underway, and the filing says it should be done by the end of the year. Tom Boswell's heart will be broken.)
UPDATE, 1/3: Just before Christmas, demolition was finished on the plant, making it #166 in my Demolished Buildings Gallery.
Comments (3)
 
 More About Florida Rock
 All posts: Florida Rock, zoning

JDLand.com Home

Comments

lester says: (12/9/11 3:15 PM)
130 feet tall? That's curious.

The area is zoned W-2, which would traditionally allow for up to 60 feet. It's part of the capital gateway overlay, which is designed "to reduce the height and bulk of buildings along the Anacostia riverfront."

Then DC goes ahead and approved (previously) 130/112/130 foot tall buildings (Phase II, III, and IV, not sure what Phase I will be). Wow. The wonders of the PUD (which basically nullifies the W-2 and CG designation).

However, moving past these decisions, how on earth do they justify 130 feet with respect to the Heights of Building Act of 1910? To allow a 130 foot tall building, you would need to have either South Capitol or Potomac be 110' wide, and as best as I can estimate from the DC property records web site, they are at most 90' wide. What gives?

Either way, it seems silly to develop an overlay to reduce height and bulk near the Anacostia riverfront, and then approve four buildings on the waterfront 100+ feet high...

Mind you, from where I live, the buildings won't really impact my view at all, I just find it all very... strange.


JD says: (12/9/11 3:22 PM)
Phase I was originally approved at 92 feet; they're requesting 95 feet this time.

There's a fair amount of discussion of the zoning starting around page 11 in the document I link to above, which says that CG/W-2 (the Capitol Gateway overlay) allows for max heights of 130 ft in mixed-use developments. (Purely commercial buildings can only be 60 feet high; the CG overlay gives the opportunity for increased density by developing mixed-use.)

Here's the Capitol Gateway Overlay, if you want to read: link




IMGoph says: (12/17/11 12:17 AM)
I like the fact that the building footprints aren't curvy like the Watergate anymore. That footprint just felt contrived.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed

See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2015!
 Top News
  
Recent Comments:  
Sally M on Notices of Virginia: Working beautifully for me. Count me in on the cult following…
conngs0 on Notices of Virginia: Works well for me. Thanks for the persistence with the technical issues associa...
JD on Notices of Virginia: We'll see what happens once there's actually some heavy traffic, but at the mome...
nairobs on Notices of Virginia: Works great for me too.



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
   THEFT
Theft 2 (Theft F/Building)
 04/23/15
400 B/O M ST SE   THEFT
2nd Degree
 04/22/15
1000 B/O 3RD ST SE   THEFT
2nd Degree
 04/20/15
1100 B/O NEW JERSEY AVE SE   THEFT
2nd Degree
 04/12/15
1100 B/O NEW JERSEY AVE SE   THEFT
2nd Degree
 04/10/15
100 B/O L ST SE   THEFT
Theft 2 (Theft F/Building)
 04/10/15
100 B/O K ST SE   THEFT F/AUTO
 04/08/15
50 B/O M ST SE   THEFT
2nd Degree
 04/07/15
100 B/O K ST SE   THEFT F/AUTO
Theft From Auto 1
 04/04/15
400 B/O M ST SE   THEFT
Shoplifting
 04/03/15
0 B/O POTOMAC AVE SE   ROBBERY
Robbery/Attempt To Commit Robbery
 03/28/15

Active Public Space Permits Archive  
1401 11TH ST SE    Maryland Transit Administration 
Issued
new  
 12/30/14
to
12/29/15
861 NEW JERSEY AVE SE    CSX Transportation Inc. 
Assigned
paving; excavation  
 01/09/15
to
10/09/15
1100 NEW JERSEY AVE SE    Capitol Riverfront BID 
Issued
streetfixture; new  
 08/19/14
to
08/18/15

Recent Issued Building Permits Archive  
1011 1ST ST SE   
04/20/15 
COLIN CLARK / MICHAEL BIANCO; COLIN CLARK; MITCH PERMUY
E98099105 / SUPPLEMENTAL
1265 1ST ST SE   
04/10/15 
CAPITAL RIVERFRONT HOTEL LLC / JERONE SCOTT
P1504925 / SUPPLEMENTAL
   
04/10/15 
BIT INVESTMENT FIFTY-EIGHT LLC / OTIS ELEVATOR COMPANY
EN1501330 / SHOP DRAWING
TYPE OF ELEVATOR : TWO (2) TRACTION / STEEL / CENTRAL / VERTICAL TRANSPOTATION LICENSE NUMBER : ELC1300386 ISSUE DATE : 08 / 04 / 2014 EXPIRATION DATE 11-30-2015
1277 1ST ST SE   
04/15/15 
BALLPARK RESIDENTIAL LLC / CLARK CONSTRUCTION GROUP LLC
AH1500366 / CONSTRUCTION
ON-SITE PROJECT WORK AND TRUCK DELIVERY HOURS 6:00AM - 7:00PM MONDAY THROUGH SATURDAY FOR THE PROJECT DURATION AND THE FOLLOWING HOLIDAYS: EMANCIPATION DAY 4 / 16 / 15 COLUMBUS DAY 10 / 12 / 15 VETERANS DAY 11 / 11 / 15
1331 4TH ST SE   
04/17/15 
CLARK CONCRETE
AH1500371 / CONSTRUCTION
AFTERHOURS TO POUR CONCRETE ON ROOF FROM 4 / 20 / 2015 TO 5 / 20 / 2015 FROM 7PM TO 7AM
   
04/21/15 
FC 1331 LLC / JAMES G HOLT
E1505081 / SUPPLEMENTAL
1150 5TH ST SE   
04/09/15 
DISTRICT OF COLUMBIA JEFFREY LUKER QUINN EVANS ARCHITECTS / REBECCA RUSCHMA ECS MID-ATLANTIC
SB1500233 / CONSTRUCTION
WE WILL PERFORM A TOTAL OF TWO SOIL BORINGS ON THE PROPOSED SITE AND ONE AUGER PROBE BORING FOR INFILTRATION TESTING. ONE BORING WILL EXTEND TO A DEPTH OF 100 FEET AND THE ANOTHER WILL EXTEND TO A DEPTH OF 15 FEET BELOW EXISTING SITE GRADES AND WILL BE LOCATED WITHIN THE BOUNDS OF THE PRIVATE PROPERTY. WE WILL ALSO DRILL ONE PROBE BORING OFFSET FROM THE 15 FOOT BORING TO A DEPTH OF APPROXIMATELY 1...
   
04/15/15 
DGS DCPS / BRUCE PAIGE INDUSTRIAL SERVICES
B1506192 / CONSTRUCTION
REPLACE EXISTING INOPERABLE GENERAC GENERATOR WITH A NEW 6.7L GENERAC GENERATOR
1015 HALF ST SE   
04/11/15 
HALF ST SE LLC / ANDREW ARNTSON; HALF ST SE LLC; ANDREW ARNTSON
P63100436 / SUPPLEMENTAL
55 M ST SE   
04/14/15 
HINES GLOBAL REIT / JOHN GIUSEPPE-RAMCO
TL1500090 / CONSTRUCTION
FIRST TIME TENANT CONSTRUCTION FOR NEW OFFICE SPACE ON THE 9TH FLOOR FINCANTIERI MARINE GROUP AS SHOWN ON THE ATTACHED THIRD PARTY REVIEWED AND APPROVED MECH. PLUMB. ELECT. FIRE PROTECTION AND ARCH. PLANS BY KTA GROUP. INTERIOR WORK ONLY. NO CHANGE IN USE.
   
04/15/15 
HINES GLOBAL REIT / JOHN GIUSEPPE-RAMCO
TL1500077 / CONSTRUCTION
TENANT LAYOUT TO CONSTRUCTION NEWTHIRD FLOOR OFFICE SPACE FOR GREAT MINDS AS SHOWN ON THE ATTACHED THIRD PARTY REVIEWED AND APPROVED MECH. PLUMB. ELECT. FIRE PROTECTION AND ARCH. DWGS. BY KTA. INTERIOR WORK ONLY NO STRUCTURAL WORK INVOLVED.
   
04/17/15 
HINES GLOBAL REIT 55 M STREET LLC /
P1505068 / SUPPLEMENTAL
80 M ST SE   
04/20/15 
WELLS REIT II 80 M STREET LLC / JOHN GIUSEPPE-RAMCO
B1503697 / CONSTRUCTION
RENOVATIONS TO EXISTING 5TH FLOOR OFFICE SPACE FOR TASC PHASE I AS SHOWN ON THE ATTACHED THIRD PARTY REVIEWED AND APPROVED MECH. PLUMB. ELECT. FIRE PROTECTION DEMOLITION AND ARCH. DWGS. BY KTA. INTERIOR WORK ONLY. NO STRUCTURAL WORK INVOLVED. NO CHANGE IN USE.
50 M ST SE   
04/07/15 
KCG 50 M LLC / FVI2020
B1501877 / CONSTRUCTION
A NEW 11 STORY AND PENTHOUSE LEVEL HOTEL WITH 195 ROOMS INCLUDING 766 SQ-FT FUNCTION ROOM 2ND FLOOR AND 4874 SQ-FT OF GENERAL RETAIL USE ON THE 1ST FLOOR. THE BUILDING WILL HAVE 2 BELOW GRADE PARKING LEVELS TO ACCOMODATE REQUIRED AUTOMOBILE PARKING. LOADING IS ACCOMODATED AT THE 1ST FLOOR.
80 M ST SE   
04/21/15 
WELLS REIT II 80 M STREET LLC / RONNIE E WRIGHT
E1505080 / SUPPLEMENTAL
   
04/21/15 
NOT AVAILABLE NOT AVAILABLE / NEIL NUTWELL; NOT AVAILABLE NOT AVAILABLE; NEIL NUTWELL
P84507258 / SUPPLEMENTAL
   
04/21/15 
UNKNOWN UNKNOWN / PATRICK BARRON; UNKNOWN UNKNOWN; ROBIN MALLEY
E38207212 / SUPPLEMENTAL
300 M ST SE   
04/21/15 
NA NA NA
EHOP1290001 / HOME OCCUPATION
1201 M ST SE   
04/09/15 
COPT / EVAN O'BRIEN/ D MCKEEVER SERVICES
B1505061 / CONSTRUCTION
INTERIOR RENOVATION ONLY TO BATHROOMS ON FLOORS 1-4.
909 NEW JERSEY AVE SE   
04/07/15 
909 NEW JERSEY AVENUE ACQUISITION LLC / SHAW HERGENRATHER
P1504830 / SUPPLEMENTAL
1200 NEW JERSEY AVE SE   
04/08/15 
JBG/FEDERAL CENTER LLC / JOHN MCDONALD
P1504842 / SUPPLEMENTAL
1000 NEW JERSEY AVE SE   
04/07/15 
PHILIP BROWN
PC93167082 / POST CARD
REPLACEMENT OF NOT MORE THAN 1 GAS APPLIANCE ON A RESIDENTIAL COMMERCIAL OR INDUSTRIAL PROJECT.
   
04/13/15 
CAPITOL HILL TOWER HOUSING COOPERATIVE INCF / BRIAN DENNIS
P1504947 / SUPPLEMENTAL
1500 SOUTH CAPITOL ST SE   
04/06/15 
WASHINGTON NATIONALS STADIUM LLC / JOHN GIUSEPPE-RAMCO
B1503799 / CONSTRUCTION
RENOVATIONS FOR NATIONALS NEW TEAM STORE LOCATED AT THE EAST GARAGE CONCOURSE AND 400 LEVELS AS SHOWN ON THE ATTACHED THIRD PARTY REVIEWED AND APPROVED MECHANICAL PLUMBING ELECTRICAL FIRE PROTECTION DEMOLITION ARCHITECTURAL AND STRUCTURAL DWGS. BY ECS MID-ATLANTIC LLC.
   
04/06/15 
WASHINGTON NATIONALS STADIUM LLC / JOHN GIUSEPPE-RAMCO
B1505076 / CONSTRUCTION
RENOVATIONS TO EXISTING CONCESSION STAND LOCATED ON THE 300 LEVEL OF NATS PARK STAND 310 NATIONALS PIZZA AS SHOWN ON THE ATTACHED THIRD PARTY REVIEWED AND APPROVED MECH. PLUMB. ELECT. FIRE PROTECTION AND ARCH. DWGS. BY ECS MID-ATLANTIC LLC. NO CHANGE IN USE NO STRUCTURAL WORK INVOLVED.
   
04/07/15 
NATIONALS STADUIM / RANDAL COX; NATIONALS STADUIM; RANDAL COX
E37461133 / SUPPLEMENTAL
   
04/08/15 
WASHINGTON NATIONAL STADIUM LIC. / DAVID C. WILLIAMS
E1504771 / SUPPLEMENTAL
   
04/09/15 
JOHN GIUSEPPE / PHIL HAUHN; JOHN GIUSEPPE; PHILIP HAUHN
E19554829 / SUPPLEMENTAL
   
04/15/15 
WASHINGTON NATIONALS STADIUM LLC / JOHN GIUSEPPE-RAMCO
B1506296 / CONSTRUCTION
REVISION TO BLDG. PERMIT B1503799 NEW TEAM STORE AT NATIONALS PARK AS PER THE ATTACHED THIRD PARTY REVIEWED AND APPROVED REVISED MECH. PLUMB. ELECT. FIRE PROTECTION AND ARCH. PLANS BY ECS MID ATLANTIC LLC. ORIGINAL APPROVED PLAN SET ATTACHED ALONG WITH WRITTEN DESCRIPTION OF CHANGES MADE.
   
04/17/15 
WASHINGTON NATIONAL STADIUM LLC / DOMINIC E TOTARO
M1501639 / SUPPLEMENTAL
   
04/17/15 
WASHINGTON NATIONALS STADIUM / STEPHEN J. EXELBERT
P1505092 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
1022 - 1109 M ST SE   03/27/15
$ 5,000,000
WASHINGTON HUMANE SOCIETY
 
9TH ST SE   03/03/15
$ 3,730,000
818 POTOMAC AVENUE SE LLC
 
POTOMAC AV SE   03/03/15
$ 3,730,000
818 POTOMAC AVENUE SE LLC
 
POTOMAC AV SE   03/03/15
$ 3,730,000
818 POTOMAC AVENUE SE LLC
 
POTOMAC AV SE   03/03/15
$ 3,730,000
818 POTOMAC AVENUE SE LLC
 
1103 9TH ST SE   03/03/15
$ 3,730,000
818 POTOMAC AVENUE SE LLC
 
1105 9TH ST SE   03/03/15
$ 3,730,000
818 POTOMAC AVENUE SE LLC
 
816 POTOMAC AVE SE   03/03/15
$ 3,730,000
818 POTOMAC AVENUE SE LLC
 
0819R L ST SE   03/03/15
$ 3,730,000
818 POTOMAC AVENUE SE LLC
 
1201 HALF ST SE   02/19/15
$ 9,000,000
WEST HALF RESIDENTIAL II LLC
 
N ST SE   02/19/15
$ 36,000,000
WEST HALF RESIDENTIAL III LLC
 
0038 N ST SE   02/19/15
$ 36,000,000
WEST HALF RESIDENTIAL III LLC
 
0036 N ST SE   02/19/15
$ 36,000,000
WEST HALF RESIDENTIAL III LLC
 
R N ST SE   02/19/15
$ 36,000,000
WEST HALF RESIDENTIAL III LLC
 
0030 N ST SE   02/19/15
$ 36,000,000
WEST HALF RESIDENTIAL III LLC
 
0032 N ST SE   02/19/15
$ 36,000,000
WEST HALF RESIDENTIAL III LLC
 
N ST SE   02/19/15
$ 36,000,000
WEST HALF RESIDENTIAL III LLC
 
1275 HALF ST   02/19/15
$ 36,000,000
WEST HALF RESIDENTIAL III LLC
 
HALF ST   02/19/15
$ 36,000,000
WEST HALF RESIDENTIAL III LLC
 
M ST   02/19/15
$ 36,000,000
WEST HALF RESIDENTIAL III LLC
 
1ST ST SE   02/10/15
$ 1,913,472
BALLPARK HOTEL LLC
 
1ST ST SE   02/10/15
$ 1,913,472
BALLPARK HOTEL LLC
 
1ST ST SE   02/10/15
$ 1,913,472
BALLPARK HOTEL LLC
 
1ST ST SE   02/10/15
$ 6,600,000
BALLPARK RESIDENTIAL LLC
 
1ST ST SE   02/10/15
$ 6,600,000
BALLPARK RESIDENTIAL LLC
 
1ST ST SE   02/10/15
$ 6,600,000
BALLPARK RESIDENTIAL LLC
 
1ST ST SE   02/10/15
$ 6,600,000
BALLPARK RESIDENTIAL LLC
 


Project Directory




     © Copyright 2015 JD.