I almost can't bring myself to write the words, but the owners of the Florida Rock site just south of Nationals Park have filed with the Zoning Commission for not only the previously reported plan to change the planned first phase office building to a residential one, but also to revisit parts of the site plan for the three subsequent phases. (For those of you versed in zoning speak, they are requesting to "revert Phases II, III, and IV to First Stage Approvals with modifications.")
This is going to be a lengthy process, with hearings at the Zoning Commission, reports from the Office of Planning and others, and presentations to the ANC (starting with one this coming Monday night, Dec. 12). So I'm going to avoid getting into the weeds too much too early, and will just give some bullet points of what changes they are looking for. (You're free to read these 57 pages of the filing for more detail.)
* The new Phase 1 building, at the far east end of the site (next to Diamond Teague Park) will now be the aforementioned residential building, a nine-story U-shaped design oriented toward the river with 300-350 units and 286 below-grade parking spaces. There will still be 12,500 square feet of retail, though they are asking that 7,000 of it be "flex space" that "may alternatively be dedicated to residential amenity space" until retail gets going. There will be a private courtyard within the "U", but there will also be the open space on the buildings' east side, now dubbed Anacostia Plaza, that will be open enough to maintain open views from First Street and the stadium's Grand Staircase to the river but will also provide "passive recreation space."
* The esplanade that has always been such a big part of the site plan remains, acting as the portion of the Anacostia Riverwalk Trail connecting South Capitol Street to Teague Park, the new pedestrian bridge, and the Yards Park. The Esplanade will "relate" to the "design vernacular" of the newly constructed boardwalks, and will also have a lot of stormwater management and bio-filtration offerings.
* On the building's west side will be the "Mews," which they call a pedestrian boulevard separating the Phase 1 building from the planned Phase 2 residential building. This path will also provide access to parking and loading for the first two phases, but "a dynamic paving design . . . will help distinguish this area as an urban space that privileges pedestrians over vehicles."
* The filing says they anticipate construction to begin in the second quarter of 2013, with first move-ins in early 2015 and the entire phase completed by summer 2015.
As for overall changes, here's what seem to be the most interesting changes from the previously approved design that the developers are looking for:
* The new plan would bring 1,164,640 square feet of gross floor area (4.6 FAR), up from 1,115,400 sq ft/4.4 FAR in the last plan. The other three phases' uses would remain unchanged (residential, office, hotel).
* Building heights of 130 feet for Phase 2-4 are being requested, compared to 130/112/130 last time around.
* Below-grade parking spaces would go from 1,010 to 1,144.
Plus, though It's hard to tell from one small site plan concept drawing, a lot of the public space design, especially to the east of the Phase 3 and 4 buildings, looks scaled back from the 2008 design. (UPDATE: Here's a graphic put together from another part of the filing that compares the 2008 site plan with the current one.)
The filing also says that "the Applicant would like the flexibility to provide interim uses on Phases, II, III, IV so that the site will not simply lay dormant pending construction," and lists a park, a farmers market, or other "simple, temporary retail uses" as examples.
And, just as in the previous plans, development of phases 3 and 4 are completely dependent on the construction of a new South Capitol Street Bridge, since the current bridge bisects the property where those buildings are planned.
Again, this is early in this new process, and there will be plenty of filings and presentations to come for all the additional detail you're going to be clamoring for. For now, the takeaway is that FRP/MRP want to get started on a residential building at 1st and Potomac in the spring of 2013, and still want to move forward on the rest of the site with a design similar to what was approved 3 1/2 years ago, but with some modifications.
This project first began its zoning quest in 1998, and went through a four-year process ending in 2008 to get its second-stage approvals. I should also note that Davis Buckley Architects, who worked on the project throughout that 10-year ordeal, is no longer part of the design team; SK&I is now on board, with Oculus as the landscape design firm. The site's owners, FRP Development/Florida Rock Properties, announced their partnership with MRP Realty earlier this year.
(As for the concrete plant currently on site, I haven't looked lately, but demolition is underway, and the filing says it should be done by the end of the year. Tom Boswell's heart will be broken.)
UPDATE, 1/3: Just before Christmas, demolition was finished on the plant, making it #166 in my Demolished Buildings Gallery.
Comments (3)
   
 
 More About Florida Rock
 All posts: Florida Rock, zoning

JDLand.com Home

Comments

lester says: (12/9/11 3:15 PM)
130 feet tall? That's curious.

The area is zoned W-2, which would traditionally allow for up to 60 feet. It's part of the capital gateway overlay, which is designed "to reduce the height and bulk of buildings along the Anacostia riverfront."

Then DC goes ahead and approved (previously) 130/112/130 foot tall buildings (Phase II, III, and IV, not sure what Phase I will be). Wow. The wonders of the PUD (which basically nullifies the W-2 and CG designation).

However, moving past these decisions, how on earth do they justify 130 feet with respect to the Heights of Building Act of 1910? To allow a 130 foot tall building, you would need to have either South Capitol or Potomac be 110' wide, and as best as I can estimate from the DC property records web site, they are at most 90' wide. What gives?

Either way, it seems silly to develop an overlay to reduce height and bulk near the Anacostia riverfront, and then approve four buildings on the waterfront 100+ feet high...

Mind you, from where I live, the buildings won't really impact my view at all, I just find it all very... strange.


JD says: (12/9/11 3:22 PM)
Phase I was originally approved at 92 feet; they're requesting 95 feet this time.

There's a fair amount of discussion of the zoning starting around page 11 in the document I link to above, which says that CG/W-2 (the Capitol Gateway overlay) allows for max heights of 130 ft in mixed-use developments. (Purely commercial buildings can only be 60 feet high; the CG overlay gives the opportunity for increased density by developing mixed-use.)

Here's the Capitol Gateway Overlay, if you want to read: link




IMGoph says: (12/17/11 12:17 AM)
I like the fact that the building footprints aren't curvy like the Watergate anymore. That footprint just felt contrived.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2018!
 Top News
  

202_cyclist on April Cosntruction Report: @malatesta— I am eagerly awaiting the robot wars!
202_cyclist on April Cosntruction Report: Unfortunately, unless JD were to join Michael Cohen in Club Fed, there won’t be ...
JD on April Cosntruction Report: I don't think we're allowed to fly drones this close to the Capitol anyway.
malatesta on April Cosntruction Report: I actually have no idea what a drone costs, or what the cost-benefit analysis wo...
Message Board (beta)

Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1100 B/O NEW JERSEY AVE SE   SEX ABUSE
First Degree Sexual Abuse
 04/17/18
400 B/O M ST SE   THEFT
Shoplifting
 04/17/18
100 B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 04/17/18
UNIT B/O N ST SE   ROBBERY  04/14/18
100 B/O I ST SE   THEFT
Theft 2nd Degree (theft From Building)
 04/12/18
UNIT B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 04/12/18
1200 B/O 4TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 04/09/18
150 B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 04/07/18
1000 B/O 3RD ST SE   BURGLARY
Burglary One
 04/07/18
1200 B/O NEW JERSEY AVE SE   ROBBERY
Assault W/i To Commit Robbery (simple Assault)
 04/05/18
UNIT B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 04/01/18
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 03/31/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 03/28/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 03/28/18
300 B/O I ST SE   ASSAULT WITH A DANGEROUS WEAPON  03/25/18
UNIT B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 03/23/18
100 B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 03/23/18
UNIT B/O I ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 03/23/18

Recent Issued Building Permits Archive  
1331 2 ST SE   
04/02/18 
DISTRICT OF COLUMBIA / MARK HARLOW CLIFFORD
SB1800225 / CONSTRUCTION
Application for Well Abandonment Workplan Approval for the abandonment of 8 monitoring wells and 21 inclinometers at the Main Pumping Station site for the DC Water Clean Rivers Project, Division I, installed under Permit Number SB1400419.
1100 2ND PL SE   
04/19/18 
CAPPER CARROLLSBURG VENTURE, LLC / TAMIKA STATON; OTIS
EN1801710 / SHOP DRAWING
Install 1 New G2S 3500LBS @350FPM, Elevator 2; 13 Floors
   
04/19/18 
CAPPER CARROLLSBURG VENTURE, LLC / TAMIKA STATON; OTIS
EN1801712 / SHOP DRAWING
Install 2 New G2S Elevators - 3500LBS@35FPM Elevator 1, 12 Floors
1331 2ND ST SE 20003   
04/05/18 
DC WATER / DAVE LEVINE
AH1800744 / CONSTRUCTION
After Hours work for structure excavation in support of DC Water, Corrman Construction 301-343-5417.
1300 4TH ST SE   
04/17/18 
null / DONNA G GRAHAM
AH1800863 / CONSTRUCTION
WR #3476633-WARD 6-20003-VAETH / BRUNO - PEPCO CREWS WILL BE WORKING THE 1200 - 1300 BLK OF 4TH ST SE - INSTALLING NETWORK TRANSFORMER AND INSTALLING PRIMARY CABLES - STARTING THURSDAY 4 / 19 / 18 UNTIL 5 / 19 / 18 - MONDAY THRU FRIDAYS AT 10PM UNTIL 10AM AND ON SATURDAY AND SUNDAYS FROM 6AM TIL 8PM.
1346 4TH ST SE   
04/10/18 
ALAN OWINGS / ROBERT HENRY
AH1800796 / CONSTRUCTION
After Hours Permit for 04 / 16 / 18 from 9AM to 7PM to perform facade, interior unit framing and drywall work, and interior Mechanical, Electrical, Plumbing and Sprinkler Rough-In.
1346 4TH ST ST SE 20003   
03/28/18 
FOREST CITY / TYLER D BARRON
AH1800712 / CONSTRUCTION
After hours for 4 / 13 / 18 to 5 / 12 / 18. Work that is to be done is quiet work of window deliveries at 5:30AM to 7:00AM by use of tower crane
82 I ST SE   
04/02/18 
GDVC EYE STREET LLC / null
FB1800055 / SUPPLEMENTAL
150 I ST SE   
03/28/18 
null
E1805313 / SUPPLEMENTAL
   
03/29/18 
null / JOHN THOMSON 3018645080
E1805337 / SUPPLEMENTAL
300 M ST SE 400   
04/09/18 
FEDERAL CENTER LP / null
M1801970 / SUPPLEMENTAL
300 M ST SE STE# 400 20024   
04/05/18 
CHARLES SMITH / EUGENE AHNS 3012811497
E1805597 / SUPPLEMENTAL
300 M ST SE STE# 400   
04/12/18 
FEDERAL CENTER LP / null
P1805161 / SUPPLEMENTAL
140 M ST SE   
03/26/18 
SQUARE 742 LLC / null
P1804630 / SUPPLEMENTAL
300 M ST SE   
03/26/18 
FEDERAL CENTER LP / JERRY BETHEA
M1801846 / SUPPLEMENTAL
401 M ST SE   
04/03/18 
TETRA TECH C/O DOEE / JESSICA REICHARD
AH1800767 / CONSTRUCTION
After hours permit for manhole access to complete inspections for DOEE Anacosta River Sediment clean up project, work hours between 7pm and 7am Monday thru Friday. Rolling work zones for all manhole access under permit # PA10374319-R1
800 NEW JERSEY AVE SE   
04/05/18 
SQUARE 737 LLC / null
P1804974 / SUPPLEMENTAL
   
04/09/18 
SQUARE 737 LLC / null
E1805700 / SUPPLEMENTAL
861 NEW JERSEY AVE SE   
04/02/18 
CONSOLIDATED RAIL CORPORATION / NA CSX TRANSPORTATION, INC.
AH1800715 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities.
   
04/11/18 
CONSOLIDATED RAIL CORPORATION / DEVIN MURDOCK
SB1800265 / CONSTRUCTION
Drill 8 borings to 40ft. Convert 4 borings into 1" temporary wells, collect groundwater from each well and abandon borings.
1100 NEW JERSEY AVE SE   
04/18/18 
null
E1805988 / SUPPLEMENTAL
1115 NEW JERSEY AVE SE   
04/17/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / GARY BRENT; BRENT
SG1800260 / CONSTRUCTION
Install 1 illuminated wall sign, 1 illuminated window sign and 1 window vinyl decal sign - Peets Coffee
1100 NEW JERSEY AVE SE 5TH FL   
04/19/18 
SQUARE 742 LLC / DOMINIC E TOTARO 301-725-1998
M1802089 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
04/13/18 
SQUARE 742 LLC / CLIFFORD DIXON
B1804348 / CONSTRUCTION
INTERIOR RENOVATIONS TO OFFICE SPACE ON THE 5TH FLOOR. **DEMOLITION, LEVEL 2 ALTERATION
   
04/19/18 
SQUARE 742 LLC / PEDRO C. CASTILLO 3019219056
E1806025 / SUPPLEMENTAL
   
04/19/18 
SQUARE 742 LLC / null
E1806015 / SUPPLEMENTAL
1115 NEW JERSEY AVE SE   
04/06/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / ACCUPERMIT LLC AS AGENT
B1803009 / CONSTRUCTION
Interior alterations for new tenant in existing commercial space to include partitions, mill work, electrical and plumbing fixtures, flooring and wall coverings, dining area furniture and kitchen equipment for a A-2 restaurant with 49 proposed occupancy.
125 O ST SE   
03/29/18 
DISTRICT OF COLUMBIA / JAMES M. HALLER
P1804624 / SUPPLEMENTAL
   
04/09/18 
DISTRICT OF COLUMBIA / TAMIKA STATON; OTIS
EN1801762 / SHOP DRAWING
I New G2S Elevator - 3500LBS @ 200FPM (7 Floors)
   
04/09/18 
DISTRICT OF COLUMBIA / TAMIKA STATON; OTIS
EN1801763 / SHOP DRAWING
Install 1 New G2S Elevator - 3500LBS @ 200FPM (6 Floors)
   
04/09/18 
DISTRICT OF COLUMBIA / TAMIKA STATON; OTIS
EN1801761 / SHOP DRAWING
Install 1 New G2S Elevators 4000LBS @ 200FPM (7 Floors)
71 POTOMAC AVE SE 20002   
04/19/18 
null / STEVE GRIFFIN
BP1802939 / POST CARD
71 POTOMAC AVE SE   
03/26/18 
FORIDA ROCK PROPERTIES INC / null
BCIV1800074 / CONSTRUCTION
This permit is for rough grading and erosion and sediment control civil work associated with the temporary parking lot, relocation of the dog park and construction staging area on the undeveloped portion of the lot.
   
04/17/18 
RIVERFRONT HOLDINGS I LLC / JUSTIN BELLOW
FD1800020 / CONSTRUCTION
Foundation only for new residential building
227 TINGEY ST SE   
03/28/18 
UNITED STATES OF AMERICA / ERICKA CLARK
AH1800760 / CONSTRUCTION
significant concrete pours and tower crane erection 5AM - 7AM and 7PM - 10:00PM
   
04/12/18 
UNITED STATES OF AMERICA / STEPHEN J. EXELBERT
P1805022 / SUPPLEMENTAL
300 TINGEY ST SE   
04/12/18 
MERCURY LLC / WILL TEASS
B1803433 / CONSTRUCTION
INTERIOR FIT-OUT / EXTENSION OF EXISTING TENANT SUITE (APPROVED UNDER B1605215) INCLUDING NEW MECHANICAL AND ELECTRICAL WORK. **LEVEL 2 ALTERATION
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.