I almost can't bring myself to write the words, but the owners of the Florida Rock site just south of Nationals Park have filed with the Zoning Commission for not only the previously reported plan to change the planned first phase office building to a residential one, but also to revisit parts of the site plan for the three subsequent phases. (For those of you versed in zoning speak, they are requesting to "revert Phases II, III, and IV to First Stage Approvals with modifications.")
This is going to be a lengthy process, with hearings at the Zoning Commission, reports from the Office of Planning and others, and presentations to the ANC (starting with one this coming Monday night, Dec. 12). So I'm going to avoid getting into the weeds too much too early, and will just give some bullet points of what changes they are looking for. (You're free to read these 57 pages of the filing for more detail.)
* The new Phase 1 building, at the far east end of the site (next to Diamond Teague Park) will now be the aforementioned residential building, a nine-story U-shaped design oriented toward the river with 300-350 units and 286 below-grade parking spaces. There will still be 12,500 square feet of retail, though they are asking that 7,000 of it be "flex space" that "may alternatively be dedicated to residential amenity space" until retail gets going. There will be a private courtyard within the "U", but there will also be the open space on the buildings' east side, now dubbed Anacostia Plaza, that will be open enough to maintain open views from First Street and the stadium's Grand Staircase to the river but will also provide "passive recreation space."
* The esplanade that has always been such a big part of the site plan remains, acting as the portion of the Anacostia Riverwalk Trail connecting South Capitol Street to Teague Park, the new pedestrian bridge, and the Yards Park. The Esplanade will "relate" to the "design vernacular" of the newly constructed boardwalks, and will also have a lot of stormwater management and bio-filtration offerings.
* On the building's west side will be the "Mews," which they call a pedestrian boulevard separating the Phase 1 building from the planned Phase 2 residential building. This path will also provide access to parking and loading for the first two phases, but "a dynamic paving design . . . will help distinguish this area as an urban space that privileges pedestrians over vehicles."
* The filing says they anticipate construction to begin in the second quarter of 2013, with first move-ins in early 2015 and the entire phase completed by summer 2015.
As for overall changes, here's what seem to be the most interesting changes from the previously approved design that the developers are looking for:
* The new plan would bring 1,164,640 square feet of gross floor area (4.6 FAR), up from 1,115,400 sq ft/4.4 FAR in the last plan. The other three phases' uses would remain unchanged (residential, office, hotel).
* Building heights of 130 feet for Phase 2-4 are being requested, compared to 130/112/130 last time around.
* Below-grade parking spaces would go from 1,010 to 1,144.
Plus, though It's hard to tell from one small site plan concept drawing, a lot of the public space design, especially to the east of the Phase 3 and 4 buildings, looks scaled back from the 2008 design. (UPDATE: Here's a graphic put together from another part of the filing that compares the 2008 site plan with the current one.)
The filing also says that "the Applicant would like the flexibility to provide interim uses on Phases, II, III, IV so that the site will not simply lay dormant pending construction," and lists a park, a farmers market, or other "simple, temporary retail uses" as examples.
And, just as in the previous plans, development of phases 3 and 4 are completely dependent on the construction of a new South Capitol Street Bridge, since the current bridge bisects the property where those buildings are planned.
Again, this is early in this new process, and there will be plenty of filings and presentations to come for all the additional detail you're going to be clamoring for. For now, the takeaway is that FRP/MRP want to get started on a residential building at 1st and Potomac in the spring of 2013, and still want to move forward on the rest of the site with a design similar to what was approved 3 1/2 years ago, but with some modifications.
This project first began its zoning quest in 1998, and went through a four-year process ending in 2008 to get its second-stage approvals. I should also note that Davis Buckley Architects, who worked on the project throughout that 10-year ordeal, is no longer part of the design team; SK&I is now on board, with Oculus as the landscape design firm. The site's owners, FRP Development/Florida Rock Properties, announced their partnership with MRP Realty earlier this year.
(As for the concrete plant currently on site, I haven't looked lately, but demolition is underway, and the filing says it should be done by the end of the year. Tom Boswell's heart will be broken.)
UPDATE, 1/3: Just before Christmas, demolition was finished on the plant, making it #166 in my Demolished Buildings Gallery.
Comments (3)
   
 
 More About Florida Rock
 All posts: Florida Rock, zoning

JDLand.com Home

Comments

lester says: (12/9/11 3:15 PM)
130 feet tall? That's curious.

The area is zoned W-2, which would traditionally allow for up to 60 feet. It's part of the capital gateway overlay, which is designed "to reduce the height and bulk of buildings along the Anacostia riverfront."

Then DC goes ahead and approved (previously) 130/112/130 foot tall buildings (Phase II, III, and IV, not sure what Phase I will be). Wow. The wonders of the PUD (which basically nullifies the W-2 and CG designation).

However, moving past these decisions, how on earth do they justify 130 feet with respect to the Heights of Building Act of 1910? To allow a 130 foot tall building, you would need to have either South Capitol or Potomac be 110' wide, and as best as I can estimate from the DC property records web site, they are at most 90' wide. What gives?

Either way, it seems silly to develop an overlay to reduce height and bulk near the Anacostia riverfront, and then approve four buildings on the waterfront 100+ feet high...

Mind you, from where I live, the buildings won't really impact my view at all, I just find it all very... strange.


JD says: (12/9/11 3:22 PM)
Phase I was originally approved at 92 feet; they're requesting 95 feet this time.

There's a fair amount of discussion of the zoning starting around page 11 in the document I link to above, which says that CG/W-2 (the Capitol Gateway overlay) allows for max heights of 130 ft in mixed-use developments. (Purely commercial buildings can only be 60 feet high; the CG overlay gives the opportunity for increased density by developing mixed-use.)

Here's the Capitol Gateway Overlay, if you want to read: link




IMGoph says: (12/17/11 12:17 AM)
I like the fact that the building footprints aren't curvy like the Watergate anymore. That footprint just felt contrived.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2016!
 Top News

conngs0 on Two-Year Change in: I think CSX has done a decent job of mitigating the inconveniences that weren't ...
JD on Two-Year Change in: I'm not sure that in the FEIS they said it wouldn't be closed at all--there had ...
walt on Two-Year Change in: CSX and city officials promised in the Final environment impact study (FEI)? tha...

Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1200 B/O 4TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/17/16
1000 B/O HALF ST SE   THEFT
Theft First Degree (all Other Larceny)
 08/16/16
700 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/15/16
1400 B/O SOUTH CAPITOL ST   THEFT
Theft 2nd Degree (all Other Larceny)
 08/14/16
16 B/O M ST SE   ROBBERY  08/12/16
1000 B/O 5TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/09/16
1200 B/O 1ST ST SE   THEFT
Theft First Degree (shoplifting)
 08/08/16
50 B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 08/02/16
600 B/O I ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/02/16
700 B/O L ST SE   ROBBERY  08/01/16
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/29/16
700 B/O L ST SE   ROBBERY  07/28/16
1100 B/O K ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 07/25/16
1200 B/O HALF ST SE   BURGLARY
Burglary Two
 07/24/16
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/23/16
900 B/O 5TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/23/16
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/22/16
1100 B/O NEW JERSEY AVE SE   THEFT
Shoplifting
 07/20/16
900 B/O 4TH ST SE   ROBBERY  07/20/16
500 B/O L ST SE   THEFT
Theft First Degree (all Other Larceny)
 07/19/16
1400 B/O SOUTH CAPITOL ST   THEFT
Theft 2nd Degree (theft From Building)
 07/19/16

Recent Issued Building Permits Archive  
1004 1ST ST SE   
08/04/16 
SQ. 740 LLC / N/A SQ 740 LLC JOHN AKRIDGE DEVELOP COMPANY; ECC, INC.
SB1600325 / CONSTRUCTION
Due diligence investigation. Installation of six 3-inch diameter direct-push geoprobe soil borings to depths of approximately 30 below grade. Soil borings will be abandoned on the same day as drilling by tremi-grouting using a bentonite slurry composed of 2 pounds of bentonite powder to 1 gallon of water. IDW will be properly managed.
1212 4TH ST SE 120   
08/04/16 
FC 1212 LLC / CLARK S FULLER
M1603023 / SUPPLEMENTAL
1150 5TH ST SE 20002   
08/11/16 
ALAN J PHELPS / DOUGLAS FOSTER
B1509540 / CONSTRUCTION
1. Renovation of existing first and second floor of the academic wing of the Van Ness building. 2. Square footage is approximately 26,000 SF ,For phase 1 3. Cost of construction is 11.5M 4. Scope of work details a. Convert existing space in to 6 new classroom space. These classrooms will be two PreK -3, two prek-4, and two Kindergarten classes. Also for phase 1,...
1150 5TH ST SE   
08/12/16 
DISTRICT OF COLUMBIA / JOHN HOMICK
E1609156 / SUPPLEMENTAL
   
08/12/16 
DISTRICT OF COLUMBIA / MATT LOSIGNOR
P1608656 / SUPPLEMENTAL
   
08/12/16 
DISTRICT OF COLUMBIA / ORLANDO M CATANA
E1609149 / SUPPLEMENTAL
1220 HALF ST SE   
08/05/16 
NA BUFFALO WILD WINGS / NA BUFFALO WILD WINGS; BELA X-PEDITERS PLUS, INC.
AH1600921 / CONSTRUCTION
Work after hours 7pm - 7am
82 I ST SE   
08/15/16 
GDCV EYE STREET LLC / GDCV EYE STREET LLC; KIM MITCHELL CDKM CONSULTING LLC
B1611941 / CONSTRUCTION
FIRST EXTENSION TO PERMIT B1507990 TO EXPIRE ON 3 / 17 / 17
   
08/15/16 
CSX TRANSPORTATION INC / BEDCO MOBILITY INC.
EN1602806 / SHOP DRAWING
Type of Elevator : One (1) vertical wheel-chair lift / steel / garage level 2 / handicap lift (13th floor)
150 I ST SE   
08/05/16 
MAXIM CRANE WORKS MAXIM CRANE WORKS
AH1600933 / CONSTRUCTION
after hours to place mobile crane to take down tower crane with mobile crane and stage trucks from 7am 8 / 8 / 2016 to 1159p-m 8 / 9 / 2016
125 L ST SE   
08/11/16 
CRANE SERVICE CO / CRANE SERVICE CO; CHRISTINE LONG
AH1600945 / CONSTRUCTION
An after hours permit is respectfully requested from 4AM Saturday thru 9PM Sunday
80 M ST SE 1   
08/10/16 
WELLS REIT II 80 M STREET LLC / THOMAS B. STEG
P1608566 / SUPPLEMENTAL
80 M ST SE 2   
08/10/16 
WELLS REIT II 80 M STREET LLC / THOMAS B. STEG
P1608568 / SUPPLEMENTAL
80 M ST SE 3   
08/10/16 
WELLS REIT II 80 M STREET LLC / THOMAS B. STEG
P1608569 / SUPPLEMENTAL
100 M ST SE 7   
08/04/16 
SQUARE 743 INC / ANTHONY G SAMBURG
E1608667 / SUPPLEMENTAL
100 M ST SE PT OF 4TH   
08/11/16 
QUARE 743 INC . / QUARE 743 INC .; JOHN GIUSEPPE-RAMCO
B1611810 / CONSTRUCTION
renovation to parts of an existing 4th floor office space, tech marine business as shown on the attached mech., plumb., elect., fire protection, demolition, and arch. dwgs. interior work only. no change in use. no struct. work. 800 sf.
300 M ST SE   
08/05/16 
FEDERAL CENTER LP / null
F1600517 / CONSTRUCTION
   
08/06/16 
FGSF TEST
PC92978992 / POST CARD
Installation of 1 temporary construction trailer on private property.
   
08/06/16 
SDS SDSDS / LAVANYA SIKHINAM; SDS SDSDS; ENRIQUE LYON
E90011839 / SUPPLEMENTAL
   
08/07/16 
XVB XVBX / FSGVSF SFGS; XVB XVBX; DAVID FARMER
E77515115 / SUPPLEMENTAL
909 NEW JERSEY AVE SE 1311   
08/11/16 
null / NA NA NA
EHOP1690902 / HOME OCCUPATION
861 NEW JERSEY AVE SE   
08/09/16 
NA CSX TRANSPORTATION, INC.
AH1600944 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities.
1000 NEW JERSEY AVE SE   
08/02/16 
null / ALLISON HINES
PC66310814 / POST CARD
Replacement of not more than 1 gas appliance, on a residential, commercial or industrial project.
1017 NEW JERSEY AVE SE   
08/04/16 
1021 NEW JERSEY AVE LLC / N/A 1021 NEW JERSEY AVE LLC POTOMAC DEVELOPMENT; ECC, INC.
SB1600326 / CONSTRUCTION
Due diligence investigation. Installation of one 3-inch diameter direct-push geoprobe soil borings to depths of approximately 30 feet below grade. Soil borings will be abandoned on the same day as drilling by tremi-grouting using a bentonite slurry composed of 2 pounds of bentonite powder to 1 gallon of water. IDW will be properly managed.
1029 NEW JERSEY AVE SE   
08/04/16 
MESERET DEGEFU / HAILU TEKLEBERHAN; ECC, INC.
SB1600327 / CONSTRUCTION
Due diligence investigation. Installation of two 3-inch diameter direct-push geoprobe soil borings to depths of approximately 30 feet below grade. Soil borings will be abandoned on the same day as drilling by tremi-grouting using a bentonite slurry composed of 2 pounds of bentonite powder to 1 gallon of water. IDW will be properly managed.
1111 NEW JERSEY AVE SE   
08/11/16 
null / THOMAS P MCGUIRE
E1609117 / SUPPLEMENTAL
125 O ST SE   
08/04/16 
JOHN LECKER, FOREST CITY WASHINGTON, INC / JOHN LECKER, FOREST CITY WASHINGTON, INC; RACHEL DOERY, PSI
SB1600337 / CONSTRUCTION
Site is located south of N Pl SE, 500ft east of intersect with First St, SE in Washington, DC. Drilling soil borings at site for future development of a 4-story concrete parking garage with 331 parking spaces at street level. A 2-story theater will be constructed above the parking garage totaling approximately 95,000 sf.
25 POTOMAC AVE SE   
08/03/16 
RIVERFRONT INVESTMENT PARTNERS / RIVERFRONT INVESTMENT PARTNERS; JASON BENTLEY
B1610683 / CONSTRUCTION
Revision to Issued Permit Number B1408697.
741 SICARD ST SE 20374   
07/29/16 
US NAVY NAVFAC WASHINGTON / US NAVY NAVFAC WASHINGTON; RPS INC
SB1600239 / CONSTRUCTION
ADVANCEMENT OF UP TO 22 SOIL BORINGS AND 4 MONITORING WELLS TO SUPPORT INVESTIGATION OF FORMER PETROLEUM UNDERGROUND STORAGE TANKS AT BUILDING 71 AND SITE 111 / 225 AT WASHINGTON NAVY YARD. SOIL BORINGS WILL BE ADVANCED TO A MAXIMUM OF 15 FT BELOW GROUND SURFACE. WELLS WILL BE INSTALLED TO A MAXIMUM DEPTH OF 13 FT BELOW GROUND SURFACE. SOIL BORINGS WILL BE BACKFILLED UPON COMPLETION. WORK PLAN HAS...
329 VIRGINIA AVE SE   
08/01/16 
CLAIRE C SCHAEFER / JOHN C. MYERS
P1608301 / SUPPLEMENTAL
385 WATER ST SE   
08/12/16 
FC 385 WATER LLC / STEPHEN J. EXELBERT
P1608654 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Capitol ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2016 JD.