I almost can't bring myself to write the words, but the owners of the Florida Rock site just south of Nationals Park have filed with the Zoning Commission for not only the previously reported plan to change the planned first phase office building to a residential one, but also to revisit parts of the site plan for the three subsequent phases. (For those of you versed in zoning speak, they are requesting to "revert Phases II, III, and IV to First Stage Approvals with modifications.")
This is going to be a lengthy process, with hearings at the Zoning Commission, reports from the Office of Planning and others, and presentations to the ANC (starting with one this coming Monday night, Dec. 12). So I'm going to avoid getting into the weeds too much too early, and will just give some bullet points of what changes they are looking for. (You're free to read these 57 pages of the filing for more detail.)
* The new Phase 1 building, at the far east end of the site (next to Diamond Teague Park) will now be the aforementioned residential building, a nine-story U-shaped design oriented toward the river with 300-350 units and 286 below-grade parking spaces. There will still be 12,500 square feet of retail, though they are asking that 7,000 of it be "flex space" that "may alternatively be dedicated to residential amenity space" until retail gets going. There will be a private courtyard within the "U", but there will also be the open space on the buildings' east side, now dubbed Anacostia Plaza, that will be open enough to maintain open views from First Street and the stadium's Grand Staircase to the river but will also provide "passive recreation space."
* The esplanade that has always been such a big part of the site plan remains, acting as the portion of the Anacostia Riverwalk Trail connecting South Capitol Street to Teague Park, the new pedestrian bridge, and the Yards Park. The Esplanade will "relate" to the "design vernacular" of the newly constructed boardwalks, and will also have a lot of stormwater management and bio-filtration offerings.
* On the building's west side will be the "Mews," which they call a pedestrian boulevard separating the Phase 1 building from the planned Phase 2 residential building. This path will also provide access to parking and loading for the first two phases, but "a dynamic paving design . . . will help distinguish this area as an urban space that privileges pedestrians over vehicles."
* The filing says they anticipate construction to begin in the second quarter of 2013, with first move-ins in early 2015 and the entire phase completed by summer 2015.
As for overall changes, here's what seem to be the most interesting changes from the previously approved design that the developers are looking for:
* The new plan would bring 1,164,640 square feet of gross floor area (4.6 FAR), up from 1,115,400 sq ft/4.4 FAR in the last plan. The other three phases' uses would remain unchanged (residential, office, hotel).
* Building heights of 130 feet for Phase 2-4 are being requested, compared to 130/112/130 last time around.
* Below-grade parking spaces would go from 1,010 to 1,144.
Plus, though It's hard to tell from one small site plan concept drawing, a lot of the public space design, especially to the east of the Phase 3 and 4 buildings, looks scaled back from the 2008 design. (UPDATE: Here's a graphic put together from another part of the filing that compares the 2008 site plan with the current one.)
The filing also says that "the Applicant would like the flexibility to provide interim uses on Phases, II, III, IV so that the site will not simply lay dormant pending construction," and lists a park, a farmers market, or other "simple, temporary retail uses" as examples.
And, just as in the previous plans, development of phases 3 and 4 are completely dependent on the construction of a new South Capitol Street Bridge, since the current bridge bisects the property where those buildings are planned.
Again, this is early in this new process, and there will be plenty of filings and presentations to come for all the additional detail you're going to be clamoring for. For now, the takeaway is that FRP/MRP want to get started on a residential building at 1st and Potomac in the spring of 2013, and still want to move forward on the rest of the site with a design similar to what was approved 3 1/2 years ago, but with some modifications.
This project first began its zoning quest in 1998, and went through a four-year process ending in 2008 to get its second-stage approvals. I should also note that Davis Buckley Architects, who worked on the project throughout that 10-year ordeal, is no longer part of the design team; SK&I is now on board, with Oculus as the landscape design firm. The site's owners, FRP Development/Florida Rock Properties, announced their partnership with MRP Realty earlier this year.
(As for the concrete plant currently on site, I haven't looked lately, but demolition is underway, and the filing says it should be done by the end of the year. Tom Boswell's heart will be broken.)
UPDATE, 1/3: Just before Christmas, demolition was finished on the plant, making it #166 in my Demolished Buildings Gallery.
Comments (3)
   
 
 More About Florida Rock
 All posts: Florida Rock, zoning

JDLand.com Home

Comments

lester says: (12/9/11 3:15 PM)
130 feet tall? That's curious.

The area is zoned W-2, which would traditionally allow for up to 60 feet. It's part of the capital gateway overlay, which is designed "to reduce the height and bulk of buildings along the Anacostia riverfront."

Then DC goes ahead and approved (previously) 130/112/130 foot tall buildings (Phase II, III, and IV, not sure what Phase I will be). Wow. The wonders of the PUD (which basically nullifies the W-2 and CG designation).

However, moving past these decisions, how on earth do they justify 130 feet with respect to the Heights of Building Act of 1910? To allow a 130 foot tall building, you would need to have either South Capitol or Potomac be 110' wide, and as best as I can estimate from the DC property records web site, they are at most 90' wide. What gives?

Either way, it seems silly to develop an overlay to reduce height and bulk near the Anacostia riverfront, and then approve four buildings on the waterfront 100+ feet high...

Mind you, from where I live, the buildings won't really impact my view at all, I just find it all very... strange.


JD says: (12/9/11 3:22 PM)
Phase I was originally approved at 92 feet; they're requesting 95 feet this time.

There's a fair amount of discussion of the zoning starting around page 11 in the document I link to above, which says that CG/W-2 (the Capitol Gateway overlay) allows for max heights of 130 ft in mixed-use developments. (Purely commercial buildings can only be 60 feet high; the CG overlay gives the opportunity for increased density by developing mixed-use.)

Here's the Capitol Gateway Overlay, if you want to read: link




IMGoph says: (12/17/11 12:17 AM)
I like the fact that the building footprints aren't curvy like the Watergate anymore. That footprint just felt contrived.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2016!
 Top News

Chaifetz10 on Columnist Walks the: @202 I walked on the bridge today from Dock79 down to Harris Teeter and I didn't...
Ampersand on Two-Year Change in: Last Thursday I biked north on 5th/6th from Navy Yard to Capitol Hill. The south...
202_cyclist on Wednesday Tidbits: Regarding my post above, Cultivate the City is operating this garden. We all mi...

  
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
16 B/O M ST SE   ROBBERY  09/23/16
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/23/16
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/19/16
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/18/16
1200 B/O 1ST ST SE   ASSAULT WITH A DANGEROUS WEAPON  09/17/16
400 B/O M ST SE   THEFT
Shoplifting
 09/16/16
1100 B/O 5TH ST SE   THEFT
Theft First Degree (all Other Larceny)
 09/06/16
700 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 09/06/16
1200 B/O 1ST ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/04/16
UNIT B/O I ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 09/04/16
1400 B/O SOUTH CAPITOL ST   THEFT
Theft 2nd Degree (all Other Larceny)
 08/28/16

Recent Issued Building Permits Archive  
1233 1ST ST SE   
09/16/16 
NA BALLPARK HOTEL LLC / NORTHEAST ELECTRIC; NA BALLPARK HOTEL LLC; HOSSEIN ECONO SIGN INC.
SG1600390 / CONSTRUCTION
To Install four signs: -3 - Channel letters on Raceways -1- Blade Sign
1331 2ND ST SE   
09/19/16 
DC WATER / DC WATER; CORMAN CONSTRUCTION
AH1601056 / CONSTRUCTION
After hour work for structure excavation and support for building permit B1311474 DC Water, Corman Construction 202-863-0052
933 5TH ST SE   
09/12/16 
null / NA NA NA
EHOP16924112 / HOME OCCUPATION
1015 HALF ST SE   
09/14/16 
HALF STREET SE LLC HALF STREET SE LLC / DARIN PASQUALLE; HALF STREET SE LLC HALF STREET SE LLC; DARIN PASQUALLE
E24765056 / SUPPLEMENTAL
   
09/21/16 
HALF STREET SE LLC / 1015 HALF SE LLC; JOHN GIUSEPPE-RAMCO
B1610675 / CONSTRUCTION
Construction of elevator lobby and common corridors on the 7th floor as shown on the electronically submitted mechanical, electrical, fire protection, and arch. dwgs. Interior work only. No structural work involved. approx. 2275 sf.
1210 HALF ST SE   
09/07/16 
HINES GLOBAL REIT 55 M STREET LLC / MATT LOSIGNOR
P1609218 / SUPPLEMENTAL
75 I ST SE   
09/07/16 
99 I ST SE LP / 99 I ST SE LP; ECS MID-ATLANTIC, LLC C/O REBECCA RUSCHMAN
SB1600354 / CONSTRUCTION
We will perform 2 soil borings and 2 CPT cone soundings on the site. The 2 soil borings and 2 CPT soundings will be extended to depths on the order of 90 ft below the existing site grades. The borings and soundings will be perfroemd within the bounds of private property and will be drilled utilizing a 3.25-inch hollow stem, continuous flight augers and generate a 6-inch annulus. After the borings...
82 I ST SE   
09/09/16 
GDVC EYE STREET LLC / MITCH A. PERMUY
E1609957 / SUPPLEMENTAL
88 K ST SE   
09/07/16 
99 I ST SE LP 99 I ST SE LP / 99 I ST SE LP 99 I ST SE LP; ECS MID-ATLANTIC, LLC C/O REBECCA RUSCHMAN
SB1600355 / CONSTRUCTION
We will perform 2 CPT cone soundings on the project site within the bounds of private space. The CPT cones will be extende to a depth of 90 feet below the existing ground surface, utilizing a 4-inch diameter cone and generate a 4-inch annulus. After the soundings are completed they will be backfilled with bentonite slurry which has a consistency of two pounds bentonite powder to one gallon water.
80 M ST SE 400   
09/15/16 
WELLS REIT II 80 M STREET LLC / null
P1609454 / SUPPLEMENTAL
50 M ST SE   
09/15/16 
KCG 50 M LLC / KCG 50 M LLC ENGLEWOOD LLC; TRACIE CLAXTON; CLAXTON
SG1600460 / CONSTRUCTION
2 Wall mounted Signs - Reversed Channel Letter 2 small wall mounted plague
80 M ST SE   
09/09/16 
WELLS REIT II 80 M STREET LLC / PHILIP G DONNELLY
E1609959 / SUPPLEMENTAL
99 M ST SE   
09/16/16 
BALLPARK SQUARE 701, LLC SKANSKA COMMERCIAL DEVELOPMENT / BALLPARK SQUARE 701, LLC SKANSKA COMMERCIAL DEVEL
AH1601047 / CONSTRUCTION
Place concrete mat foundation slab. Before work hours - 3AM to 7AM on 9 / 19 / 2016 and 9 / 20 / 2016, if weather or jobsite delays prevail. Permit will only be needed / used for 1 of the 2 days. (Per ANC agreement "before hours work on ONE of the following days: either September 17, 19, or 20," & "to begin no earlier than 3:00 am" )
   
09/16/16 
BALLPARK SQUARE 701, LLC SKANSKA COMMERCIAL DEVELOPMENT / BALLPARK SQUARE 701, LLC SKANSKA COMMERCIAL DEVEL
AH1601048 / CONSTRUCTION
Place concrete at 99 M Street SE for mat foundation slab. Saturday 9 / 17 / 2016 concrete placement from 3AM to 7PM. (Per ANC agreement "before hours work on ONE of the following days: either September 17, 19, or 20," & "to begin no earlier than 3:00 am" )
100 M ST SE 4   
09/09/16 
SQUARE 743 INC / null
P1609322 / SUPPLEMENTAL
100 M ST SE   
09/20/16 
QUARE 743 INC / QUARE 743 INC; QUARE 743 INC; PHILIP HAUHN
E14003252 / SUPPLEMENTAL
202 M ST SE   
09/09/16 
UNITED STATES OF AMERICA / EBONY BROWN DC HUMANITIES AND ARTS COMMISSION
TN1600199 / CONSTRUCTION
SPECIAL EVENT 202 ARTS & MUSIC FESTIVAL 1 SL 250 24 X 32 STAGE
1100 NEW JERSEY AVE SE 845   
09/21/16 
SQUARE 742 LLC SPAULDING & SLYE C/O WC SMITH / SQUARE 742 LLC SPAULDING & SLYE C/O WC SMITH; WILLIAM SNODDY
B1612012 / CONSTRUCTION
Interior Renovation on the 8th Floor on behalf of Maxim Health 5,138 sqft
1100 NEW JERSEY AVE SE   
09/14/16 
SPAULDING AND SLYE SPAULDING AND SLYE / HALEY HUGGINS; SPAULDING AND SLYE SPAULDING AND SLYE; JOHNNY RILING
E39166644 / SUPPLEMENTAL
125 O ST SE   
09/19/16 
DISTRICT OF COLUMBIA / DC WATER HQ; DAVID FONTANA MSC
EX1600110 / CONSTRUCTION
Site grading and demo per erosion control plan only for future new DC Water HQ building under seperate permit.
1244 SOUTH CAPITOL ST SE   
09/19/16 
1244 SOUTH CAPITOL RESIDENTIAL LLC / RONALD C. CAYTON
E1610018 / SUPPLEMENTAL
385 WATER ST SE   
09/15/16 
FC 385 WATER LLC / EDUARDO L. LOPEZ
E1610139 / SUPPLEMENTAL
355 WATER ST SE   
09/14/16 
OLIVIA DARROW RAGNAR EVENTS LLC
TN1600198 / CONSTRUCTION
SPECIAL EVENT RAGNAR RELMAY WASHINGTON DC 2 20 X 20 TENTS 25 10 X 10 TENTS 1 30 X 40 TENT FENCING FOR BEER GARDEN
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Capitol ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2016 JD.