Since January, 2003
            
 Sliding from Before to After

Yes, it's time for another batch of updated construction photos. This is a tough stretch of year to take these--the sun never gets very high in the sky, so anything facing due south is about impossible to get without glare. And, for places like Canal Park, it's hard to even get some locations out of the shadows long enough to get a photo that you can decipher. But you can see (below left, and on the project page) a couple of shots of the progress on the park's pavilion where the Park Tavern restaurant will be housed, along with plenty of shots vaguely showing the other ongoing ground-level work. Meanwhile, at Capitol Quarter (below right), they continue to just zip right along, with framing now well underway on the north side of L and around up 4th, and prep work for foundations continuing in the project's final block, on the south side of L.
In the Renovation/Rehabilitation portion of the tour, we have a few updated images of the Boilermaker Shops (above left), another building that's tough to shoot in winter, even more so when there's not much of it other than steel beams at the moment (though they have recently been painted white). Meanwhile, 225 Virginia/200 I is coming pretty close to the end of its exterior renovations, though work inside will continue in preparation for the arrival of three DC agencies later this year.
There isn't much new to see of Lot 38 Espresso (aka the Little Red Building 2.0, above left), which the grapevine says is now shooting for a mid-December opening. (But, really, at this point, it opens when it opens--the last batch of permits and approvals is always slow going, and I bet the owner wants it open even more than you do.) I also took a bunch of shots of the former National Geospatial Intelligence Agency building at 1st and M (above right), not because there's been any changes to it, but because I really enjoyed finally being able to aim a camera at it without having guards reaching for their guns. (Nyaah! Nyaah! Click! Click! Click!)
I came home with 438 new photos (yikes), and you can browse the 180-plus I decided to upload to the online archive here. (Yes, it's true, you don't actually get to see every photo I've ever taken. Which is probably for the best.)
Remember to click the icon to see the entire range of photos for any location, while the project pages linked to above are your best bet if you're looking for paired before-and-afters and/or narrated tours.
And, in case you didn't see my tweet or my late-night update, the residential/Teeter project at 4th and M got all the dotted i's and crossed t's I mentioned in my initial post, and is officially now considered by Forest Ctiy as "commenced." (I just can't call it 1212 4th Street yet. Doesn't really make the location pop as well as "4th and M.")
Comments (0)
   
 
 More About 225 Virginia/Old Post Plant/200 I

JDLand.com Home

Comments

No comments posted.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2016!
 Top News

JD on Two-Year Change in: I'm not sure that in the FEIS they said it wouldn't be closed at all--there had ...
walt on Two-Year Change in: CSX and city officials promised in the Final environment impact study (FEI)? tha...
Ampersand on Two-Year Change in: I think this will be weird, but probably fine; there's plenty of width for two-w...

Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1200 B/O 4TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/17/16
1000 B/O HALF ST SE   THEFT
Theft First Degree (all Other Larceny)
 08/16/16
700 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/15/16
1400 B/O SOUTH CAPITOL ST   THEFT
Theft 2nd Degree (all Other Larceny)
 08/14/16
16 B/O M ST SE   ROBBERY  08/12/16
1000 B/O 5TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/09/16
1200 B/O 1ST ST SE   THEFT
Theft First Degree (shoplifting)
 08/08/16
50 B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 08/02/16
600 B/O I ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/02/16
700 B/O L ST SE   ROBBERY  08/01/16
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/29/16
700 B/O L ST SE   ROBBERY  07/28/16
1100 B/O K ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 07/25/16
1200 B/O HALF ST SE   BURGLARY
Burglary Two
 07/24/16
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/23/16
900 B/O 5TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/23/16
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/22/16
1100 B/O NEW JERSEY AVE SE   THEFT
Shoplifting
 07/20/16
900 B/O 4TH ST SE   ROBBERY  07/20/16
500 B/O L ST SE   THEFT
Theft First Degree (all Other Larceny)
 07/19/16
1400 B/O SOUTH CAPITOL ST   THEFT
Theft 2nd Degree (theft From Building)
 07/19/16

Recent Issued Building Permits Archive  
1004 1ST ST SE   
08/04/16 
SQ. 740 LLC / N/A SQ 740 LLC JOHN AKRIDGE DEVELOP COMPANY; ECC, INC.
SB1600325 / CONSTRUCTION
Due diligence investigation. Installation of six 3-inch diameter direct-push geoprobe soil borings to depths of approximately 30 below grade. Soil borings will be abandoned on the same day as drilling by tremi-grouting using a bentonite slurry composed of 2 pounds of bentonite powder to 1 gallon of water. IDW will be properly managed.
1212 4TH ST SE 120   
08/04/16 
FC 1212 LLC / CLARK S FULLER
M1603023 / SUPPLEMENTAL
1150 5TH ST SE 20002   
08/11/16 
ALAN J PHELPS / DOUGLAS FOSTER
B1509540 / CONSTRUCTION
1. Renovation of existing first and second floor of the academic wing of the Van Ness building. 2. Square footage is approximately 26,000 SF ,For phase 1 3. Cost of construction is 11.5M 4. Scope of work details a. Convert existing space in to 6 new classroom space. These classrooms will be two PreK -3, two prek-4, and two Kindergarten classes. Also for phase 1,...
1150 5TH ST SE   
08/12/16 
DISTRICT OF COLUMBIA / JOHN HOMICK
E1609156 / SUPPLEMENTAL
   
08/12/16 
DISTRICT OF COLUMBIA / MATT LOSIGNOR
P1608656 / SUPPLEMENTAL
   
08/12/16 
DISTRICT OF COLUMBIA / ORLANDO M CATANA
E1609149 / SUPPLEMENTAL
1220 HALF ST SE   
08/05/16 
NA BUFFALO WILD WINGS / NA BUFFALO WILD WINGS; BELA X-PEDITERS PLUS, INC.
AH1600921 / CONSTRUCTION
Work after hours 7pm - 7am
82 I ST SE   
08/15/16 
GDCV EYE STREET LLC / GDCV EYE STREET LLC; KIM MITCHELL CDKM CONSULTING LLC
B1611941 / CONSTRUCTION
FIRST EXTENSION TO PERMIT B1507990 TO EXPIRE ON 3 / 17 / 17
   
08/15/16 
CSX TRANSPORTATION INC / BEDCO MOBILITY INC.
EN1602806 / SHOP DRAWING
Type of Elevator : One (1) vertical wheel-chair lift / steel / garage level 2 / handicap lift (13th floor)
150 I ST SE   
08/05/16 
MAXIM CRANE WORKS MAXIM CRANE WORKS
AH1600933 / CONSTRUCTION
after hours to place mobile crane to take down tower crane with mobile crane and stage trucks from 7am 8 / 8 / 2016 to 1159p-m 8 / 9 / 2016
125 L ST SE   
08/11/16 
CRANE SERVICE CO / CRANE SERVICE CO; CHRISTINE LONG
AH1600945 / CONSTRUCTION
An after hours permit is respectfully requested from 4AM Saturday thru 9PM Sunday
80 M ST SE 1   
08/10/16 
WELLS REIT II 80 M STREET LLC / THOMAS B. STEG
P1608566 / SUPPLEMENTAL
80 M ST SE 2   
08/10/16 
WELLS REIT II 80 M STREET LLC / THOMAS B. STEG
P1608568 / SUPPLEMENTAL
80 M ST SE 3   
08/10/16 
WELLS REIT II 80 M STREET LLC / THOMAS B. STEG
P1608569 / SUPPLEMENTAL
100 M ST SE 7   
08/04/16 
SQUARE 743 INC / ANTHONY G SAMBURG
E1608667 / SUPPLEMENTAL
100 M ST SE PT OF 4TH   
08/11/16 
QUARE 743 INC . / QUARE 743 INC .; JOHN GIUSEPPE-RAMCO
B1611810 / CONSTRUCTION
renovation to parts of an existing 4th floor office space, tech marine business as shown on the attached mech., plumb., elect., fire protection, demolition, and arch. dwgs. interior work only. no change in use. no struct. work. 800 sf.
300 M ST SE   
08/05/16 
FEDERAL CENTER LP / null
F1600517 / CONSTRUCTION
   
08/06/16 
FGSF TEST
PC92978992 / POST CARD
Installation of 1 temporary construction trailer on private property.
   
08/06/16 
SDS SDSDS / LAVANYA SIKHINAM; SDS SDSDS; ENRIQUE LYON
E90011839 / SUPPLEMENTAL
   
08/07/16 
XVB XVBX / FSGVSF SFGS; XVB XVBX; DAVID FARMER
E77515115 / SUPPLEMENTAL
909 NEW JERSEY AVE SE 1311   
08/11/16 
null / NA NA NA
EHOP1690902 / HOME OCCUPATION
861 NEW JERSEY AVE SE   
08/09/16 
NA CSX TRANSPORTATION, INC.
AH1600944 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities.
1000 NEW JERSEY AVE SE   
08/02/16 
null / ALLISON HINES
PC66310814 / POST CARD
Replacement of not more than 1 gas appliance, on a residential, commercial or industrial project.
1017 NEW JERSEY AVE SE   
08/04/16 
1021 NEW JERSEY AVE LLC / N/A 1021 NEW JERSEY AVE LLC POTOMAC DEVELOPMENT; ECC, INC.
SB1600326 / CONSTRUCTION
Due diligence investigation. Installation of one 3-inch diameter direct-push geoprobe soil borings to depths of approximately 30 feet below grade. Soil borings will be abandoned on the same day as drilling by tremi-grouting using a bentonite slurry composed of 2 pounds of bentonite powder to 1 gallon of water. IDW will be properly managed.
1029 NEW JERSEY AVE SE   
08/04/16 
MESERET DEGEFU / HAILU TEKLEBERHAN; ECC, INC.
SB1600327 / CONSTRUCTION
Due diligence investigation. Installation of two 3-inch diameter direct-push geoprobe soil borings to depths of approximately 30 feet below grade. Soil borings will be abandoned on the same day as drilling by tremi-grouting using a bentonite slurry composed of 2 pounds of bentonite powder to 1 gallon of water. IDW will be properly managed.
1111 NEW JERSEY AVE SE   
08/11/16 
null / THOMAS P MCGUIRE
E1609117 / SUPPLEMENTAL
125 O ST SE   
08/04/16 
JOHN LECKER, FOREST CITY WASHINGTON, INC / JOHN LECKER, FOREST CITY WASHINGTON, INC; RACHEL DOERY, PSI
SB1600337 / CONSTRUCTION
Site is located south of N Pl SE, 500ft east of intersect with First St, SE in Washington, DC. Drilling soil borings at site for future development of a 4-story concrete parking garage with 331 parking spaces at street level. A 2-story theater will be constructed above the parking garage totaling approximately 95,000 sf.
25 POTOMAC AVE SE   
08/03/16 
RIVERFRONT INVESTMENT PARTNERS / RIVERFRONT INVESTMENT PARTNERS; JASON BENTLEY
B1610683 / CONSTRUCTION
Revision to Issued Permit Number B1408697.
741 SICARD ST SE 20374   
07/29/16 
US NAVY NAVFAC WASHINGTON / US NAVY NAVFAC WASHINGTON; RPS INC
SB1600239 / CONSTRUCTION
ADVANCEMENT OF UP TO 22 SOIL BORINGS AND 4 MONITORING WELLS TO SUPPORT INVESTIGATION OF FORMER PETROLEUM UNDERGROUND STORAGE TANKS AT BUILDING 71 AND SITE 111 / 225 AT WASHINGTON NAVY YARD. SOIL BORINGS WILL BE ADVANCED TO A MAXIMUM OF 15 FT BELOW GROUND SURFACE. WELLS WILL BE INSTALLED TO A MAXIMUM DEPTH OF 13 FT BELOW GROUND SURFACE. SOIL BORINGS WILL BE BACKFILLED UPON COMPLETION. WORK PLAN HAS...
329 VIRGINIA AVE SE   
08/01/16 
CLAIRE C SCHAEFER / JOHN C. MYERS
P1608301 / SUPPLEMENTAL
385 WATER ST SE   
08/12/16 
FC 385 WATER LLC / STEPHEN J. EXELBERT
P1608654 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Capitol ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2016 JD.