In a conference room at Nationals Park on Wednesday night, a bevy of representatives from CSX, DDOT, and FHWA along with consultants galore showed the public for the first time a series of 12 "project concepts" for how to handle CSX's desire/need to expand the capacity of the 3,800-foot-long Virginia Avenue Tunnel that runs from 2nd to 12th Street SE.
The concepts are now posted on the project web site, and can be grouped as seven "rebuild" options along with four other "reroute" options that would bring about the abandonment of the tunnel altogether (and, it must be said, are probably a just smidge less likely to be one of the alternatives chosen).
Three of the rebuild options are along the lines of what's been discussed for more than two years now, which would be the running of a temporary track in an open trench while the expansion work is done on the existing tunnel. While having the trench on the south side of the tracks (Concept 2) has been the "default" discussion and has to be assumed to be CSX's preferred choice, Concept 3 shows the possibility of running the trench on the north side of the tunnel, which would be right next to the Southeast Freeway (and which I'm imagining would run into some issues with having to make sure all freeway supports are adequately protected). Concept 4 runs a "serpentine" trench both north and south of the existing tracks.
Concept 5 is an intriguing new notion, where a second permanent tunnel would be built parallel and south of the existing one. There's also the idea of just widening the current tunnel either while trains continue to use the tunnel (Concept 6) or with freight traffic temporarily rerouted either to Union Station (Concept 7A) or outside the District entirely (with a route shown that would take trains from Richmond through Ohio and up to Buffalo before turning back to the East Coast).
The "reroute" options all propose abandoning the tunnel, either building a nine-mile-long freight tunnel from National Airport to the Deanwood Metro station about 80 feet underground (Concept 8) or building other alignments proposed in recent years by the National Capital Planning Commission (Concepts 9 and 10), or running on CSX's existing tracks out to Ohio and then northward.
But of course, these are concepts, and one of the reasons for going through a NEPA process is to study the different ideas to then come up with alternatives, accompanied by scads of data on noise, vibration, pollution, traffic, and timeline impacts. And to determine how much the various alternatives would cost--because it's likely that CSX is not going to be too gung-ho on the options anticipated to run into the billions of dollars.
It's expected that the public meeting where the alternatives will be unveiled will be in February of 2012, at which point so many of the questions that residents have been asking for so long about how the tunnel construction will affect the day-to-day lives of people who live near and use Virginia Avenue will get some concrete answers.
Faisal Hameed of DDOT, who ran much of the meeting, emphasized a number of times during the Q&A that this is a unique project: a private company is doing work they are paying for themselves on a right of way that they own some (but not all) of, but the impacts on vehicle/pedestrian/bicycle transportation are expected to be extensive enough that DDOT requested this environmental assessment before getting to the point of signing off on any permits that CSX will need to do the work. (There is also apparently still some negotiating going on between CSX and DDOT about exactly whose right of way is where, but it was said that no portion of the project will enter private land, though some small incursions will happen on the Marine bachelor enlisted quarters' site west of 7th Street.)
The Q&A was a pretty peaceful one as these things go (which makes a cranky blogger so very happy!). Most of the wrangling between audience members and CSX was over the route that hazardous materials take when they are forced to go around the District because of various city laws and federal regulations; the audience members were trying to get CSX to admit that there's an existing route bypassing the city that's shorter than anything shown in the concepts, while CSX wasn't going to get anywhere near telling people where hazardous materials travel.
In response to one audience question (coming as a result of the new FAQ posted on the project web site), CSX did say that they are going to "strongly pursue" getting a waiver to stop the currently required blowing of horns anytime a train enters the tunnel, and that they think it should be a "strong possibility" that it can happen, though of course they weren't wanting to commit.
There were also questions that will be better asked when the alternatives are unveiled, about construction staging, safety during construction, noise and vibration impacts, traffic flow, emergency planning, alley access, and what CSX will do to restore or even improve the Virginia Avenue streetscape when construction is finished. (As for any historic preservation impacts, a Section 106 review of the project is being done concurrently with this NEPA assessment.)
Comments are being accepted on these 12 concepts for the next 30 days, either by using the web site or e-mailing contact@virginiaavenuetunnel.com. (About 530 comments were received after the September scoping meeting.) It's hoped the environmental assessment will be completed with a final NEPA decision by the summer of 2012; though, if there is a finding that there will be a "significant environmental impact" from whichever construction alternative is chosen, then a full Environmental Impact Study (EIS) would then have to be done.
Comments (4)
   
 
 More About CSX/Virginia Ave. Tunnel

JDLand.com Home

Comments

Bruce says: (12/1/11 6:28 PM)
I'm glad they showed us some concepts..it will be a long process.


F says: (12/2/11 9:39 AM)
I wonder how many of those are "serious" concepts. It seems as though CSX is presenting some so-called alternate concepts to make it look like they're considering options when they've already decided on Concept 2 or something close to it.


MJM says: (12/3/11 3:43 PM)
If Concept 5 is a dig, build, cover, repeat as you go instead of one open long trench that may be the best option of them all. Can anyone confirm that is how Concept 5 would be constructed?


Douglas Willinger says: (12/4/11 3:30 AM)
Concept 5 also preserves a wider space making it easier to construct a below ground cut and cover tunnel for replacing the elevated SE Freeway- and would even be better if the new northern tunnel was shifted closer to the new southern tunnel.

link

link

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

jdc on Making it Official: Maybe someday it'll stop being a habit, but I still find myself coming to JDland...
MJM on Making it Official: Oh wow, was wondering if you were coming back. Its been a great run and to see ...
MalS on Making it Official: Very best wishes and thank you JD! What an incredible resource for those of us w...
goldfish on Making it Official: Thanks JD for the thousands of posts on the goings-on in {insert preferred neigh...
JD on Making it Official: This is the part I'm going to miss most of all, the commenting. With one or two ...
Jaybird on Making it Official: JD, I remember meeting you down by the construction site for the ballpark in 20...
Get JDLand Updates In Your Inbox!


Thousands and thousands of photos showing the neighborhood changing. More than 150 buildings no longer with us. All the news, since 2003. Photos from various archives showing the neighborhood in the more distant past. Maps from the early 1900s. Overhead Photo Comparisons: 1949, 1988, 2002-2008. All Blog Entries, 2003 - Present Major Events, 1799 - Present A series of blog entries looking at the neighborhood's history.
Near Southeast's Rearview Mirror


City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
No records added or modified in the past two weeks.

Recent Issued Building Permits Archive  
1300 4TH ST SE 1001   
02/22/21 
AP BOWER RETAIL LLC / null
E2104231 / SUPPLEMENTAL
1346 4TH ST SE APT 1M   
02/06/21 
null / NA NA NA
EHOP21945129 / HOME OCCUPATION
1331 4TH ST SE R-2   
02/08/21 
FC 1331 LLC / FC 1331 LLC
BP2101814 / POST CARD
10 I ST SE   
02/16/21 
CAPITOL HILL RACQUET CLUB / NA; VICTORIA STEINHOFF
SB2100112 / CONSTRUCTION
Installation of up to six (6) 3-inch diameter direct-push Geoprobe borings to depths of up to 30 feet below grade as part of an environmental assessment.
555 L ST SE   
01/29/21 
UNITED STATES OF AMERICA / RENNE WELL; RICK HARLAN SCHNEIDER
B2102004 / CONSTRUCTION
DGS PROJECT REHABILITATION+RESTORATION OF THE HISTORIC LINCOIN FIELDHOUSE
861 NEW JERSEY AVE SE 20003   
02/23/21 
809-853 NEW JERSEY AVE ACQUISITION LLC / SUSANA VAZQUEZ
AH2100728 / CONSTRUCTION
Dismantling of tower crane.
809 NEW JERSEY AVE SE   
02/11/21 
GREYSTAR GP LLC 809-853 NEW JERSEY AVENUE ACQUISITION LLC / null
E2103926 / SUPPLEMENTAL
853 NEW JERSEY AVE SE   
02/11/21 
GREYSTAR GP LLC / null
E2103924 / SUPPLEMENTAL
861 NEW JERSEY AVE SE   
02/05/21 
GS CSX HOTEL OWNER LLC / null
E2103762 / SUPPLEMENTAL
1275 NEW JERSEY AVE SE   
02/02/21 
FC 1275 NJ LLC / null
E2103662 / SUPPLEMENTAL
   
02/11/21 
FC 1275 NJ LLC / null
P2103445 / SUPPLEMENTAL
848 SOUTH CAPITOL ST SE   
02/16/21 
CXS TRANSPORTATION INC / VICTORIA STEINHOFF; TBD
SB2100111 / CONSTRUCTION
Installation of up to six (6) 3-inch diameter direct-push Geoprobe borings to depths of up to 30 feet below grade as part of an environmental assessment.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2022 JD.