In a conference room at Nationals Park on Wednesday night, a bevy of representatives from CSX, DDOT, and FHWA along with consultants galore showed the public for the first time a series of 12 "project concepts" for how to handle CSX's desire/need to expand the capacity of the 3,800-foot-long Virginia Avenue Tunnel that runs from 2nd to 12th Street SE.
The concepts are now posted on the project web site, and can be grouped as seven "rebuild" options along with four other "reroute" options that would bring about the abandonment of the tunnel altogether (and, it must be said, are probably a just smidge less likely to be one of the alternatives chosen).
Three of the rebuild options are along the lines of what's been discussed for more than two years now, which would be the running of a temporary track in an open trench while the expansion work is done on the existing tunnel. While having the trench on the south side of the tracks (Concept 2) has been the "default" discussion and has to be assumed to be CSX's preferred choice, Concept 3 shows the possibility of running the trench on the north side of the tunnel, which would be right next to the Southeast Freeway (and which I'm imagining would run into some issues with having to make sure all freeway supports are adequately protected). Concept 4 runs a "serpentine" trench both north and south of the existing tracks.
Concept 5 is an intriguing new notion, where a second permanent tunnel would be built parallel and south of the existing one. There's also the idea of just widening the current tunnel either while trains continue to use the tunnel (Concept 6) or with freight traffic temporarily rerouted either to Union Station (Concept 7A) or outside the District entirely (with a route shown that would take trains from Richmond through Ohio and up to Buffalo before turning back to the East Coast).
The "reroute" options all propose abandoning the tunnel, either building a nine-mile-long freight tunnel from National Airport to the Deanwood Metro station about 80 feet underground (Concept 8) or building other alignments proposed in recent years by the National Capital Planning Commission (Concepts 9 and 10), or running on CSX's existing tracks out to Ohio and then northward.
But of course, these are concepts, and one of the reasons for going through a NEPA process is to study the different ideas to then come up with alternatives, accompanied by scads of data on noise, vibration, pollution, traffic, and timeline impacts. And to determine how much the various alternatives would cost--because it's likely that CSX is not going to be too gung-ho on the options anticipated to run into the billions of dollars.
It's expected that the public meeting where the alternatives will be unveiled will be in February of 2012, at which point so many of the questions that residents have been asking for so long about how the tunnel construction will affect the day-to-day lives of people who live near and use Virginia Avenue will get some concrete answers.
Faisal Hameed of DDOT, who ran much of the meeting, emphasized a number of times during the Q&A that this is a unique project: a private company is doing work they are paying for themselves on a right of way that they own some (but not all) of, but the impacts on vehicle/pedestrian/bicycle transportation are expected to be extensive enough that DDOT requested this environmental assessment before getting to the point of signing off on any permits that CSX will need to do the work. (There is also apparently still some negotiating going on between CSX and DDOT about exactly whose right of way is where, but it was said that no portion of the project will enter private land, though some small incursions will happen on the Marine bachelor enlisted quarters' site west of 7th Street.)
The Q&A was a pretty peaceful one as these things go (which makes a cranky blogger so very happy!). Most of the wrangling between audience members and CSX was over the route that hazardous materials take when they are forced to go around the District because of various city laws and federal regulations; the audience members were trying to get CSX to admit that there's an existing route bypassing the city that's shorter than anything shown in the concepts, while CSX wasn't going to get anywhere near telling people where hazardous materials travel.
In response to one audience question (coming as a result of the new FAQ posted on the project web site), CSX did say that they are going to "strongly pursue" getting a waiver to stop the currently required blowing of horns anytime a train enters the tunnel, and that they think it should be a "strong possibility" that it can happen, though of course they weren't wanting to commit.
There were also questions that will be better asked when the alternatives are unveiled, about construction staging, safety during construction, noise and vibration impacts, traffic flow, emergency planning, alley access, and what CSX will do to restore or even improve the Virginia Avenue streetscape when construction is finished. (As for any historic preservation impacts, a Section 106 review of the project is being done concurrently with this NEPA assessment.)
Comments are being accepted on these 12 concepts for the next 30 days, either by using the web site or e-mailing contact@virginiaavenuetunnel.com. (About 530 comments were received after the September scoping meeting.) It's hoped the environmental assessment will be completed with a final NEPA decision by the summer of 2012; though, if there is a finding that there will be a "significant environmental impact" from whichever construction alternative is chosen, then a full Environmental Impact Study (EIS) would then have to be done.
Comments (4)
   
 
 More About CSX/Virginia Ave. Tunnel

JDLand.com Home

Comments

Bruce says: (12/1/11 6:28 PM)
I'm glad they showed us some concepts..it will be a long process.


F says: (12/2/11 9:39 AM)
I wonder how many of those are "serious" concepts. It seems as though CSX is presenting some so-called alternate concepts to make it look like they're considering options when they've already decided on Concept 2 or something close to it.


MJM says: (12/3/11 3:43 PM)
If Concept 5 is a dig, build, cover, repeat as you go instead of one open long trench that may be the best option of them all. Can anyone confirm that is how Concept 5 would be constructed?


Douglas Willinger says: (12/4/11 3:30 AM)
Concept 5 also preserves a wider space making it easier to construct a below ground cut and cover tunnel for replacing the elevated SE Freeway- and would even be better if the new northern tunnel was shifted closer to the new southern tunnel.

link

link

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts
  

CJBabyDaddy on August Tidbit Roundup: @Smitty: JD’s Tingey Square link above reveals all. Think Times Square but with...
smitty2k1 on August Tidbit Roundup: So what's with Tingey Square? Just a new traffic pattern? It seems to be quite t...
RMP on August Tidbit Roundup: Work is progressing at Hatoba (formerly 100 montaditos) but to the untrained eye...
walt on August Tidbit Roundup: Well, I finally ate at El Bebe and loved their tacos.
GAK on Tidbits: WestHalf is now leasing and has floor plans and pricing posted on the website
GarfieldPark on Tidbits: DC Vedgefest was today @ Nats Park. A lot of people and a lot of vendors. Was de...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
150 B/O L ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 08/18/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/15/19
700 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/15/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 08/15/19
100 B/O M ST SE   THEFT
Theft First Degree (purse-snatching)
 08/14/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 08/14/19
500 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 08/14/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 08/12/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/07/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 08/06/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/06/19
800 B/O VIRGINIA AVE SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 08/05/19
UNIT B/O N ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/04/19
400 B/O M ST SE   THEFT
Shoplifting
 08/01/19
900 B/O 3RD ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/26/19
600 B/O M ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 07/25/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 07/25/19

Recent Issued Building Permits Archive  
1100 2ND PL SE   
08/06/19 
DC WATER / JEFF NOLD
AH1901095 / CONSTRUCTION
CCTV inspection of Sanitary Sewer sytem at the corner of 2nd Place and L Street SE.
808 3RD ST SE   
07/29/19 
LAURA R JENKINS / BRANDON K. VIERNES; BRANDON K. VIERNES
M1903669 / SUPPLEMENTAL
913 4TH ST SE   
08/07/19 
JANE SESSA / KYLE YOST; KYLE YOST
SOL1901388 / CONSTRUCTION
rooftop solar pv system, less than 4' above roof.
   
08/14/19 
JANE T SESSA / null
E1910482 / SUPPLEMENTAL
1331 4TH ST SE 719   
08/07/19 
null / NA NA NA
EHOP19936898 / HOME OCCUPATION
1346 4TH ST SE   
07/24/19 
FC 1346 HOLDCO I LLC / null
P1908097 / SUPPLEMENTAL
1346 4TH ST SE 20011   
08/16/19 
FC 1346 HOLDCO 1 LLC / null
E1910605 / SUPPLEMENTAL
312 K ST SE   
08/05/19 
HENRY LOWNDES MAURY TRUSTEES / null
E1910076 / SUPPLEMENTAL
   
08/07/19 
HENRY L MAURY / BJORN FALK; ANTHONY COLELLA
SOL1901686 / CONSTRUCTION
Install 6.54 solar PV system using 20 327-watt solar panels, roof mounted, with micro-inverters.
100 M ST SE   
07/29/19 
SQUARE 743 INC / KIM MITCHELL; MONUMENT REALITY
B1909745 / CONSTRUCTION
CONSTRUCTION OF OFFICE SPACE ON THE 7TH FLOOR - MULTI TENANT FLOOR IN AN EXISTING OFFICE BUILDING. THE SPACE IS IN SHELL CONDITION, NOT PREVIOUSLY OCCUPIED. THIS IS AN EXPANSION OF AN EXISTING TENANT ON THE 7TH FLOOR
   
08/06/19 
SQUARE 743 INC / PAUL THIEBERGER; PAUL THIEBERGER
P1908468 / SUPPLEMENTAL
   
08/16/19 
SQUARE 743 INC / BRIAN QUINN; NA
B1911537 / CONSTRUCTION
Interior renovation for new tenant in existing office space on partial area of the 9th floor.
300 M ST SE   
08/08/19 
FEDERAL CENTER LP / MIKE BOONE
AH1901148 / CONSTRUCTION
PEPCO-WO#15676746 / 02-ALLEN / CHESTER-CREWS WILL BE INSTALLING CABLE. 300 BLK M ST SE 400 BLK M ST SE 400 BLK TINGEY ST SE 1200 BLK 4TH ST SE THEY WILL BE TAKING PARKING LANE AND MIDDLE LANE M-F 11PM-7AM
800 NEW JERSEY AVE SE   
08/14/19 
NEW JERSEY AT H LLC / null
E1910458 / SUPPLEMENTAL
861 NEW JERSEY AVE SE   
08/07/19 
809-853 NEW JERSEY AVE ACQUISITION LLC / JOSEPH M MAGNOLIA; JOSEPH M MAGNOLIA
P1908508 / SUPPLEMENTAL
   
08/08/19 
GRAYSTAR GP 11,LLC / KIM MITCHELL
SH1900015 / CONSTRUCTION
Support of excavation for entire site for two below grade parking levels
   
08/14/19 
GRAYSTAR GP 11 LLC / MITCH A. PERMUY; MITCH A. PERMUY
E1910454 / SUPPLEMENTAL
   
08/14/19 
GRAYSTAR GP 11 LLC / MITCH A. PERMUY; MITCH A. PERMUY
E1910455 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
07/26/19 
SQUARE 742 LLC / WILLIAM SNODDY; TBD
B1911194 / CONSTRUCTION
Tenant Finish Out. Existing Condition to be demolished and new office space built to tenant's standards. Office consists of open office and private offices.
   
07/30/19 
SQUARE 742 LLC / null
P1908231 / SUPPLEMENTAL
   
08/06/19 
SQUARE 742 LLC / ;
P1908470 / SUPPLEMENTAL
   
08/06/19 
SQUARE 742 LLC / null
M1903804 / SUPPLEMENTAL
520 TINGEY ST SE   
08/12/19 
US GENERAL SERVICES ADMINISTRATION / JOHN WICKLIFFE; NA
TN1900153 / CONSTRUCTION
Install 100ft x 90ft Tent No Cooking, No Propane, No Stages, No Smoking Installed Aug 16, 2019 - Feb 9, 2020 Events Daily 8:00 am - 10:00 pm
227 TINGEY ST SE   
07/31/19 
UNITED STATES OF AMERICA / BILL SAUNDERS; BILL SAUNDERS
P1908289 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2019 JD.