Just sent out by DDOT: "Today the District Department of Transportation (DDOT) announced the start of land acquisition and preliminary design work for the South Capitol Street Project, which includes replacement of the current Frederick Douglass Memorial Bridge. [...] While the Record of Decision (ROD) is still pending, the Federal Highway Administration signed the project's Final Environmental Impact Statement (FEIS) following the requisite 30-day public comment period that ended in May."
I'm posting quickly, so I shall now crib unabashedly from my post on the Final EIS, from back in April:
If you are interested in this subject, there is more verbiage and documentation accompanying the plans than you could ever dream of. (Traffic studies! Environmental consequences! Technical reports!) And I've written a lot about the process, which began more than a decade ago with other studies before the EIS got underway. And I'm sure there will be posts on other blogs delving more specifically into portions of the plans. But, since most people probably want to know "what does this mean for me?", you can see this graphic (from the 224-MB chapter 2 of the FEIS) giving a quick overview of what changes are planned along South Capitol Street if the final EIS is signed off on (and, more importantly, if funding is secured). The short version, for the west side of the Anacostia:
* Add "pedestrian amenities" and enhance the streetcape along South Capitol north of I and along New Jersey Avenue SE north of the freeway.
* Replace the existing ramp to the freeway from South Capitol and I with an at-grade intersection. (This would be a left turn onto a ramp to the freeway from under the freeway, near the current Nats HH economy parking lot.)
* Bring New Jersey Avenue SE back to a 160-foot full right-of-way, and add streetscape enhancements.
* "Reconstruct South Capitol Street as an urban boulevard." This means bringing M Street up to an "at-grade" intersection (no more tunnel), and would include new signalized at-grade intersections to allow traffic to cross South Capitol on K and L streets. (M Street would also get reconstructed between the Halfs [SE and SW].) The section of South Capitol north of M would have the same streetscape that the south portion received during its 2007/08 makeover, with wide sidewalks and a tree-lined median.
* Build a traffic oval at South Capitol, Potomac, Q, as the gateway to a new arched bascule-design Douglass Bridge that would have wide "multi-use trails" (i.e., sidewalks!) in both directions. The existing bridge would be demolished, after the new bridge is built somewhat downriver of the current location.
The Executive Summary (220 MB PDF) gives a good overview of the FEIS and preferred alternative (as it should!), but I also suggest wandering through the Chapter 2: Alternatives section, especially if you came to the neighborhood or JDLand after 2008 and didn't get to follow along during the EIS process, or if you're interested in the additional plans for east of the river, which I'm going to leave to others to discuss. My previous posts on all of this may be of interest as well. If you're wanting to see some of the earlier studies referenced in the FEIS, there are links to them at the top of my South Capitol Street project page.
How much would this all cost? The preferred alternative is priced in this final EIS at $806 million in FY 2014 dollars. (New bridges are expensive, you know.) Note that nothing in today's statement from DDOT says anything about funding, or a construction timeline.
You can also check my South Capitol Street and South Capitol Street Bridge page for all the info about the plans, along with my scores of posts over the past few years.
Comments (6)
   
 
 More About South Capitol St.

JDLand.com Home

Comments

Alan says: (9/29/11 9:35 AM)
Hey JD, what does 'Bring New Jersey Avenue SE back to a 160-foot full right-of-way,' mean?


JD says: (9/29/11 9:53 AM)
If you look on the graphic: link Basically it means widening New Jersey south of the freeway to K (where they can). There's that little service road on the east side that would go away. If you read deeper into the FEIS, it's about adding bike lanes and streetscape improvements (wider sidewalks) on New Jersey than more cars.


JD says: (9/29/11 10:54 AM)
And, since someone asked me privately, I'll also point out that the $806 million price tag is for the entire project. The new bridge itself is priced at $357 million, not all that different from the cost of the new 11th Street Bridges.


Alan says: (9/29/11 1:25 PM)
Thanks!


F says: (10/1/11 2:17 PM)
Considering the work on New Jersey Ave, the construction by W.C. Smith on the Trash Transfer site and the CSX railway project...are the horse stables still going to stay there. There must be some Cruelty to Animals ordinance thats being violated.


AVC says: (10/5/11 2:22 PM)
The woman who runs the horse carriage company and owns the horses has been given an eviction notice from the city as they own the property she has been leasing. Not sure where she will be able to go.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2016!
 Top News

202_cyclist on Columnist Walks the: Bring on the Cuba! Also, our condolences are with the family and teammates of J...
conngs0 on Columnist Walks the: I think the overall point is that there are different ways to skin a cat (Sorry,...
202_cyclist on Wednesday Tidbits: As the kiddos say, does anyone have any deets about the new urban vegetable gard...

  
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
16 B/O M ST SE   ROBBERY  09/23/16
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/23/16
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/19/16
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/18/16
1200 B/O 1ST ST SE   ASSAULT WITH A DANGEROUS WEAPON  09/17/16
400 B/O M ST SE   THEFT
Shoplifting
 09/16/16
1100 B/O 5TH ST SE   THEFT
Theft First Degree (all Other Larceny)
 09/06/16
700 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 09/06/16
1200 B/O 1ST ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/04/16
UNIT B/O I ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 09/04/16
1400 B/O SOUTH CAPITOL ST   THEFT
Theft 2nd Degree (all Other Larceny)
 08/28/16

Recent Issued Building Permits Archive  
1233 1ST ST SE   
09/16/16 
NA BALLPARK HOTEL LLC / NORTHEAST ELECTRIC; NA BALLPARK HOTEL LLC; HOSSEIN ECONO SIGN INC.
SG1600390 / CONSTRUCTION
To Install four signs: -3 - Channel letters on Raceways -1- Blade Sign
1331 2ND ST SE   
09/19/16 
DC WATER / DC WATER; CORMAN CONSTRUCTION
AH1601056 / CONSTRUCTION
After hour work for structure excavation and support for building permit B1311474 DC Water, Corman Construction 202-863-0052
933 5TH ST SE   
09/12/16 
null / NA NA NA
EHOP16924112 / HOME OCCUPATION
1015 HALF ST SE   
09/14/16 
HALF STREET SE LLC HALF STREET SE LLC / DARIN PASQUALLE; HALF STREET SE LLC HALF STREET SE LLC; DARIN PASQUALLE
E24765056 / SUPPLEMENTAL
   
09/21/16 
HALF STREET SE LLC / 1015 HALF SE LLC; JOHN GIUSEPPE-RAMCO
B1610675 / CONSTRUCTION
Construction of elevator lobby and common corridors on the 7th floor as shown on the electronically submitted mechanical, electrical, fire protection, and arch. dwgs. Interior work only. No structural work involved. approx. 2275 sf.
1210 HALF ST SE   
09/07/16 
HINES GLOBAL REIT 55 M STREET LLC / MATT LOSIGNOR
P1609218 / SUPPLEMENTAL
75 I ST SE   
09/07/16 
99 I ST SE LP / 99 I ST SE LP; ECS MID-ATLANTIC, LLC C/O REBECCA RUSCHMAN
SB1600354 / CONSTRUCTION
We will perform 2 soil borings and 2 CPT cone soundings on the site. The 2 soil borings and 2 CPT soundings will be extended to depths on the order of 90 ft below the existing site grades. The borings and soundings will be perfroemd within the bounds of private property and will be drilled utilizing a 3.25-inch hollow stem, continuous flight augers and generate a 6-inch annulus. After the borings...
82 I ST SE   
09/09/16 
GDVC EYE STREET LLC / MITCH A. PERMUY
E1609957 / SUPPLEMENTAL
88 K ST SE   
09/07/16 
99 I ST SE LP 99 I ST SE LP / 99 I ST SE LP 99 I ST SE LP; ECS MID-ATLANTIC, LLC C/O REBECCA RUSCHMAN
SB1600355 / CONSTRUCTION
We will perform 2 CPT cone soundings on the project site within the bounds of private space. The CPT cones will be extende to a depth of 90 feet below the existing ground surface, utilizing a 4-inch diameter cone and generate a 4-inch annulus. After the soundings are completed they will be backfilled with bentonite slurry which has a consistency of two pounds bentonite powder to one gallon water.
80 M ST SE 400   
09/15/16 
WELLS REIT II 80 M STREET LLC / null
P1609454 / SUPPLEMENTAL
50 M ST SE   
09/15/16 
KCG 50 M LLC / KCG 50 M LLC ENGLEWOOD LLC; TRACIE CLAXTON; CLAXTON
SG1600460 / CONSTRUCTION
2 Wall mounted Signs - Reversed Channel Letter 2 small wall mounted plague
80 M ST SE   
09/09/16 
WELLS REIT II 80 M STREET LLC / PHILIP G DONNELLY
E1609959 / SUPPLEMENTAL
99 M ST SE   
09/16/16 
BALLPARK SQUARE 701, LLC SKANSKA COMMERCIAL DEVELOPMENT / BALLPARK SQUARE 701, LLC SKANSKA COMMERCIAL DEVEL
AH1601047 / CONSTRUCTION
Place concrete mat foundation slab. Before work hours - 3AM to 7AM on 9 / 19 / 2016 and 9 / 20 / 2016, if weather or jobsite delays prevail. Permit will only be needed / used for 1 of the 2 days. (Per ANC agreement "before hours work on ONE of the following days: either September 17, 19, or 20," & "to begin no earlier than 3:00 am" )
   
09/16/16 
BALLPARK SQUARE 701, LLC SKANSKA COMMERCIAL DEVELOPMENT / BALLPARK SQUARE 701, LLC SKANSKA COMMERCIAL DEVEL
AH1601048 / CONSTRUCTION
Place concrete at 99 M Street SE for mat foundation slab. Saturday 9 / 17 / 2016 concrete placement from 3AM to 7PM. (Per ANC agreement "before hours work on ONE of the following days: either September 17, 19, or 20," & "to begin no earlier than 3:00 am" )
100 M ST SE 4   
09/09/16 
SQUARE 743 INC / null
P1609322 / SUPPLEMENTAL
100 M ST SE   
09/20/16 
QUARE 743 INC / QUARE 743 INC; QUARE 743 INC; PHILIP HAUHN
E14003252 / SUPPLEMENTAL
202 M ST SE   
09/09/16 
UNITED STATES OF AMERICA / EBONY BROWN DC HUMANITIES AND ARTS COMMISSION
TN1600199 / CONSTRUCTION
SPECIAL EVENT 202 ARTS & MUSIC FESTIVAL 1 SL 250 24 X 32 STAGE
1100 NEW JERSEY AVE SE 845   
09/21/16 
SQUARE 742 LLC SPAULDING & SLYE C/O WC SMITH / SQUARE 742 LLC SPAULDING & SLYE C/O WC SMITH; WILLIAM SNODDY
B1612012 / CONSTRUCTION
Interior Renovation on the 8th Floor on behalf of Maxim Health 5,138 sqft
1100 NEW JERSEY AVE SE   
09/14/16 
SPAULDING AND SLYE SPAULDING AND SLYE / HALEY HUGGINS; SPAULDING AND SLYE SPAULDING AND SLYE; JOHNNY RILING
E39166644 / SUPPLEMENTAL
125 O ST SE   
09/19/16 
DISTRICT OF COLUMBIA / DC WATER HQ; DAVID FONTANA MSC
EX1600110 / CONSTRUCTION
Site grading and demo per erosion control plan only for future new DC Water HQ building under seperate permit.
1244 SOUTH CAPITOL ST SE   
09/19/16 
1244 SOUTH CAPITOL RESIDENTIAL LLC / RONALD C. CAYTON
E1610018 / SUPPLEMENTAL
385 WATER ST SE   
09/15/16 
FC 385 WATER LLC / EDUARDO L. LOPEZ
E1610139 / SUPPLEMENTAL
355 WATER ST SE   
09/14/16 
OLIVIA DARROW RAGNAR EVENTS LLC
TN1600198 / CONSTRUCTION
SPECIAL EVENT RAGNAR RELMAY WASHINGTON DC 2 20 X 20 TENTS 25 10 X 10 TENTS 1 30 X 40 TENT FENCING FOR BEER GARDEN
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Capitol ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2016 JD.