July 18, 2006
April 26, 2015
Van at M, Looking South-Southeast (see more)

The DC Housing Authority has filed a request with the Zoning Commission for a time extension to construct the mixed-income apartment buildings it has planned for the north half of Square 882 (the old Capper Seniors block along L Street between 5th and 7th, seen at right) and the north half of Square 769, between 2nd and 3rd on L just east of Canal Park (below, the building at left, next to the proposed 250 M Street).
When the plans for these two buildings were approved by the Zoning Commission in 2009 (see the zoning order), it was required that building permits be applied for by August of this year, with construction to begin by August of 2012. However, attempts at funding either the Square 882 189-unit building or 171-unit Square 769N building the have not thus far borne any fruit, and so a time extension is needed. Between them, the buildings would have 72 units reserved for households making less than 60 percent of the area median income, and the Square 769 building would also have just over 4,000 square feet of ground-floor retail space.
The Zoning Commission will hear this request at its meeting on Monday night; because there is no request to modify any portion of the PUD beyond the time requirement, this will most likely be handled as a consent calendar item. There will also be a presentation on this request and the state of the Capper redevelopment in general at Monday's ANC 6D meeting. (There was also one given at Tuesday night's ANC 6B's Planning and Zoning Committee meeting, but I had a baseball game to watch.) But since the Zoning Commission hearing is at the same time as the 6D meeting, it would seem that there is no anticipated opposition from 6D.
The Office of Planning prepared a short report recommending approval of the time extension, showing that the requirements for an extension have been met. It also quotes the development team as saying that there have been 75 outreach efforts for financing, all unsuccessful. "The inability to secure financing for residential projects, especially those including affordable units, is not unusual in the current marketplace."
If you want to know more about these two planned apartment projects, and the other three mixed-income buildings planned along the east side of Canal Park and on the DPW/trash transfer site, my Capper Apartments page has additional background, as do the scads of blog posts I've written on the various plans. And my main Capper page has the background on the entire redevelopment project.
UPDATE: And, of course, within seconds of my pulling the trigger and posting this entry, I've received a copy of the letter to the Zoning Commission requesting the PUD. Which I'm posting before reading.
Comments (2)
   
 
 More About Lofts at Capitol Quarter

JDLand.com Home

Comments

B in DC says: (9/7/11 3:36 PM)
Just throwing out a random question. What would be the possibility of turning the four remaining parcels over to EYA, allowing them to develop "Phase 3" of Capitol Quarter, but with a greater percentage of affordable units to still provide for replacements for all former Capper residents? EYA/DCHA might have a better chance of getting funding that way.


JD says: (9/7/11 3:43 PM)
I think there are all manner of possibilities being explored. But you wouldn't be able to get the density required to get all needed affordable housing units (and the needed number of market-rate units to make the projects financially viable) by just replacing the apartment buildings with townhouses. There are 1130 units still on the boards to be constructed (excluding Capitol Quarter), of which 309 need to be public housing. You have to build apartment buildings to get to those numbers.




Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed

See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2015!
 Top News
  
Bruce on Your Sunday Morning: Great seeing you out and about yesterday.
Jaybird on Your Sunday Morning: Welcome back JD! That is one amazing pair of before and afters. Not sure where...
willinrm on Due South Opening: does anyone have a navy yard/eastern market/capitol hill happy hour website? dat...
Section314 on Due South Opening: First thing back, you can go take pictures of the construction starting at 99 M....



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
900 B/O POTOMAC AVE SE   THEFT F/AUTO
 08/17/15
500 B/O L ST SE   THEFT F/AUTO
 08/17/15
UNIT B/O K ST SE   THEFT F/AUTO
 08/16/15
500 B/O L ST SE   THEFT
 08/08/15
UNIT B/O I ST SE   BURGLARY
 08/07/15
300 B/O WATER ST SE   THEFT
 08/05/15
UNIT B/O I ST SE   THEFT
 08/04/15
50 B/O M ST SE   THEFT
 08/04/15
400 B/O M ST SE   THEFT
 08/03/15
1100 B/O NEW JERSEY AVE SE   THEFT
 07/29/15

Recent Issued Building Permits Archive  
1277 1ST ST SE   
08/11/15 
BALLPARK RESIDENTIAL LLC / RICHARD V CAREY
P1508164 / SUPPLEMENTAL
   
08/21/15 
BALLPARK RESIDENTIAL LLC BALLPARK RESIDENTIAL LLC / CLINT HOLMES; BALLPARK RESIDE BALLPARK RESIDENTIAL LLC; MITCH PERMUY
E20139177 / SUPPLEMENTAL
1000 5TH ST SE   
08/18/15 
UNITED STATES OF AMERICA / JOSEPH M MAGNOLIA
P1508371 / SUPPLEMENTAL
1150 5TH ST SE   
08/10/15 
DEPARTMENT OF GENERAL SERVICES DC PUBLIC SCHOOL / DEPARTMENT OF G DC PUBLIC SCHOOL
B1511234 / CONSTRUCTION
REVISION TO B1511107 TO CORRECT QUADANT ON ADDRESS FROM 1150 5TH STREET N.E. TO 1150 5TH STREET S.E. TO UPGRADE THE ELECTRICAL SERVICES OF A DISTRICT OF COLUMBIA PUBLIC SCHOOL FROM 1200AMP TO 3 000 AMP.
   
08/11/15 
PEPCO PEPCO
AH1500668 / CONSTRUCTION
INSTALLATION OF CABLE AND METERS
1220 12TH ST SE   
08/13/15 
WASHINGTON GAS LIGHT CO / JOHN GIUSEPPE-RAMCO
B1509350 / CONSTRUCTION
RENOVATIONS TO EXISTING 3RD FLOOR OFFICE SPACE EXELIS AS SHOWN ON THE ATTACHED MECH. PLUMB. ELECT. FIRE PROTECTION DEMOLITION AND ARCH. DWGS. INTERIOR WORK ONLY. NO CHANGE IN US. NO STRUCT. WORK.
909 HALF ST SE   
08/13/15 
BAKER DC LLC / CHRISTINE LONG
AH1500677 / CONSTRUCTION
AN AFTER HOURS PERMIT IS RESPECTFULLY REQUESTED FROM 11:00PM FRIDAY THRU 11:00PM SATURDAY
   
08/18/15 
BAKER DC
AH1500686 / CONSTRUCTION
AN AFTER HOURS PERMIT IS RESPECTFULLY REQUESTED FROM 12:01AM WEDNESDAY THRU 11:59PM THURSDAY. 1-49 BLOCK OF K ST SE
   
08/21/15 
BAKER DC / CHRISTINE LONG
AH1500695 / CONSTRUCTION
AN AFTER HOURS PERMIT IS FROM 12:01AM THRU 11:59PM FROM 08 / 25 / 2015 TO 08 / 29 / 2015
1015 HALF ST SE   
08/13/15 
HALF ST SE LLC / GREGORY E LIGON
E1508399 / SUPPLEMENTAL
   
08/17/15 
HALF ST SE LLC / ANTHONY G SAMBURG
E1508502 / SUPPLEMENTAL
   
08/20/15 
WSP PARSONS BRINCKERHOFF / STEVE AUD; WSP PARSONS BRINCKERHOFF; STEVE AUD
E95740122 / SUPPLEMENTAL
1220 HALF ST SE   
08/12/15 
BUFFALO WILD WINGS / NICOLE WHITE; BUFFALO WILD WINGS; GREG CONCANNON
AR49901357 / SUPPLEMENTAL
   
08/13/15 
BUFFALO WILD WINGS / BELA X-PEDITERS PLUS INC.
AH1500681 / CONSTRUCTION
WORK AFTER HOURS 7PM-7AM. 8 / 13 / 2015 TO 9 / 13 / 2015
601 L ST SE   
08/17/15 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / KRISSY GER LISA LJ PERMIT
B1510955 / CONSTRUCTION
REVISION TO B1101058 MINOR GRADING REVISION
   
08/20/15 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / MARK A DORSEY
EN1502944 / SHOP DRAWING
TYPE OF ELEVATOR ONE (1) HYDRO / STEEL / CENTRALLY / PASSENGER TO PROVIDE ACCESS BETWEEN G AND G2 FLOORS AS PER PLANS.
   
08/20/15 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / MARK A DORSEY
EN1502945 / SHOP DRAWING
TYPE OF ELEVATOR: TWO (2) TRACTION / STEEL / CENTRALLY / PASSENGER (5TH FLOOR).
   
08/20/15 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / MARK A DORSEY
EN1502970 / SHOP DRAWING
TYPE OF ELEVATOR ONE (1) TRACTION / STEEL / CENTRALLY / PASSENGER (6TH FLOOR).
   
08/20/15 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / MARK A DORSEY
EN1502971 / SHOP DRAWING
TYPE OF ELEVATOR ONE (1) TRACTION / STEEL / CENTRALLY / PASSENGER (6TH FLOOR).
80 M ST SE   
08/24/15 
COLUMBIA PROPERTY TRUST / KRISTINA DELGADO
B1510944 / CONSTRUCTION
PARTIAL 4TH FLOOR RENOVATIONS INCLUDING MECHANICAL PLUMBING ELECTRICAL AS WELL AS FURNITURE INSTALLATION.
20 M ST SE   
08/19/15 
SOUTHEAST REALTY LLC / ELEANOR FARID; SOUTHEAST REALTY LLC; RODNEY CANNON
E69278004 / SUPPLEMENTAL
50 M ST SE   
08/11/15 
MILLER?LONG
TC1500036 / CONSTRUCTION
TOWER CRANE FOR JOB SITE USE
   
08/13/15 
MILLER?LONG MILLER?LONG
AH1500674 / CONSTRUCTION
AFTERHOURS TO PUT UP TOWERCRANE WITH 200 TON MOBILE CRANE SATURDAY 8 / 15 / 2015 AND 8 / 16 / 2015 FROM 5AM TO 9PM
   
08/14/15 
KCG 50 M LLC / JOSEPH E RICHARDS
E1508432 / SUPPLEMENTAL
   
08/21/15 
KCG 50 M LLC / DANIEL R. RUDE
P1508460 / SUPPLEMENTAL
55 M ST SE   
08/19/15 
DOUG OLSON / DOUG OLSON; NONE
SG1500414 / CONSTRUCTION
NEW SIGNS INSTALLATION AS PER PLANS
1100 NEW JERSEY AVE SE   
08/11/15 
CHRISTOPHER CONDON
PC69159304 / POST CARD
INTERIOR DEMOLITION OF NON-BEARING ELEMENTS IN A SPACE UP TO 5 000 SQUARE FEET (464.5 SQUARE METERS)
1500 SOUTH CAPITOL ST SE   
08/14/15 
P1508259 / SUPPLEMENTAL
301 WATER ST SE   
08/12/15 
LUMBER SHED LIC / ROBERT WATTS; LUMBER SHED LIC; ROBERT WATTS
E99575145 / SUPPLEMENTAL
355 WATER ST SE   
08/14/15 
TIAN LUU / TIAN LUU; TIAN LUU; JAMES BORROR
E95497821 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory




     © Copyright 2015 JD.