Sliding from Before to After
 The DC Housing Authority has filed a request with the Zoning Commission for a time extension to construct the mixed-income apartment buildings it has planned for the north half of Square 882 (the old Capper Seniors block along L Street between 5th and 7th, seen at right) and the north half of Square 769, between 2nd and 3rd on L just east of Canal Park (below, the building at left, next to the proposed 250 M Street). When the plans for these two buildings were approved by the Zoning Commission in 2009 (see the zoning order), it was required that building permits be applied for by August of this year, with construction to begin by August of 2012. However, attempts at funding either the Square 882 189-unit building or 171-unit Square 769N building the have not thus far borne any fruit, and so a time extension is needed. Between them, the buildings would have 72 units reserved for households making less than 60 percent of the area median income, and the Square 769 building would also have just over 4,000 square feet of ground-floor retail space.  The Zoning Commission will hear this request at its meeting on Monday night; because there is no request to modify any portion of the PUD beyond the time requirement, this will most likely be handled as a consent calendar item. There will also be a presentation on this request and the state of the Capper redevelopment in general at Monday's ANC 6D meeting. (There was also one given at Tuesday night's ANC 6B's Planning and Zoning Committee meeting, but I had a baseball game to watch.) But since the Zoning Commission hearing is at the same time as the 6D meeting, it would seem that there is no anticipated opposition from 6D. The Office of Planning prepared a short report recommending approval of the time extension, showing that the requirements for an extension have been met. It also quotes the development team as saying that there have been 75 outreach efforts for financing, all unsuccessful. "The inability to secure financing for residential projects, especially those including affordable units, is not unusual in the current marketplace." If you want to know more about these two planned apartment projects, and the other three mixed-income buildings planned along the east side of Canal Park and on the DPW/trash transfer site, my Capper Apartments page has additional background, as do the scads of blog posts I've written on the various plans. And my main Capper page has the background on the entire redevelopment project.
JDLand.com Home
B in DC says: (9/7/11 3:36 PM)
Just throwing out a random question. What would be the possibility of turning the four remaining parcels over to EYA, allowing them to develop "Phase 3" of Capitol Quarter, but with a greater percentage of affordable units to still provide for replacements for all former Capper residents? EYA/DCHA might have a better chance of getting funding that way.
JD says: (9/7/11 3:43 PM)
I think there are all manner of possibilities being explored. But you wouldn't be able to get the density required to get all needed affordable housing units (and the needed number of market-rate units to make the projects financially viable) by just replacing the apartment buildings with townhouses. There are 1130 units still on the boards to be constructed (excluding Capitol Quarter), of which 309 need to be public housing. You have to build apartment buildings to get to those numbers.
Add a Comment:
Comments are closed for this post.
JDLand Comments RSS Feed
See All Current News Items |
Full Blog Archive
|
|
|
Full Neighborhood Development Map
There's a lot more than just the projects listed here. See the complete map of completed, underway, and proposed projects all across the neighborhood.
What's New This Year A quick look at what's arrived or been announced since the end of the 2018 baseball season.
Food Options, Now and Coming Soon
There's now plenty of food options in the neighborhood. Click to see what's here, and what's coming.
Anacostia Riverwalk
A bridge between Teague and Yards Parks is part of the planned 20-mile Anacostia Riverwalk multi-use trail along the east and west banks of the Anacostia River.
Virginia Ave. Tunnel Expansion
Construction underway in 2015 to expand the 106-year-old tunnel to allow for a second track and double-height cars. Expected completion 2018.
Rail and Bus Times Get real time data for the Navy Yard subway, Circulator, Bikeshare, and bus lines, plus additional transit information.
Rail and Bus Times Get real time data for the Navy Yard subway, Circulator, Bikeshare, and bus lines, plus additional transit information.
Canal Park
Three-block park on the site of the old Washington Canal. Construction begun in spring 2011, opened Nov. 16, 2012.
Nationals Park
21-acre site, 41,000-seat ballpark, construction begun May 2006, Opening Day March 30, 2008.
Washington Navy Yard
Headquarters of the Naval District Washington, established in 1799.
Yards Park
5.5-acre park on the banks of the Anacostia. First phase completed September 2010.
Van Ness Elementary School
DC Public School, closed in 2006, but reopening in stages beginning in 2015.
Agora/Whole Foods
336-unit apartment building at 800 New Jersey Ave., SE. Construction begun June 2014, move-ins underway early 2018. Whole Foods expected to open in late 2018.
New Douglass Bridge
Construction underway in early 2018 on the replacement for the current South Capitol Street Bridge. Completion expected in 2021.
1221 Van
290-unit residential building with 26,000 sf retail. Underway late 2015, completed early 2018.
NAB HQ/Avidian
New headquarters for National Association of Broadcasters, along with a 163-unit condo building. Construction underway early 2017.
Yards/Parcel O Residential Projects
The Bower, a 138-unit condo building by PN Hoffman, and The Guild, a 190-unit rental building by Forest City on the southeast corner of 4th and Tingey. Underway fall 2016, delivery 2018.
New DC Water HQ
A wrap-around six-story addition to the existing O Street Pumping Station. Construction underway in 2016, with completion in 2018.
The Harlow/Square 769N Apts
Mixed-income rental building with 176 units, including 36 public housing units. Underway early 2017, delivery 2019.
West Half Residential
420-unit project with 65,000 sf retail. Construction underway spring 2017.
Novel South Capitol/2 I St.
530ish-unit apartment building in two phases, on old McDonald's site. Construction underway early 2017, completed summer 2019.
1250 Half/Envy
310 rental units at 1250, 123 condos at Envy, 60,000 square feet of retail. Underway spring 2017.
Parc Riverside Phase II
314ish-unit residential building at 1010 Half St., SE, by Toll Bros. Construction underway summer 2017.
99 M Street
A 224,000-square-foot office building by Skanska for the corner of 1st and M. Underway fall 2015, substantially complete summer 2018. Circa and an unnamed sibling restaurant announced tenants.
The Garrett
375-unit rental building at 2nd and I with 13,000 sq ft retail. Construction underway late fall 2017.
Yards/The Estate Apts. and Thompson Hotel
270-unit rental building and 227-room Thompson Hotel, with 20,000 sq ft retail total. Construction underway fall 2017.
Meridian on First
275-unit residential building, by Paradigm. Construction underway early 2018.
The Maren/71 Potomac
264-unit residential building with 12,500 sq ft retail, underway spring 2018. Phase 2 of RiverFront on the Anacostia development.
DC Crossing/Square 696
Block bought in 2016 by Tishman Speyer, with plans for 800 apartment units and 44,000 square feet of retail in two phases. Digging underway April 2018.
One Hill South Phase 2
300ish-unit unnamed sibling building at South Capitol and I. Work underway summer 2018.
New DDOT HQ/250 M
New headquarters for the District Department of Transportation. Underway early 2019.
37 L Street Condos
11-story, 74-unit condo building west of Half St. Underway early 2019.
CSX East Residential/Hotel
225ish-unit AC Marriott and two residential buildings planned. Digging underway late summer 2019.
1000 South Capitol Residential
224-unit apartment building by Lerner. Underway fall 2019.
Capper Seniors 2.0
Reconstruction of the 160-unit building for low-income seniors that was destroyed by fire in 2018.
Chemonics HQ
New 285,000-sq-ft office building with 14,000 sq ft of retail. Expected delivery 2021.
Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.
|
|
1100 B/O NEW JERSEY AVE SE
|
| BURGLARY
Burglary Two
| 11/26/20
|
UNIT B/O M ST SE
|
| ROBBERY
| 11/25/20
|
1000 B/O NEW JERSEY AVE SE
|
| THEFT FROM AUTO
Theft (theft From Motor Vehicle)
| 11/24/20
|
UNIT B/O I ST SE
|
| ROBBERY
Carjacking
| 11/23/20
|
200 B/O M ST SE
|
| ASSAULT WITH A DANGEROUS WEAPON
| 11/22/20
|
UNIT B/O I ST SE
|
| THEFT
Theft 2nd Degree (all Other Larceny)
| 11/22/20
|
700 B/O L ST SE
|
| THEFT
Theft 2nd Degree (all Other Larceny)
| 11/22/20
|
1000 B/O 3RD ST SE
|
| ROBBERY
| 11/21/20
|
1200 B/O 1ST ST SE
|
| THEFT FROM AUTO
Theft (theft From Motor Vehicle)
| 11/19/20
|
UNIT B/O M ST SE
|
| THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
| 11/18/20
|
1000 B/O HALF ST SE
|
| THEFT
Theft 2nd Degree (all Other Larceny)
| 11/12/20
|
1100 B/O 2ND PLACE SE
|
| MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
| 11/12/20
|
1000 B/O 8TH ST SE
|
| THEFT
Theft First Degree (theft From Building)
| 11/12/20
|
1000 B/O HALF ST SE
|
| THEFT FROM AUTO
Theft (theft Of Motor Vehicle Parts Or Accessories)
| 11/10/20
|
400 B/O M ST SE
|
| THEFT
Theft 2nd Degree (all Other Larceny)
| 11/05/20
|
300 B/O L ST SE
|
| THEFT FROM AUTO
Theft (theft From Motor Vehicle)
| 11/05/20
|
900 B/O 4TH ST SE
|
| THEFT FROM AUTO
Theft (theft From Motor Vehicle)
| 11/01/20
|
UNIT B/O I ST SE
|
| THEFT
Theft First Degree (shoplifting)
| 10/31/20
|
900 B/O HALF ST SE
|
| MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
| 10/29/20
|
300 B/O TINGEY ST SE
|
| ROBBERY
Carjacking
| 10/29/20
|
1300 B/O 4TH ST SE
|
| THEFT
Theft 2nd Degree (all Other Larceny)
| 10/28/20
|
|
Recent Issued Building Permits
| Archive
|
|
1200 1ST ST SE
|
|
11/04/20
PEPCO / DONNA G GRAHAM
AH2100169 /
CONSTRUCTION
WO #16029084 / 02 - 1200 1ST ST SE - PEPCO / WA CHESTER TO REMOVE AND INSTALL CABLES MONDAY THROUGH SATURDAYS FROM 9PM TO 6AM STARTING 11 / 5 / 20 TO 12 / 5 / 20
|
1018 3RD ST SE
|
|
11/10/20
DAVID A LEINER / null
E2101357 /
SUPPLEMENTAL
|
1300 4TH ST SE 1001
|
|
11/03/20
YAAN REAL ESTATE LP / null
P2100950 /
SUPPLEMENTAL
|
1300 4TH ST SE RU-1
|
|
11/19/20
AP BOWER RETAIL LLC / null
E2101650 /
SUPPLEMENTAL
|
1057 5TH ST SE
|
|
11/05/20
PAM HARDER / null
E2101183 /
SUPPLEMENTAL
|
82 I ST SE
|
|
11/12/20
STARRY / null
E2101432 /
SUPPLEMENTAL
|
330 K ST SE
|
|
11/09/20
MINDY J SHAW / CASEY CHARKHABI; NA
B2008664 /
CONSTRUCTION
Adding a bathroom on the first floor
|
|
|
11/10/20
JINGSONG XIA / null
P2101107 /
SUPPLEMENTAL
|
100 M ST SE
|
|
11/12/20
LHREV WASHINGTON M ST LLC / null
P2101170 /
SUPPLEMENTAL
|
|
|
11/12/20
SQUARE 743 INC / ;
P2101121 /
SUPPLEMENTAL
|
139 N ST SE
|
|
11/10/20
BROOKFIELD DEVELOPMENT / JUSTIN BELLOW; BROOKFIELD DEVELOPMENT
B2004436 /
CONSTRUCTION
NEW CONSTRUCTION 10-STORY PLUS PENTHOUSE APARTMENT BUILDING WITH 379 UNITS. PROPOSED GROSS FLOOR AREA: 225,000 SF.
SH2000028 issued
|
1275 NEW JERSEY AVE SE
|
|
11/04/20
USA / null
E2101168 /
SUPPLEMENTAL
|
|
|
11/09/20
BROOKFIELD PROPERTIES / TIM GOOD
BP2100588 /
POST CARD
|
71 POTOMAC AVE SE APT 1208
|
|
11/02/20
null / NA NA NA
EHOP20957167 /
HOME OCCUPATION
|
71 POTOMAC AVE SE
|
|
11/04/20
RIVERFRONT HOLDINGS II, LLC / null
M2100380 /
SUPPLEMENTAL
|
|
|
11/04/20
RIVERFRONT HOLDINGS II, LLC / null
P2100978 /
SUPPLEMENTAL
|
|
|
11/09/20
MRP REALTY / null
E2101319 /
SUPPLEMENTAL
|
227 TINGEY ST SE
|
|
11/18/20
FC 227 LLC / null
E2101630 /
SUPPLEMENTAL
|
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;
|
|
|
No commercial transaction records added or modified in the past two weeks. |
|
|