Since January, 2003
            
 Sliding from Before to After

It's been so long since I've written about this that I forgot it was even still in progress, but DDOT has announced two public meetings to present the "preferred alternative" and the Final Environmental Impact Statement for the South Capitol Street Corridor, first on April 26 at Amidon-Bowen Elementary School in SW and then two days later at Savoy Elementary School in SE. This is the long-term study of how to improve South Capitol Street on both sides of the Anacostia River to better address safety, traffic, pedestrian, and streetscape issues, and includes the construction of a new Frederick Douglass Bridge.
If you are interested in this subject, there is more verbiage and documentation accompanying the plans than you could ever dream of. (Traffic studies! Environmental consequences! Technical reports!) And I've written a lot about the process, which began more than a decade ago with other studies before the EIS got underway. And I'm sure there will be posts on other blogs delving more specifically into portions of the plans. But, since most people probably want to know "what does this mean for me?", you can see this graphic (from the 224-MB chapter 2 of the FEIS) giving a quick overview of what changes are planned along South Capitol Street if the final EIS is signed off on (and, more importantly, if funding is secured). The short version, for the west side of the Anacostia:
* Add "pedestrian amenities" and enhance the streetcape along South Capitol north of I and along New Jersey Avenue SE north of the freeway.
* Replace the existing ramp to the freeway from South Capitol and I with an at-grade intersection. (This would be a left turn onto a ramp to the freeway from under the freeway, near the current Nats HH economy parking lot.)
* Bring New Jersey Avenue SE back to a 160-foot full right-of-way, and add streetscape enhancements.
* "Reconstruct South Capitol Street as an urban boulevard." This means bringing M Street up to an "at-grade" intersection (no more tunnel), and would include new signalized at-grade intersections to allow traffic to cross South Capitol on K and L streets. (M Street would also get reconstructed between the Halfs [SE and SW].) The section of South Capitol north of M would have the same streetscape that the south portion received during its 2007/08 makeover, with wide sidewalks and a tree-lined median.
* Build a traffic oval at South Capitol, Potomac, Q, as the gateway to a new arched bascule-design Douglass Bridge that would have wide "multi-use trails" (i.e., sidewalks!) in both directions. The existing bridge would be demolished, after the new bridge is built somewhat downriver of the current location.
The Executive Summary (220 MB PDF) gives a good overview of the FEIS and preferred alternative (as it should!), but I also suggest wandering through the Chapter 2: Alternatives section, especially if you came to the neighborhood or JDLand after 2008 and didn't get to follow along during the EIS process, or if you're interested in the additional plans for east of the river, which I'm going to leave to others to discuss. My previous posts on all of this may be of interest as well. If you're wanting to see some of the earlier studies referenced in the FEIS, there are links to them at the top of my South Capitol Street project page.
How much would this all cost? The preferred alternative is priced in this final EIS at $806 million (not billion! yeesh) in FY 2014 dollars. (New bridges are expensive, you know.)
(I know that this is a very quick overview of a big study and plan, but there will be plenty of time to talk more about it, especially with the upcoming public meetings.)
Comments (2)
   
 
 More About South Capitol St.

JDLand.com Home

Comments

John says: (4/18/11 6:13 PM)
Um, $806 *million*?


JD says: (4/18/11 6:20 PM)
Argh. Thanks. Fixed. Frickin' server issues have me totally frazzled.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

202_cyclist on Yards West Zoning: Honorable Mention Tower Crane Update: A tower crane was installed this past week...
JD on Yards West Zoning: There was a homicide on Saturday in the general vicinity of 5th and Virginia. Th...
202_cyclist on Yards West Zoning: Quit the gun play, people. https://mobile.twitter.com/DCPoliceDept /status/1053...
CJBabyDaddy on Yards West Zoning: What’s next? JDLand&1/2?
malatesta on Yards West Zoning: No matter what anyone says, I'm calling it "Qwandor the Dragon Street"...
B in DC on Whole Foods: JD, several folks requested that in the EIS process but were told that it was ou...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
900 B/O 5TH ST SE   HOMICIDE
Murder I
 10/20/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/20/18
1000 B/O 1ST ST SE   THEFT
Theft 2nd Degree (theft From Building)
 10/19/18
400 B/O M ST SE   THEFT
Shoplifting
 10/17/18
100 B/O N ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/17/18
700 B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 10/10/18
50 M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 10/08/18
1100 B/O 10TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/07/18
100 B/O M ST SE   ROBBERY  10/05/18
700 B/O L ST SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 10/04/18
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (theft From Building)
 09/28/18
1100 B/O 1ST ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/27/18
100 B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 09/26/18
100 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/26/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 09/26/18
1100 B/O 5TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/24/18
150 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 09/22/18
700 B/O L ST SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 09/22/18

Recent Issued Building Permits Archive  
1100 2ND PL SE   
10/12/18 
null / DONNA G GRAHAM
AH1900071 / CONSTRUCTION
WR #3585809 - M.ALLEN / A.PRICE - 1100 2ND PLACE SE - PEPCO CREWS WILL BE SPLICING CABLES AT NIGHT STARTING 10 / 15 / 18 UNTIL 11 / 2 / 18 FROM 10:00 PM TIL 7:00AM MONDAY THROUGH SUNDAYS
1346 4TH ST SE   
09/28/18 
ALAN OWINGS / ROBERT HENRY
AH1801345 / CONSTRUCTION
After Hours Permit for 10 / 08 / 2018 to perform construction work with the below activities: Interior Operations: 7AM - 7PM - ADVANCED NOTICE TO RESIDENTS, OPERATION CONTACT PERSON ON SITE TO ADDRESS ANY UNEXPECTED NOISE ISSUES BEFORE 9:00AM WITH CONTACT NAME AND TELEPHONE. Exterior Operations: 9AM-7PM - NO EXTERIOR ACTIVITY, TRAFFIC, NOISE GENERATION BEFORE 9am WITH ON SITE OBSERVANCE. ...
   
10/09/18 
FC 1346, LLC / null
E1900300 / SUPPLEMENTAL
   
10/18/18 
FC 1346, LLC / DFM DEVELOPMENT SERVICES, LLC
B1809670 / CONSTRUCTION
Parcel O-2 at the Yards. Revision to Permit B1610576 for installation of flood wall on 5th Street, SE, the reduction of roadway width, and widening of sidewalk to provide adequate pedestrian clear space between flood wall and edge of tree pit. TPR
2 I ST SE   
09/25/18 
MCDONALDS CORPORATION / TAMIKA STATON; OTIS
EN1802612 / SHOP DRAWING
Install 1 New G2S Elevator - 4000LBS @ 350FPM
   
09/25/18 
MCDONALDS CORPORATION / TAMIKA STATON; OTIS
EN1802611 / SHOP DRAWING
Install 3 new G2S Elevators - 3500LBS @ 350FPM
   
09/26/18 
MCDONALDS CORPORATION / null
E1811060 / SUPPLEMENTAL
   
10/09/18 
CRESECENT CAPTIAL VIEW / null
P1900223 / SUPPLEMENTAL
   
10/17/18 
MCDONALDS CORPORATION / DONNA G GRAHAM
AH1900080 / CONSTRUCTION
WR #3573836 - M.ALLEN / BRUNO - WARD 6 - 20003 - PEPCO CREWS WILL BE WORKING #2 I ST SE - MAY NEED TO BLOCK "I" STREET ON OCCASION TO INSTALL NETWORK TRANSFORMERS AND INSTALL AND SPLICE CABLES - CREW WILL BE WORKING AT NIGHTS DURING THE WEEK (MONDAY-FRIDAYS) FROM 9PM TIL 7AM - PEPCO CREWS WILL ALSO BE WORKING SATURDAY AND SUNDAYS FROM 6AM TIL 6PM - WORK IS ONGOING
4 I ST SE   
10/09/18 
CRESCENT COMMUNITIES / null
P1900221 / SUPPLEMENTAL
328 K ST SE   
09/27/18 
MARK BARRETT / null
E1811075 / SUPPLEMENTAL
   
10/04/18 
MARK BARRETT / BJORN FALK
SOL1800999 / CONSTRUCTION
Installation of a 5.559kW solar PV system. Roof mounted, 17 panels with integrated microinverters.
401 L ST SE   
10/11/18 
MICHAEL R BRICKMAN / FLOYD H. FURR
P1900299 / SUPPLEMENTAL
   
10/11/18 
MICHAEL R BRICKMAN / DARIUS LYVERS 703-491-1234
M1900108 / SUPPLEMENTAL
300 M ST SE   
09/25/18 
FEDERAL CENTER LP / null
E1811000 / SUPPLEMENTAL
   
09/25/18 
FEDERAL CENTER LP / null
E1811001 / SUPPLEMENTAL
   
09/25/18 
FEDERAL CENTER LP / null
E1810999 / SUPPLEMENTAL
400 M ST SE   
10/18/18 
CAPPER SENIOR 11 LIMITED PARTNERSHIP / null
E1900650 / SUPPLEMENTAL
1111 NEW JERSEY AVE SE   
10/17/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
E1900581 / SUPPLEMENTAL
79 POTOMAC AVE SE 1ST FL   
10/03/18 
RIVERFRONT HOLDINGS I LLC / null
P1900101 / SUPPLEMENTAL
71 POTOMAC AVE SE   
09/28/18 
FORIDA ROCK PROPERTIES INC / BARR CONCRETE
AH1801325 / CONSTRUCTION
After hours to pour concrete with pump truck 9 / 28 / 2018 to 10 / 28 / 22018 from 11pm to 7am
   
10/04/18 
FORIDA ROCK PROPERTIES INC / BARR CONCRETE
AH1900029 / CONSTRUCTION
Afterhours to pour concrete with pump truck saturday 10 / 06 / 2018 from 12am to 7am
79 POTOMAC AVE SE   
10/04/18 
RIVERFRONT HOLDINGS I LLC / null
M1900054 / SUPPLEMENTAL
201 TINGEY ST SE   
10/09/18 
JBG/SEFC 170 LLC / DONNA G GRAHAM
AH1900051 / CONSTRUCTION
WR #3566756 - M.ALLEN / BRUNO - 201 TINGEY ST SE - PEPCO CREWS WILL BE INSTALLING NETWORK TRANSFORMERS AND INSTALLING CABLES - PEPCO WILL HAVE TO SHUT DOWN 3RD ST BETWEEN WATER ST & TINGEY ST SE TO SET TRANSFORMERS ONLY - WORK WILL BEGIN 10 / 12 / 18 THROUGH 11 / 30 / 18 - MONDAY THRU FRIDAYS FROM 10PM TIL 8AM AND SATURDAYS AND SUNDAYS FROM 6AM TIL 6PM
227 TINGEY ST SE   
10/09/18 
FOREST CITY WASHINGTON / DFM DEVELOPMENT SERVICES, LLC
AH1900056 / CONSTRUCTION
Yards Parcel L-2. Afterhours permit for follow-up test run of the precast concrete façade panel installation. Work to take place 7pm on 10 / 10 to 7am on 10 / 11.
   
10/15/18 
GONE YARD HOTEL OWNER LLC / MICHAEL ERIC CAMPBELL 703-631-2711
FB1900011 / SUPPLEMENTAL
NO. TO BE INSTALLED (2) GROSS RATING: 999999 BTU / HR NATURAL GAS STEAM PRESSURE 160 PSI OUTPUT: 960,000 BTU / HR
   
10/15/18 
GONE YARD HOTEL OWNER LLC / MICHAEL ERIC CAMPBELL
UP1900012 / SUPPLEMENTAL
   
10/17/18 
UNITED STATES OF AMERICA / DFM DEVELOPMENT SERVICES, LLC
AH1900079 / CONSTRUCTION
Yards Parcel L-2. Afterhours permit for the purpose of installing precast concrete façade panels. Work to take place 7PM to 7AM, 10 / 22 through 11 / 3.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.