Since January, 2003
            
 Page Through from Before to After

Michael Perkins at GGW got his hands on the draft version DDOT's 2010 Ballpark District Performance Parking Report, and while I'll leave it to him to handle the in-depth discussion of pricing and meter use in Near Southeast as well as other neighborhoods, there are a few action items in the report that might be of general interest (you should read all 31 pages if you want the nitty-gritty).
Now, this is a draft report, but assuming it becomes final...:
Revenues from the parking program have been able to provide $812,100 for "non-automotive transportation improvements" in 2011, which will include a new Capital Bikeshare location at the Yards Park and $135,000 for a new fence along New Jersey Avenue by the railroad tracks (presumably it won't hide the "Water Pylons" public art coming to the freeway underpass). There will also be two or three other new bikeshare stations somewhere in the Ballpark District parking zones (Near Southeast, Southwest, and southern Capitol Hill), but those haven't been announced.
There will also be a $70,000 grant to partially fund a Capitol Riverfront BID Transportation Study, which the page 25 of the report says will happen during this fiscal year and will look at:
* The need for additional traffic signals and stop signs based on pedestrian and vehicular patterns (and recent accidents);
* Neighborhood traffic circulation patterns including one way street circulation and freeway access and turning movements onto the freeway frontage roads;
* How the CSX tunnel reconstruction will impact traffic flow and SE/SW freeway access/egress;
* Existing and future parking demand and the proposed parking supply to meet that demand;
* On street parking strategies and supply for commercial, residential and visitor populations;
* Optimum Circulator routes and hours of operation;
* Recommended routes for bike lanes that tie into the Riverfront Trail system;
* The optimum route for a streetcar line in the M Street right of way and how it would service the Buzzard Point subdistrict; and
* How M Street is designed and works as a multi-modal transit corridor while exhibiting a high quality of design in the public realm.
Gosh, I'm just not sure if residents will be interested in any of these! If perchance a reader or two might have an idea or data point for the above items, feel free to discuss in the comments.
Note that this study doesn't quite seem to match the overarching Near Southeast/Southwest combined traffic study that got some discussion late last year, but perhaps there's more going on than what's mentioned in the DDOT report.
DDOT is also proposing that non-gameday parking rates at the multispace meters between South Capitol and 2nd Streets from the freeway to M Street go up to $6 for three hours (first hour $1.50, second hour $2.50, third hour $3). Plus, the boundaries of the parking zone will move eastward to 11th St. SE from 9th St.
By the way, if you have a fab idea for how some of the proceeds from the parking revenue can be spent on the aforementioned non-automotive transportation improvements, you can submit a written proposal to DDOT (further information on page 26 of the report). And if you want background on how the Performance Parking Pilot came into existence back in 2008, my Stadium Parking page can help with that.
Comments (3)
   
 
 More About parking

JDLand.com Home

Comments

Andrew in DC says: (3/24/11 3:09 PM)
"first hour $1.50, second hour $2.50, third hour $3" ... is $7, not $6 :)


JD says: (3/24/11 3:13 PM)
Yup, but thankfully that's DDOT's error and not mine. :) Guess that's why it's a DRAFT!



Rick says: (3/29/11 2:16 PM)
Perhaps some of the money could be used to study abuse of the Visitor Parking Passes each house gets - ever wonder why some of the passes have faded in the sunlight?

Also, DDOT staff said their analysis of the parking program revealed few if anyone was parking and therefor paying the meter along Virginia Ave north of the freeway between 6th and 5th SE. They indicated the meter would be removed and the block returned to Zone 6 residential parking as it had always been. This was almost a year ago, but the meter and signs remain.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

VelocityChris on I'm Dreaming of: The description and picture of the Detroit-style pizza sounds/looks just like th...
JD on I'm Dreaming of: Longtime readers may remember the many trips with Mr JDLand to Michigan, where h...
dcgent on I'm Dreaming of: Detroit-style pizza coming to undisclosed navy yard location https://dc.eater.c...
Westnorth on I'm Dreaming of: XO sauce is fish-based, as with many Cantonese sauces: https://en.wikipedia.org/...
NavyYardGuy on I'm Dreaming of: @hamburgular --I had the XO spaghetti last week too VERY fishy taste -- they sai...
Hamburglar on I'm Dreaming of: I took my wife over to try out ABC Pony for dinner. Be careful with the SPAGHET...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
No records added or modified in the past two weeks.

Recent Issued Building Permits Archive  
1402 1ST ST SE   
11/25/19 
UNITED STATES OF AMERICA / DAVID C POSTLEWAITE
SB1900412 / CONSTRUCTION
Parcel G2:WSP will complete four borings up to the deepest potential subgrade elevation (approx. 32 ft. bgs). The proposed boring locations would be in the four quadrants of Parcel G2 to check for spatial variability in contaminant concentrations. WSP will collect and analyze three soil samples from each boring from depths corresponding to potential subgrade elevations (i.e. 10-12 ft. bgs, 20-22 ...
1212 4TH ST SE   
11/25/19 
FC 1212 LLC / TAMIKA STATON; OTIS
ER2000409 / SHOP DRAWING
Replace governor car #2 - Part #: TBA20641H6 Replace hoist belts #1 and #4 - Part #: SB0003119
1300 4TH ST SE   
11/15/19 
ASANA PARTNERS / DEBRA MARSHALL; THE DONOHOE COMPANIES INC
B2001773 / CONSTRUCTION
ADD EXTERIOR DOOR, ADD INTERIOR DOOR , ANY RELAYED,ELECTRICAL,PLUMBING, RELOCATING UNBUILT APPROVED NON LOAD BEARING FIRE RATED PARTITIONS @ FIRST FLOOR APPROVED UNDER PERMIT #B1711970. ATTACHED
   
12/06/19 
ASANA PARTNERS / S.A. COMUNALE; S.A. COMUNALE
P2001954 / SUPPLEMENTAL
1346 4TH ST SE   
12/06/19 
KAITLYNN MATTEO / W. SAKIE - BHAR; W. SAKIE - BHAR; NA
SG2000117 / CONSTRUCTION
Install one set of non illuminated sign on to existing store front building
300 M ST SE   
11/11/19 
FEDERAL CENTER LP / null
P2001215 / SUPPLEMENTAL
861 NEW JERSEY AVE SE   
11/15/19 
CSX TRANSPORTATION INC / ERICKA CLARK; DGS CONSTRUCTION
TC2000008 / CONSTRUCTION
(2) tower cranes
   
11/26/19 
GREYSTAR GP I I, LLC / KIM MITCHELL; KIM MITCHELL
FD1900040 / CONSTRUCTION
TWO BELOW GRADE PRKING LEVELS, CONCRETE FOUNDATION WALLS, SLAB ON GRADE, COLUMNS ELEVATED DECKS UP TO GRADE WITH UNDERGROUND UTILITIES (MECHANICAL, PLUMBING, ELECTRICAL)
   
12/05/19 
MIKE ALLEN / JANE MCCRAY
AH2000244 / CONSTRUCTION
WO# 1611441 - Mike Allen / P. Helgeson. Pepco to install network transformer
1111 NEW JERSEY AVE SE   
11/15/19 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / TANYA HILL; THYSSENKRUPP
ER2000366 / SHOP DRAWING
REPLACE EXISTING 8MM WORN HOIST CABLES WITH LIKE IN KIND ON ELEVATOR #4. WORK TO ALLOW UNIT TO BE RETURNED TO SERVICE.
1299 NEW JERSEY AVE SE   
11/12/19 
BROOKFIELD DEVELOPMENT / JUSTIN BELLOW
BP2000489 / POST CARD
125 O ST SE   
11/25/19 
DISTRICT OF COLUMBIA / DAVID C POSTLEWAITE
SB1900411 / CONSTRUCTION
WSP will complete three borings up to the deepest potential subgrade elevation (approx. 32 ft. bgs). WSP assumes that borings will not be installed inside the fleet maintenance facility due to access restrictions imposed by DC Water. The proposed boring locations form an ā€˜Lā€™ shape around the eastern and southern sides of the fleet maintenance facility. WSP will collect and analyze three soil samp...
71 POTOMAC AVE SE   
12/06/19 
MPR REALTY / BOB BIROONAK; BOB BIROONAK; ART DISPLAY CO
SG2000099 / CONSTRUCTION
One building name MAREN Two set of address numbers all signs are non-illuminated
201 TINGEY ST SE   
11/14/19 
BROOKFIELD PROPERTIES / DFM DEVELOPMENT SERVICES, LLC
AH2000197 / CONSTRUCTION
Afterhours work at Tingey Square Project. The work performed will be forming, prepping and paving at Tingey Square park. Friday and Saturday the 15th & 16th, from 7PM to midnight. If required, Sunday the 17th from 7AM to 3PM. ANC Support provided. Associated Permit Include PA328164-R1 and PA10760162.
227 TINGEY ST SE   
12/02/19 
FC 227 LLC / KAYLA SHATTUCK; BROOKFIELD PROPERTIES MANAGEMENT LLC.
RW1900122 / CONSTRUCTION
Construction of new retaining wall located between Canal Street St and Third Street, SE.
300 TINGEY ST SE   
12/04/19 
FC BOILERMAKER LLC / ROBERT S. WATTS; ROBERT S. WATTS
E2002289 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2019 JD.