The Usual Suspects gathered today at Second and M streets, SE, for Canal Park's ceremonial groundbreaking (at last). Mayor Fenty, Ward 6 council member Tommy Wells, Deputy Mayor Valerie Santos, Christopher Smith of W.C. Smith, and Chris Vanarsdale of the Canal Park Development Association each said a few words, with the words "school buses" being uttered a number of times as speakers talked about the previous life of these three blocks in the middle of Near Southeast. [The mayor even went off-script during his remarks to ask a startled neighborhood blogger how many photos of school buses are in the blog's archive; "about a thousand," came the response, which sounded flip but which is probably true.]
Here is a quick assemblage of photos from the event; if you want to know more about the park (or see old photos of school buses), my Canal Park project page is worth peeking at, as is the official Canal Park web site. Construction is expected to take 12-14 months, so look for the park to open in Fall of 2011.
For those who haven't been following along, Canal Park will stretch from I to M streets SE along the two parts of Second Street--some people may know this location as the open field across from Subway and Five Guys, about three blocks northeast of Nationals Park. The park has been designed to be a showcase of low-impact design and "green" features, including a sizeable stormwater management component. The southern block, across from the US Department of Transportation headquarters, will have a large plaza, a "significant water feature" that will transform into an ice skating rink in winter, and a large two-level pavilion that will be home to a cafe and observation area. The middle block has a rain garden, a children's play area, a small performance stage, and an open lawn. The northern block, the "most pastoral of the three," will have an open lawn, and the slight grade of the block as it slopes upward toward I Street has allowed the designers to envision this as an informal amphitheater, for events like summer movie nights and whatnot. There is also a "linear rain garden" that runs along the eastern edge of the park's three blocks. (Note that K and L streets will still be open to traffic, though there will be well-marked crosswalks.)
[PS: And, yes, I absconded with one of the shovels. But it was donated, not stolen!]
UPDATE: Here is the press release from the mayor's office on the project.
Comments (10)
   
 
 More About Canal Park
 All posts: Canal Park

JDLand.com Home

Comments

GW says: (8/31/10 12:36 PM)
"...so look for the park to open in Fall of..." *2011*


JD says: (8/31/10 12:37 PM)
Oops, thanks.


Richard says: (8/31/10 1:46 PM)
How about that shout out to the Blogger by
Mayor Fenty...and his use of Near Southeast in
his remarks!


JD says: (8/31/10 1:54 PM)
It will be a long, lonely, and ultimately fruitless crusade of mine to convince people that this neighborhood's name truly is Near Southeast. And yes, I did notice that the Mayor said it. :-)


Hillad says: (8/31/10 2:53 PM)
And what are all those poor dogs going to do in the evenings now?


MJM says: (8/31/10 4:56 PM)
Got an e-mail this morning - not too sure if it is true or not - on the VA Ave dog park. The was being planned for a while but if the e-mail is true, there is a fence up. Will check it out around 6 to see if it is true.


MJM says: (8/31/10 7:50 PM)
Yup, its a dog park, just waiting on the gates to be put in - supposedly by the end of the week. Its a good size area near the spay/neuter clinic.


Sophia Monster says: (9/1/10 3:01 PM)
Isn't this the 10th groundbreaking they've had for this park? Maybe I'm just thinking of other Near Southeast projects. In either case, they might want to start thinking about reusing some of those shovels.


JD says: (9/1/10 3:30 PM)
Nope, this is the only groundbreaking Canal Park has had. Back in 2007 they had a ceremony to honor a big check the city received from JBG Cos. to help fund both it and Diamond Teague Park.

Actual shovels-in-the-ground groundbreakings since I've been watching have been Nationals Park, Capper, Onyx/100 M, Yards Park, Diamond Teague Park, and now Canal Park.


JoeNDC says: (9/2/10 8:10 AM)
Why yes Sophia Monster, you are correct. They should reuse those shovels. In fact they were looking for an extra that was earmarked for their next groundbreaking. Alas, it disappeared. Rumor on the street from those in attendance said they saw a woman with a camera around her neck slowing, ever so quietly slinking away, stage right with what appeared to be a shovel. Strange, very strange indeed. Hmmmmm.:)

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

CJBabyDaddy on Retail Roundup: So, when construction of the Parcel I “skybridge” apartment building gets to the...
JD on Retail Roundup: Yes, right the first time! [image]
Jscott280 on Retail Roundup: Sorry Parcel i lol
Jscott280 on Retail Roundup: Spoke with a parking lot attendant at Parcel I after I saw all monthly parking w...
AUshutterbug on Anchovy Social Opens: @Sasq thanks! We are anxious too. The "flood" happened 3 days before t...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
UNIT B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/15/20
400 B/O M ST SE   ASSAULT WITH A DANGEROUS WEAPON  02/08/20
300 B/O TINGEY ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/02/20
700 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 02/01/20
600 B/O VIRGINIA AVE SE   ASSAULT WITH A DANGEROUS WEAPON  01/29/20
1300 B/O 4TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 01/27/20
1100 B/O 8TH ST SE   BURGLARY
Burglary Two
 01/25/20
303 VIRGINIA AVE SE   ROBBERY  01/25/20
400 B/O M ST SE   THEFT
Shoplifting
 01/23/20
1255 1ST ST SE   THEFT
Theft 2nd Degree (theft From Building)
 01/19/20

Recent Issued Building Permits Archive  
909 4TH ST SE   
02/12/20 
MEREDITH FASCETT / null
E2004655 / SUPPLEMENTAL
1300 4TH ST SE APT 214   
02/03/20 
null / NA NA NA
EHOP20983190 / HOME OCCUPATION
900 5TH ST SE   
01/24/20 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / WILLIAM B. CRIST; WILLIAM B. CRIST
E2003968 / SUPPLEMENTAL
1021 5TH ST SE   
02/13/20 
KEVIN WILLIAMS / KEVIN WILLIAMS; KEVIN WILLIAMS
B2005053 / CONSTRUCTION
Apply for building permit to have final closing inspection for permit #B1602481 & B1602513 per inspector inspection report since these permits has expired.
82 I ST SE   
01/27/20 
GDV EYE STREET LLC / null
P2003302 / SUPPLEMENTAL
   
01/27/20 
GDV EYE STREET LLC / null
M2001261 / SUPPLEMENTAL
100 I ST SE APT T-13   
01/25/20 
null / NA NA NA
EHOP20960826 / HOME OCCUPATION
150 I ST SE   
02/14/20 
SQUARE 737 LLC / JASON D DORRIS
AH2000818 / CONSTRUCTION
Construction of a new 13 story apartment building with three below grade parking levels, 1st floor retail, and amenity areas; 375 units and 181 parking spaces. To include mechanical, electrical, plumbing, elevators and structural work.
250 M ST SE   
02/14/20 
SQUARE 769 LLC / null
P2003901 / SUPPLEMENTAL
800 NEW JERSEY AVE SE   
01/30/20 
NEW JERSEY AT H LLC / MICHELLE GABBITAS
AH2000649 / CONSTRUCTION
Manhole rehabilitation on New Jersey, 2nd St and M St SE to repair 3 existing sewer manholes in DDOT ROW. Work will all be done through existing manholes (trenchless) and include lining, rebuilding and bypass of existing manholes.
861 NEW JERSEY AVE SE   
01/28/20 
DISTRICT OF COLUMBIA / JANE MCCRAY
AH2000647 / CONSTRUCTION
Pepco contractor, W.A.Chester, will be splicing cable on 02 / 01 / 2020 - 02 / 28 / 2020, from 9 PM - 7 AM.
1275 NEW JERSEY AVE SE 20003   
02/14/20 
BROOKFIELD PROPOERTIES / TIM GOOD
AH2000849 / CONSTRUCTION
After hours to conduct work on 1275 New Jersey Ave SE on the upcoming holiday, Presidents Day, February 17, 2020. Operations would include below grade concrete and waterproofing activities with access limited to N Street. This permit would not include extended work hours beyond the normal 7am to 7pm period.
1275 NEW JERSEY AVE SE   
01/29/20 
US GOVERNMENT / null
E2004153 / SUPPLEMENTAL
   
01/29/20 
MILLER AND LONG / WILLIAM MOORE
AH2000659 / CONSTRUCTION
Afterhours to pour concrete with pump truck from 11pm to 7am from 2 / 6 / 2020 to 3 / 6 / 2020
   
01/30/20 
UNITED STATES OF AMERICA / VINCENT J. BROWNING; VINCENT J. BROWNING
P2003449 / SUPPLEMENTAL
1-Oil / Sand interceptor
   
01/30/20 
US GOVERNMENT / null
E2004202 / SUPPLEMENTAL
   
02/07/20 
MILLER AND LONG / WILLIAM MOORE
AH2000699 / CONSTRUCTION
Afterhours to put up towercrane with mobile crane saturday 2 / 8 / 2020 and 2 / 9 / 2020 from 5am to 1159pm
1322 PATTERSON AVE SE   
02/13/20 
JOINT BASE ANACOSTIA BOLLING - UNITED STATES NAVAL OBSERVATORY SI / TONYA HARRIS; TONYA HARRIS; TBD
BCIV2000046 / CONSTRUCTION
***FEDERAL PROPERTY*** PROJECT WILL CONSIST OF DREDGING THE EXISTING RETENTION POND AND INSPECTING AND CLEANING THE OUTLET CONTROL STRUCTURE (S1) LOCATED ON THE UNITED STATES NAVAL OBSERVATORY TO REMOVE SEDIMENT ACCUMULATION. CONTRACTOR SHALL AVOID THE CLEARING OF VEGETATION ON POND EMBANKMENTS AND SURROUNDING AREAS SO AS TO KEEP RESTORATION AND REPLANTING TO A MINIMUM.
71 POTOMAC AVE SE   
02/13/20 
MRP REALTY / JAMES VANEGAS
AH2000681 / CONSTRUCTION
Perform interior and exterior construction activities. New construction 14-story new residential multi-family building.
79 POTOMAC AVE SE   
01/23/20 
RIVERFRONT HOLDINGS I LLC / ; W&M NA
B2003750 / CONSTRUCTION
320 SQ Ft metal canopy extension to exterior canopy. Existing canopy is standalone structure covering an outdoor bar area.
227 TINGEY ST SE   
01/23/20 
FFC 227 / ANDY MCKELVEY; ANDY MCKELVEY
SP1900050 / CONSTRUCTION
Install in-ground, gunite swimming pool on 11th floor of new construction. Scope includes gunite pool shell, finishes, and closed pool circulation system. All fresh water plumbing, sewer, electrical and mechanical work / connections by others. this permit is for a new commercial swimming pool
   
02/12/20 
GONE YARD HOTEL OWNER LLC / BOB BIROONAK; BOB BIROONAK
SG2000048 / CONSTRUCTION
one double face illuminated blade sign
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.