Thanks to one of the National Capital Planning Commission's fabulous documents, we're starting to get first hints of plans by the Cohen Companies for what they are describing as a three-building, 815,000-square-foot office, hotel, retail project on the very eastern end of M Street, nestled between Boathouse Row and the CSX tracks east of Maritime Plaza. It's so early in the process that it's not even on Cohen's New Projects page, but City Paper's Housing Complex blog has learned that the company will be putting together a planned unit development application to the Zoning Commission "over the next six to nine months." (No financing is lined up, though, so don't look for digging to start anytime soon.) See the NCPC document for some early drawings and some basic information on how they envision the offerings of the three buildings.
(Cohen Companies, by the way, is the developer of Velocity.)
Back in 2003-ish, there were plans for this site to be a townhouse development (see page 15), but those never got off the ground partly because of zoning issues, which then begat an attempted rezoning of the area in 2004 that failed. But rezoning of the site will have to be back in the forefront when this project's PUD application hits the zoning committee, since the space is still zoned "M" (industrial).
The project is in front of NCPC because of Cohen's request to close "paper street" segments of Virginia Avenue, M, and 14th streets. This is a part of a settlement between 1333 M Street, SE, LLC and the city from a lawsuit over waterfront development in South*west*, where the Cohen Companies are agreeing to release their claims in exchange for three small pieces of government land at 1333 M SE as well as the city's support in requesting the street closures. (The street closures themselves have been approved by the city council as bill B18-0572, and are expected to become law later this month.)
The NCPC is objecting to the street closures; and thankfully Greater Greater Washington has been writing in detail on the case, so I'm just going to throw it over to them for all the nitty gritty, because it's way out of my league. (Read also this GGW entry about connecting this area to the neighborhoods to its north if/when the remnants of the freeway to Barney Circle are removed.) But, again, the NCPC staff recommendation report is also a great read for not only the NCPC's concerns but also for the history of the area under review and other details. The NCPC board is meeting this afternoon, and we'll see what comes out of the session (I assume GGW will be hot on the trail).
If you've never ventured down that way, my East M page has a few not-particularly-current photos of the location (I don't get there very often myself), along with more images of Boathouse Row. When the project begins to wind its way through the zoning process, I'll get more on the ball. The city's 2009 Boathouse Row Planning Study is also a good spot to learn more about the area.
UPDATE: Thanks to commenter Evan, I'm reminded that I should have included the additional information that, because this is part of the old Washington Gas (and I think Steuart Petroleum) site, there are some serious remediation issues to be addressed, which are mentioned both by Ron Cohen on page 25 of this 2003 ZC transcript and on page 19 of this 2004 ZC transcript (saying that the contaminated soil is 11 feet down). Remediation is also mentioned in the 2009 Boathouse Row Planning Study and in this EPA document (under "Washington Gas and Light"). Oh, and the EPA's 1999 record of decision on what cleanup remedies would be needed. It should be noted that both Maritime Plaza buildings were completed after this document. (This is all before my time, so I'm researching on the fly.)
UPDATE II: Here's a WBJ article (subscribers only for 7 days) on the NCPC angle; it also reminds that, outside the monumental core of the city, NCPC's rulings are purely advisory.
Comments (4)
   
 
 More About 1333 M

JDLand.com Home

Comments

evan says: (5/6/10 1:24 PM)
Isn't that the old Washington Gas site?? If so, then it's HEAVILY polluted. They did coal gasification on that site for a really long time, and the pollution is incredibly extensive. It should be an EPA superfund site.

The District has been fighting with Washington Gas for years to get Washington Gas to pay for the remediation--and it won't be cheap!

I CANNOT believe that anyone would get the green light to develop on that site or would want to...


JD says: (5/6/10 1:36 PM)
You're right, and the remediation is mentioned in some of the zoning documenst from 2005 (when they were talking about rezoning the area).


c says: (5/7/10 9:08 AM)
today's post express, page 21 profiles our hood


JD says: (5/7/10 2:46 PM)
That Express article was originally published in March, don't know why they printed it again:

link


Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2018!
 Recent Posts

JES on Watching the Neighborhood: This is awesome. I wonder what a similar post looking up Half from the CF gate w...
RMP on Watching the Neighborhood: This is amazing. Thank you for all the hard work over the years to make this pos...
conngs0 on Watching the Neighborhood: Remarkable! It's been a pretty amazing transformation over the years even from ...
Gamble Rogers on Watching the Neighborhood: This is amazing work, JD.
202_cyclist on A Quick Hard: FOUND: keys for a Mini Cooper. My wife and I found a pair of keys this morning...
Westnorth on A Quick Hard: I hope Brogan isn't related to infamous Elon Musk hanger-on Brogan BamBrogan; if...
  
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
800 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 06/18/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 06/16/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 06/11/18
1100 B/O 8TH ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 06/10/18
UNIT B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 06/09/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 06/06/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 06/04/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 06/04/18
700 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 05/29/18
1000 B/O NEW JERSEY AVE SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 05/28/18
1100 B/O 10TH ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 05/26/18
1100 B/O 9TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 05/25/18
UNIT B/O I ST SE   THEFT
Theft First Degree (all Other Larceny)
 05/25/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 05/22/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 05/21/18
300 B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 05/19/18

Recent Issued Building Permits Archive  
1018 3RD ST SE   
06/06/18 
DAVID A LEINER / SCOTT STERL
F1800474 / CONSTRUCTION
REPLACEMENT OF AN EXISTING CHAIN LINK FENCE TO A WOODEN FENCE 6FT. TALL.
1212 4TH ST SE   
06/06/18 
null / THAIS NA PEACHER
EHOP18924304 / HOME OCCUPATION
101 H ST SE   
05/22/18 
SQUARE 737 LLC / null
M1802469 / SUPPLEMENTAL
   
05/23/18 
SQUARE 737 LLC / null
P1806213 / SUPPLEMENTAL
   
06/05/18 
SQUARE 737 LLC / JOHN SONNER 4438727277
E1807389 / SUPPLEMENTAL
   
06/06/18 
SQUARE 737 LLC / null
P1806501 / SUPPLEMENTAL
2 I ST SE   
05/22/18 
CRESCENT CAPITOL VIEW / null
E1807051 / SUPPLEMENTAL
   
05/31/18 
CRESCENT CAPITOL VIEW / null
E1807278 / SUPPLEMENTAL
   
05/23/18 
CRESCENT CAPITAL VIEW, LLC / ERICKA CLARK
TC1800034 / CONSTRUCTION
Renewal of tower crane permit #TC1700022 EXTENSION WILL EXPIRE ON 11 / 23 / 2018
202 M ST SE   
05/29/18 
null
E1807211 / SUPPLEMENTAL
   
05/29/18 
null
P1806323 / SUPPLEMENTAL
100 M ST SE   
06/05/18 
SQUARE 743 INC / ROBERT L HUNTER 703-404-0303
M1802631 / SUPPLEMENTAL
202 M ST SE   
05/31/18 
UNITED STATES OF AMERICA / null
P1806387 / SUPPLEMENTAL
300 M ST SE   
05/25/18 
FEDERAL CENTER LP / GARY BRENT; CARLOS DIAZ
SG1800308 / CONSTRUCTION
Install 2 illuminated wall signs and 1 temporary Banner - Sprint
   
06/01/18 
FEDERAL CENTER LP / SAM HOLLEN
B1809520 / CONSTRUCTION
INTERIOR RENOVATION TO 8TH FLOOR OFFICE SPACE. PARTITIONS, FURNITURE, MECHANICAL, ELECTRICAL AND LIFE SAFETY. NO PLUMBING OR STRUCTURAL. 860 SQUARE FEET. STRATEGIC INSIGHT
410 M ST SE   
05/30/18 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / SCOTT NICHOLS
AN1800023 / CONSTRUCTION
AT&T proposes to add three new antennas to an existing rooftop telecommunications facility.
800 NEW JERSEY AVE SE   
05/24/18 
SQUARE 737 LLC / null
P1806243 / SUPPLEMENTAL
861 NEW JERSEY AVE SE   
05/23/18 
CONSOLIDATED RAIL CORPORATION / NA CSX TRANSPORTATION INC.
AH1800974 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities. **TO EXCLUDE LEGAL HOLIDAYS**
1115 NEW JERSEY AVE SE   
05/22/18 
DONOHOE REAL ESTATE SERVICES / null
M1802478 / SUPPLEMENTAL
   
06/07/18 
DONOHOE REAS ESTATE SERVICES / null
E1807467 / SUPPLEMENTAL
1115 NEW JERSEY AVE SE 20003   
06/14/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / THOMAS P MCGUIRE 410-766-7463
E1807687 / SUPPLEMENTAL
   
06/14/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / THOMAS P MCGUIRE 410-766-7463
E1807698 / SUPPLEMENTAL
1115 NEW JERSEY AVE SE   
06/12/18 
GALLERY CAPITOL WATERFRONT PROPERTY LLC / null
P1806653 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
06/12/18 
SQUARE 742 LLC / CLIFFORD DIXON
B1807730 / CONSTRUCTION
REVISION: REVISE B1804348 5TH FLOOR OFFICE SPACE TO EXTEND THE OFFICE INTO ADDITIONAL SPACE TO CREATE A LARGER OPEN OFFICE
71 POTOMAC AVE SE   
05/30/18 
FORIDA ROCK PROPERTIES INC / ANKIT K SINGH
UT1800044 / CONSTRUCTION
Removal of an Underground storage Tank (UST) 7 feet in diameter and approximately 16 feet long (approximately 6,000 gallons). Suspected Fuel Tank. Tank is filled with water and soil. Tank will be cleaned, removed and disposed off as per the appropriate standards and requirements.
221 TINGEY ST SE   
06/05/18 
GONE YARD HOTEL OWNER LLC / MITCH PERMUY 7272100491
E1807017 / SUPPLEMENTAL
227 TINGEY ST SE   
05/25/18 
FOREST CITY WASHINGTON / MELISSA DIAZ
B1801871 / CONSTRUCTION
Yards Parcel L-2. New 11-story mixed use building with residential, retail on ground level, and underground parking garage. TPR
   
05/31/18 
FOREST CITY WASHINGTON / DANIEL P. THOMPSON
P1806388 / SUPPLEMENTAL
(2) Backwater valve
   
06/07/18 
UNITED STATES OF AMERICA / MICHAEL ERIC CAMPBELL 571-229-1360
M1802664 / SUPPLEMENTAL
Equipment Manufacturer Equipment Model AAON DOAS, RTU and AHU DAIKIN VRF and split systems DESERT AIRE LC06R7NFDDMLAERD
   
06/07/18 
FOREST CITY WASHINGTON / DANIEL P. THOMPSON
P1806553 / SUPPLEMENTAL
REVISION TO P1806388. IN LIEU OF 753 SINKS SHOULD READ 264 SINKS, 489 BASINS
300 TINGEY ST SE   
06/04/18 
FC BOILERMAKER LLC / ALBERT E. WILLIAMS 443-532-0991
M1802615 / SUPPLEMENTAL
   
06/04/18 
FC BOILERMAKER LLC / null
P1806437 / SUPPLEMENTAL
   
06/05/18 
FC BOILERMAKER LLC / CARLOS E. MONTES
P1806464 / SUPPLEMENTAL
355 WATER ST SE   
06/14/18 
UNITED STATES OF AMERICA / EDUARDO LOPEZ 2023884000
E1807680 / SUPPLEMENTAL
355 WATER ST ST SE   
06/13/18 
UNITED STATES OF AMERICA / KIMBERLY SPEED
TN1800127 / CONSTRUCTION
The Great Lawn at Yards Park will be the site of the California State Society Annual Summer Picnic. The contract specifies the licensee to obtain permits for tents and generators on the lawn. The large tent is 100 x 40 - which I have the Certificate of Flame Resistance), as well as a generator. I have the generator specifications from the distributor.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.