It's more than 100 pages of high finance and headache-inducing legalese, but nonetheless I've gotten my hands on the "Preliminary Official Statement" for what is expected to be a $29 million PILOT bond sale to fund a series of infrastructure improvements for future phases of the Capper/Carrollsburg redevelopment. (This is the document written for investors to help them decide whether or not to purchase the bonds.) If you want to know all about how these bonds are being structured (with monies from the Downtown TIF playing a part), this is the document for you. It also has some good background on the Capper project if you're just catching up.
But it also has a few tidbits on the current and projected path of some upcoming parts of the overall project, starting on page 19. Here are the items that are probably of most interest, with the usual caveats that no timeline is written in stone anymore:
* Financing for the second phase of Capitol Quarter is being negotiated and is expected to close in mid-2010. Development work would then begin in August, and vertical construction in November. (Phase 2 covers the blocks between Third and Fourth and I and M, and will contain 116 new for-sale townhouses and 47 public housing rental units.)
* All but five of the 121 CQ phase 1 townhouses have sold, and two of those are being held back as model units.
* Financing is "being negotiated" for the planned apartment building on the northern half of Square 882, the site that's been the subject of my recent posts on the Marines coveting the site as well. That financing is expected to close in late 2010 according to this document, with an expected completion date of the apartment building in April 2012.
This $29M bond sale is not the last one for Capper infrastructure; the city council approved a total of $55 million in bond funding back in 2006, and the document says that the city "expects" another bond issuance for the rest of the money, "though the timing of such issuance is currently uncertain" (page 10).
As for what exactly the monies will be funding, the document lays out the following (page 22), though this is for the entire $55 million, so it can't be said that this current $29 million offering will cover all this (which will bum out the people who see the phase "community center"). Some of this work would also happen on the streets surrounding Canal Park:
* Repairing and replacing underground water and utility lines;
* Repairing streets and streetscapes and adding landscaping;
* Demolishing the DPW building (and smoke stack!) at 900 New Jersey, relocating DPW's operations, environmental site remediations (remember, that site was operating as a trash transfer site as far back as 1905);
* Building I Street through to New Jersey Avenue; and
* Constructing the new community center at Fifth and K.
It's expected that the bonds will be "priced" this week, with the sale closing by the end of the month.
I hear rumors that DPW could be out of their site by next spring, as the search continues for a new home for their operations (and maybe is getting close to a resolution).
Comments (6)
   
 
 More About Capper

JDLand.com Home

Comments

incognito says: (3/22/10 3:45 PM)
It is subtle and wonky, but the canalparkdc.org website now has on their homepage the three dimensional model of the park as released by Studios architecture in their drawings. Uncertain how long ago this change was made but I do think it looks great. Now we just have to continue pushing for construction to begin asap and no later than the advertised September 2010.


bt says: (3/22/10 3:54 PM)
47 public housing rental units???? WHY? Aren't there enough? Are we encouraging people to be losers? I want to do nothing and live in a brand new housing community!! where do i sign up? what are the qualifications?


JD says: (3/22/10 3:58 PM)
The public housing component is the only reason why Capitol Quarter is being built in the first place. The entire redevelopment got a Hope VI grant from HUD to replace 700 units of public housing in a new development with the same 700 units plus another 800 market-rate units. 300 of the units were already built in Capper Seniors #1 and 400 M. The rest will be in the Capitol Quarter townhouses and in the 5 mixed-income apartment buildings.



Michael says: (3/22/10 4:25 PM)
Canal Park... little surprise that the Web site's link to the building schedule it broken )


Kenny says: (3/23/10 11:18 AM)
Isn't I Street already built to New Jersey Avenue? Or is my memory already failing me...


JD says: (3/23/10 11:19 AM)
Not from the east. I stops at Second/Canal, then starts again at New Jersey.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

RMP on Tidbits: @CJBabyDaddy it feels like a treat these days to get to use the crosswalk in fro...
CJBabyDaddy on Tidbits: @RMP: Brookfield retains control of some blocks that have yet to be turned over...
RMP on Tidbits: Who is responsible for the new block of Water between 4th and 5th? DDOT? Brookfi...
jdc on Tidbits: With build out around Yards Park nearing completion, I wonder if attention will ...
202_cyclist on Tidbits: Here are some photos of the new public space/park at the end of 4th Street that ...
202_cyclist on Tidbits: When we were walking along the river today we must have seen two dozen turtles a...
  
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
UNIT B/O I ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 04/21/19
400 B/O M ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 04/19/19
70 B/O I ST SE   ROBBERY  04/16/19
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 04/15/19
1500 B/O SOUTH CAPITOL ST   THEFT
Theft 2nd Degree (all Other Larceny)
 04/13/19
800 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 04/12/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 04/05/19
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 04/05/19
1500 B/O SOUTH CAPITOL ST   THEFT
Theft 2nd Degree (all Other Larceny)
 04/03/19
200 B/O I ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 04/02/19
200 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 04/02/19
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 03/30/19
1200 B/O VAN ST SE   BURGLARY
Burglary Two
 03/25/19
800 B/O 3RD ST SE   ASSAULT WITH A DANGEROUS WEAPON  03/25/19

Recent Issued Building Permits Archive  
1100 2ND PL SE   
04/10/19 
SQUARE 769N OWNER LLC / FRANK CAVANAGH; X
SG1900275 / CONSTRUCTION
Install one building sign
1331 4TH ST SE CU   
04/01/19 
FC 1331 LLC / null
P1905037 / SUPPLEMENTAL
1000 5TH ST SE   
04/09/19 
UNITED STATES OF AMERICA / TANYA HILL
B1906864 / CONSTRUCTION
***DGS REPLACEMENT OF EXISTING SINKS WITH NEW SINKS AND CABINETS AT THE DAYCARE SPACES. REVISION OF EXISTING WATER SUPPLY AND WASTE PIPES FOR NEW SINKS.
   
04/13/19 
UNITED STATES OF AMERICA / null
E1906382 / SUPPLEMENTAL
   
04/17/19 
UNITED STATES OF AMERICA / FRANKLIN T GAINES
P1905523 / SUPPLEMENTAL
1003 5TH ST SE   
04/19/19 
MICHIKO BONAWITZ / DOUGLAS IAN BONAWITZ
F1900293 / CONSTRUCTION
Put in an iron fence 3feet high and gate by R & F Metals.
150 I ST SE BASE   
04/09/19 
null
E1906206 / SUPPLEMENTAL
150 I ST SE   
04/01/19 
PEPCO UTILITY WORK / MIKE BOONE
AH1900707 / CONSTRUCTION
PEPCO-WR#3518247-ALLEN / POWER COMM-CREWS TO INSTALL TRANSFORMER / CABLE MON-SAT.
250 M ST SE   
04/15/19 
SQUARE 769 LLC / STEVEN CHEN
AH1900779 / CONSTRUCTION
Work Onsite Only - Emancipation Day
   
04/18/19 
BAKER DC LLC / CHRISTINE LONG
TC1900019 / CONSTRUCTION
Permit for Baker DC LLC to temp erect tower crane on private property
300 M ST SE   
04/01/19 
FEDERAL CENTER, LP / SAM HOLLEN
B1907517 / CONSTRUCTION
INTERIOR RENOVATION TO 2ND FLOOR OFFICE SPACE.  PARTITIONS, FURNITURE, MECHANICAL, ELECTRICAL AND LIFE SAFETY.  980 SQUARE FEET. ICI SERVICES
   
04/02/19 
FEDERAL CENTER, LP / SAM HOLLEN
B1907519 / CONSTRUCTION
INTERIOR RENOVATION TO 8TH FLOOR OFFICE SPACE.  PARTITIONS, FURNITURE, MEP AND LIFE SAFETY.  990 SQUARE FEET. ICI SERVICES
880 NEW JERSEY AVE SE   
04/19/19 
880 NEW JERSEY AVE LLC / JAMES W LASHER
E1906502 / SUPPLEMENTAL
1200 NEW JERSEY AVE SE   
04/15/19 
EARL MITCHELL / null
E1906389 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
04/09/19 
SQUARE 742 LLC / MICHAEL ZEARING
AN1900118 / CONSTRUCTION
Remove (3) (E) 2.5GHz RFS (APXVTM14-C-120) Panel Antennas with Associated Cabling Remove (3) (E) 2.5GHz Alcatel Lucent (TD-RRH8x20-2500) RRH's with associated cabling Contractor to verify existing mount and if necessary replace with 3.5" OD x 8' SCH. 40 Pipe per Sprint standards Install (3) (N) 2.5GHz Nokia Airscale MAA 64T64R 128AE B41 120 AAHC MIMO Antennas Install (3) (N) MIMO Mounting Br...
125 O ST SE   
04/18/19 
DISTRICT OF COLUMBIA / BILL SAUNDERS; TBD
B1908317 / CONSTRUCTION
ADD 1 RESERVE TANK TO CLEAN AGENT FIRE SYSTEM.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2019 JD.