It's more than 100 pages of high finance and headache-inducing legalese, but nonetheless I've gotten my hands on the "Preliminary Official Statement" for what is expected to be a $29 million PILOT bond sale to fund a series of infrastructure improvements for future phases of the Capper/Carrollsburg redevelopment. (This is the document written for investors to help them decide whether or not to purchase the bonds.) If you want to know all about how these bonds are being structured (with monies from the Downtown TIF playing a part), this is the document for you. It also has some good background on the Capper project if you're just catching up.
But it also has a few tidbits on the current and projected path of some upcoming parts of the overall project, starting on page 19. Here are the items that are probably of most interest, with the usual caveats that no timeline is written in stone anymore:
* Financing for the second phase of Capitol Quarter is being negotiated and is expected to close in mid-2010. Development work would then begin in August, and vertical construction in November. (Phase 2 covers the blocks between Third and Fourth and I and M, and will contain 116 new for-sale townhouses and 47 public housing rental units.)
* All but five of the 121 CQ phase 1 townhouses have sold, and two of those are being held back as model units.
* Financing is "being negotiated" for the planned apartment building on the northern half of Square 882, the site that's been the subject of my recent posts on the Marines coveting the site as well. That financing is expected to close in late 2010 according to this document, with an expected completion date of the apartment building in April 2012.
This $29M bond sale is not the last one for Capper infrastructure; the city council approved a total of $55 million in bond funding back in 2006, and the document says that the city "expects" another bond issuance for the rest of the money, "though the timing of such issuance is currently uncertain" (page 10).
As for what exactly the monies will be funding, the document lays out the following (page 22), though this is for the entire $55 million, so it can't be said that this current $29 million offering will cover all this (which will bum out the people who see the phase "community center"). Some of this work would also happen on the streets surrounding Canal Park:
* Repairing and replacing underground water and utility lines;
* Repairing streets and streetscapes and adding landscaping;
* Demolishing the DPW building (and smoke stack!) at 900 New Jersey, relocating DPW's operations, environmental site remediations (remember, that site was operating as a trash transfer site as far back as 1905);
* Building I Street through to New Jersey Avenue; and
* Constructing the new community center at Fifth and K.
It's expected that the bonds will be "priced" this week, with the sale closing by the end of the month.
I hear rumors that DPW could be out of their site by next spring, as the search continues for a new home for their operations (and maybe is getting close to a resolution).
Comments (6)
   
 
 More About Capper

JDLand.com Home

Comments

incognito says: (3/22/10 3:45 PM)
It is subtle and wonky, but the canalparkdc.org website now has on their homepage the three dimensional model of the park as released by Studios architecture in their drawings. Uncertain how long ago this change was made but I do think it looks great. Now we just have to continue pushing for construction to begin asap and no later than the advertised September 2010.


bt says: (3/22/10 3:54 PM)
47 public housing rental units???? WHY? Aren't there enough? Are we encouraging people to be losers? I want to do nothing and live in a brand new housing community!! where do i sign up? what are the qualifications?


JD says: (3/22/10 3:58 PM)
The public housing component is the only reason why Capitol Quarter is being built in the first place. The entire redevelopment got a Hope VI grant from HUD to replace 700 units of public housing in a new development with the same 700 units plus another 800 market-rate units. 300 of the units were already built in Capper Seniors #1 and 400 M. The rest will be in the Capitol Quarter townhouses and in the 5 mixed-income apartment buildings.



Michael says: (3/22/10 4:25 PM)
Canal Park... little surprise that the Web site's link to the building schedule it broken )


Kenny says: (3/23/10 11:18 AM)
Isn't I Street already built to New Jersey Avenue? Or is my memory already failing me...


JD says: (3/23/10 11:19 AM)
Not from the east. I stops at Second/Canal, then starts again at New Jersey.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2016!
 Top News
  

snakegriffin on Two-Year Change in: That's terrible. It doesn't help that there are constantly fire/police/other ser...
Ampersand on Two-Year Change in: Walt - thanks for pointing to Meredith's Facebook page. I will definitely be fol...
walt on Two-Year Change in: Our ANC Commissioner Meredith Fascett has been working with DDOT to improve that...

Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1400 B/O SOUTH CAPITOL ST   THEFT
Theft 2nd Degree (all Other Larceny)
 08/28/16
1200 B/O 4TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/17/16
1000 B/O HALF ST SE   THEFT
Theft First Degree (all Other Larceny)
 08/16/16
700 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/15/16
1400 B/O SOUTH CAPITOL ST   THEFT
Theft 2nd Degree (all Other Larceny)
 08/14/16
16 B/O M ST SE   ROBBERY  08/12/16
1000 B/O 5TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/09/16
1200 B/O 1ST ST SE   THEFT
Theft First Degree (shoplifting)
 08/08/16
50 B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 08/02/16
600 B/O I ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 08/02/16
700 B/O L ST SE   ROBBERY  08/01/16

Recent Issued Building Permits Archive  
1150 5TH ST SE 20002   
08/11/16 
ALAN J PHELPS / DOUGLAS FOSTER
B1509540 / CONSTRUCTION
1. Renovation of existing first and second floor of the academic wing of the Van Ness building. 2. Square footage is approximately 26,000 SF ,For phase 1 3. Cost of construction is 11.5M 4. Scope of work details a. Convert existing space in to 6 new classroom space. These classrooms will be two PreK -3, two prek-4, and two Kindergarten classes. Also for phase 1,...
1150 5TH ST SE   
08/12/16 
DISTRICT OF COLUMBIA / JOHN HOMICK
E1609156 / SUPPLEMENTAL
   
08/12/16 
DISTRICT OF COLUMBIA / MATT LOSIGNOR
P1608656 / SUPPLEMENTAL
   
08/12/16 
DISTRICT OF COLUMBIA / ORLANDO M CATANA
E1609149 / SUPPLEMENTAL
82 I ST SE   
08/15/16 
GDCV EYE STREET LLC / GDCV EYE STREET LLC; KIM MITCHELL CDKM CONSULTING LLC
B1611941 / CONSTRUCTION
FIRST EXTENSION TO PERMIT B1507990 TO EXPIRE ON 3 / 17 / 17
   
08/15/16 
CSX TRANSPORTATION INC / BEDCO MOBILITY INC.
EN1602806 / SHOP DRAWING
Type of Elevator : One (1) vertical wheel-chair lift / steel / garage level 2 / handicap lift (13th floor)
125 L ST SE   
08/11/16 
CRANE SERVICE CO / CRANE SERVICE CO; CHRISTINE LONG
AH1600945 / CONSTRUCTION
An after hours permit is respectfully requested from 4AM Saturday thru 9PM Sunday
80 M ST SE 1   
08/10/16 
WELLS REIT II 80 M STREET LLC / THOMAS B. STEG
P1608566 / SUPPLEMENTAL
80 M ST SE 2   
08/10/16 
WELLS REIT II 80 M STREET LLC / THOMAS B. STEG
P1608568 / SUPPLEMENTAL
80 M ST SE 3   
08/10/16 
WELLS REIT II 80 M STREET LLC / THOMAS B. STEG
P1608569 / SUPPLEMENTAL
100 M ST SE PT OF 4TH   
08/11/16 
QUARE 743 INC . / QUARE 743 INC .; JOHN GIUSEPPE-RAMCO
B1611810 / CONSTRUCTION
renovation to parts of an existing 4th floor office space, tech marine business as shown on the attached mech., plumb., elect., fire protection, demolition, and arch. dwgs. interior work only. no change in use. no struct. work. 800 sf.
909 NEW JERSEY AVE SE 1311   
08/11/16 
null / NA NA NA
EHOP1690902 / HOME OCCUPATION
861 NEW JERSEY AVE SE   
08/09/16 
NA CSX TRANSPORTATION, INC.
AH1600944 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities.
1111 NEW JERSEY AVE SE   
08/11/16 
null / THOMAS P MCGUIRE
E1609117 / SUPPLEMENTAL
385 WATER ST SE   
08/12/16 
FC 385 WATER LLC / STEPHEN J. EXELBERT
P1608654 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Capitol ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2016 JD.