On a chilly morning (with winds high enough to scuttle the planned boat tour), DDOT announced that work is officially underway on the new 11th Street Bridges, the $300 million four-year project to build three new spans across the Anacostia River to provide both expanded freeway access between I-295 and the SE/SW Freeway and a new local-traffic bridge connecting Anacostia and Near Southeast.
Pile driving in the river is expected to start within the next day or two (it was supposed to start today, but the winds scuttled that, too). Engineers said it should be at least 18 months before there are any changes to the traffic flow on either side of the river.
The biggest changes in the configuration of the bridges will be the new ramps allowing for access from southbound I-295 to the bridges and from the bridges to northbound DC295, meaning that much of the neighborhood cut-through traffic and bad flow on Pennsylvania Avenue should be mitigated, though residents who oppose the expansion of the bridges' capacity--such as the Capitol Hill Restoration Society--differ with DDOT on the benefits of the project.
The third span--a "local street that happens to cross a river," in the words of DDOT's Bart Clark--will be built with streetcar tracks included in the two curb lanes, and will also include wide pedestrian/cycling paths, bulb-out bridge overlooks (where you can stop and look at the view without impeding the flow), and even osprey nest perches down by the water. This span, allowing local traffic to cross the river without having to mix with high-speed freeway traffic as it currently does, will reach street level at O Street on the west side of the river, which will also make for an easy connection to the Anacostia Riverwalk Trail. And all new bridges will be built with shoulders, to help lessen backups when there are accidents.
One additional change in all of this is that the Anacostia Community Boathouse operations, which are currently nestled between the existing spans, will be permanently moved northeast, to the Anacostia marina, and the old red brick buildings will be demolished. (A temporary structure is being built to get their operations moved by spring.)
For the next few months, pile driving and some off-roadway clearing and minor lane shifts on DC-295 will be the extent of the construction, but by late spring or early summer there will begin to be work underway on both O Street and M Street
I've added new graphics to my 11th Street Bridges page that show the plans for the new bridges. It will be an interesting project to watch over the next few years.
In addition, demolition work on the existing ramps to and from RFK has perked back up again, and there will be lane closures on the portion of the freeway that connects to Pennsylvania Avenue within the next few weeks. (If you saw the variable message sign at the Sixth Street SE exit that said "Freeway to be closed on or about 1/9/2010," it was a bit of a verbiage boo-boo that was meant to alert drivers to the coming lane closures, and is being fixed.)
There was a decent amount of press at the briefing (both Dr. Gridlock and Bob Marbourg were in the house, so you know it was serious), and I'll be updating this entry as stories come online, most of which will no doubt give more focus to the changes coming to the east side of the river than I have here (though I have posted some enlarged graphics that show both sides of the river). Here's the DDOT press release, fact sheet, and FAQ.
UPDATE: Links to Dr. Gridlock, WTOP, and City Paper. And WUSA. (I won't bother with pieces written right off the press release.)
UPDATE II: A bike-centric look at the plans from WashCycle.
Comments (0)
 
 More About 11th Street Bridges

JDLand.com Home

Comments

G St says: (12/30/09 9:13 AM)
Lookin' for fun and feelin' groovy.

Those bridges needed some work - hope they decide (when they're done) to *light 'em up*... in blue lights, like the one next to Nats Park.


InvestDest says: (12/30/09 9:26 AM)
Another bridge that lacks style and creativity. Is it too much to ask for an awe-inspiring bridge of which we can be proud?

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed

See All Current News Items | Full Blog Archive

 
 Top News
  
Tell readers about your apartment/house/item
for two weeks for $5.
Someone's looking for
what you're selling!
List it here.
Recent Comments:  
Andrew in DC on Southeast Blvd.: It sounds like DDOT is pulling a fast one. But they wouldn't do that would they...
202_cyclist on Southeast Blvd.: Will options A1 - A3 allow for more housing to be built along the former right-o...
sumar16 on Southeast Blvd.: Thanks for the update JD. As an L Street resident overlooking the current constr...
Gamble Rogers on Southeast Blvd.: You rock, JD. Enjoy the holiday weekend! And seriously, I'm with Commissioners ...



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
M ST SE AND HALF ST SE   ROBBERY /  08/17/14
800 B/O VIRGINIA AVE SE   THEFT F/AUTO /  08/17/14
M ST SE AND 5TH ST SE   THEFT F/AUTO /  08/15/14
1400 B/O 1ST ST SE   THEFT F/AUTO /  08/14/14
1000 B/O 1ST ST SE   BURGLARY /  08/12/14
800 B/O L ST SE   THEFT F/AUTO /  08/11/14
HALF ST SE AND L ST SE   THEFT F/AUTO /  08/11/14
1000 B/O NEW JERSEY AVE SE   THEFT /  08/07/14
1100 B/O 10TH ST SE   THEFT /  08/07/14
70 B/O I ST SE   THEFT /  08/02/14
100 B/O K ST SE   THEFT F/AUTO /  08/01/14
200 B/O L ST SE   THEFT F/AUTO /  07/30/14
L ST SE AND 2ND ST SE   THEFT F/AUTO /  07/30/14
70 B/O I ST SE   MOTOR VEHICLE THEFT /  07/29/14
70 B/O I ST SE   THEFT /  07/29/14

Active Public Space Permits Archive  
1331 2ND ST SE    Carlton Ray 
Assigned
paving; streetfixture; excavation  
 02/10/14
to
02/09/15
908 3RD ST SE    Rachel Frankel 
Issued
streetfixture; new  
 07/24/14
to
09/21/14
1026 3RD ST SE    Wash Gas & Light Co. 
Issued
excavation; new  
 06/26/14
to
09/04/14
1331 4TH ST SE    Forest City Forest City 
Issued
excavation; new  
 01/10/14
to
02/10/15
410 M ST SE    Pepco Holdings Inc 
Issued
excavation; new  
 07/11/14
to
09/08/14
880 NEW JERSEY AVE SE    WASHINGTON GAS 
Issued
excavation; new  
 07/28/14
to
09/26/14
301 TINGEY ST SE    Potbelly Sandwich Works LLC 
Issued
new  
 03/21/12
to
11/27/14

Recent Issued Building Permits Archive  
1011 1ST ST SE   
08/11/14 
TOLL DC LP / ALBERT J. PEARCE
FB1400108 / SUPPLEMENTAL
1259 1ST ST SE   
08/11/14 
CAPITAL RIVERFRONT HOTEL LLC / CAPITAL RIVERFR HOTEL LLC
AH1400636 / CONSTRUCTION
AFTER HOURS FOR PERMIT NUMBER B1401471 FOR 8 / 12 THROUGH 9 / 11 FROM 5AM TO 7PM MONDAY THROUGH SATURDAY.
1201 4TH ST SE   
08/12/14 
JBG/FEDERAL CENTER LIC / JIM CALABRESE
AN1400129 / CONSTRUCTION
PLEASE EXTEND PERMIT AN1300174 THIS IS THE FIRST EXTENSION AND PERMIT WILL BE VALID UNTIL 1 / 31 / 2015.
1212 4TH ST SE   
08/25/14 
FC 1212 LLC / MARK E. RESNICK
E1408462 / SUPPLEMENTAL
1331 4TH ST SE   
08/14/14 
F. C. 1331 LLC / FVI 2020
B1402843 / CONSTRUCTION
CONSTRUCTION OF A BRAND NEW 11 STORY BUILDING. THE BUILDING IN TOTAL IS 350 000 SQ FT. ADDING 327 RESIDENTIAL RENTAL UNITS 20 000 SQ FT. IN COMMERCIAL SPACE AND 3 BELOW GRADE PARKING LEVELS.
   
08/15/14 
CLARK CONCRETE
AH1400650 / CONSTRUCTION
AFTER HOURS TO POUR CONCRETE ON JOBSITE FROM 7AM TO 7PM FROM SUNDAY TO SATURDAY 8 / 15 / 2014 TO 11 / 15 / 2014
1000 5TH ST SE   
08/13/14 
UNITED STATES OF AMERICA /
FD1400132 / CONSTRUCTION
NEW FOUNDATION TO GRADE PERMIT FOR NEW COMMUNITY CENTER INCLUDING UTILITIES. REVISION TO FD1400029 TO REVISE STRUCTURAL DETAILS OF COLUMS.
   
08/20/14 
UNITED STATES OF AMERICA / BRUCE G. PICKETT
E1408304 / SUPPLEMENTAL
1220 12TH ST SE   
08/27/14 
FAIRBANKS MORSE ENGINE / EVAN O'BRIEN/ D MCKEEVER SERVICES
B1411219 / CONSTRUCTION
INTERIOR ONLY NON-STRUCTURAL ALTERATION TO EXISTING OFFICE SPACE. WORK INCLUDS MINOR PARTITION CHANGES AND THE ASSOCIATED HVAC AND ELECTRICAL ALTERATIONS.
1015 HALF ST SE   
08/12/14 
HALF ST SE LLC / SAM HOLLEN RAMCO OF DC INC.
TL1400162 / CONSTRUCTION
INTERIOR TENANT LAYOUT OF 1ST FLOOR PERFORMANCE STUDIO SPACE AND OFFICE SPACE. PARTITIONS FURNITURE MECHANICAL ELECTRICAL AND LIFE SAFETY. CBS
   
08/15/14 
HALF ST SE LLC / ROBERT L HUNTER
M1402951 / SUPPLEMENTAL
   
08/16/14 
SAM HOLLEN / DONALD VEALS; SAM HOLLEN; DONALD VEALS
E83010192 / SUPPLEMENTAL
200 I ST SE   
08/08/14 
DANIEL RILEY / OMAR BIAGAS; DANIEL RILEY; JOHN BIAGAS
E47247428 / SUPPLEMENTAL
41 L ST SE   
08/20/14 
WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY (WMATA) / SAMIR ALQUTRI - GEOTECHNICAL SOLUTIONS INC.
SB1400402 / CONSTRUCTION
GSI PLANS TO DRILL 4 SOIL TEST BORINGS TO CONFIRM SOIL STRENGTH WITH A HOLLOW-STEM AUGER EQUIPPED WITH A SPLIT SPOON SAMPLER FOR THE SPT N-VALUE TESTS DOWN TO A MAXIMUM DEPTH OF 80 FEET BELOW EXISTING GRADES. ALL BORINGS WILL BE DRILLED TO THE MAXIMUM DEPTH OR AUGER REFUSAL WHICHEVER OCCURS FIRST. THE BORE HOLES DIMENSION WILL BE 3.25 INCHES AND SHALL BE GROUTED UPON COMPLETION.
20 M ST SE   
08/22/14 
TRANSWESTERN JEFFERY W GROSS / ANDREW ARNTSON; TRANSWESTERN JEFFERY W GROSS; ANDREW ARNTSON
P96600069 / SUPPLEMENTAL
   
08/22/14 
TRANSWESTERN JEFFERY W GROSS / ANDREW ARNTSON; TRANSWESTERN JEFFERY W GROSS; ANDREW ARNTSON
G22130990 / SUPPLEMENTAL
   
08/25/14 
SUBWAY / N/A; DAMON ELLIS
SG1400416 / CONSTRUCTION
INSTALLATION OF NON ELECTRIC SIGN 10FT 8IN LENGTH 2IN WIDE 25IN HEIGHT
   
08/27/14 
JOHN GLUSEPPE-RAMCO / CARL LAVENDT; JOHN GLUSEPPE-RAMCO; CARL LAVENDT
E10905761 / SUPPLEMENTAL
100 M ST SE   
08/16/14 
NORTHWOOD INVESTERS LLC / STANLEY HUBBARD; NORTHWOOD INVESTERS LLC; STANLEY HUBBARD
E14516088 / SUPPLEMENTAL
901 M ST SE   
08/14/14 
CARLTON RAY
AH1400642 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
1201 M ST SE   
08/14/14 
CARLTON RAY
AH1400641 / CONSTRUCTION
TO PERFORM TEMPORARY LANE CLOSURES
861 NEW JERSEY AVE SE   
08/21/14 
CONSOLIDATED RAIL CORPORATION / ROBERT COLISH
P1407975 / SUPPLEMENTAL
1111 NEW JERSEY AVE SE   
08/12/14 
NJA ASSOCIATES LLC / COLIN CLARK
B1308085 / CONSTRUCTION
CONSTRUCT A NEW 13 STORY APARTMENT BUILDING WITH THREE BELOW GRADE PARKING LEVELS FIRST FLOOR RETAIL A PRIVATE SWIMMING POOL PROJECTIONS OF BAY WINDOWS 324 UNITS TO INCLUDE MECHANICAL PLUMBING ELECTRICAL AND ELEVATOR WORK.
1200 SOUTH CAPITOL ST SE   
08/26/14 
MR BALLPARK 4 LLC. / MR BALLPARK 4 LLC.; RPS INC.
SB1400375 / CONSTRUCTION
ENVIRONMENTAL SOIL BORINGS FOR DUE DILIGENCE INVESTIGATION. ADVANCE A SERIES OF 10 ENVIRONMENTAL SOIL BORINGS AT THE SUBJECT SITE TO COLLECT SOIL AND GROUNDWATER SAMPLES FOR FIELD SCREENING AND LABORATORY ANALYSIS. THE SOIL BORINGS ARE BEING CONDUCTED AS PART OF A DUE DILIGENCE INVESTIGATION ASSOCIATED WITH A REAL ESTATE TRANSACTION. INVESTIGATION DERIVED WASTE -IDW- WILL BE LABORATORY TESTED AND ...
1230 SOUTH CAPITOL ST SE   
08/21/14 
PUBLIC STORAGE INSTITUTE FUND / RAYMOND SCIANNELLA
E1408379 / SUPPLEMENTAL
   
08/21/14 
PUBLIC STORAGE INSTITUTE FUND / CHRIS WING
B1410888 / CONSTRUCTION
INTERIOR ALTERATION TO EXISTING SELF STORAGE BUILDING TO REPLACE FIRE ALARM SYSTEM.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory




Blog/Home
Project Directory
Photo Archive
Event Photos
 
Nats Park
Food Map
What's New
History

 
Demolished Buildings
Historic Photos
Satellite Images
Timeline
 
About JDLand
Message JD
Advertise
Photo Use
 
     © Copyright 2014 JD.