On a chilly morning (with winds high enough to scuttle the planned boat tour), DDOT announced that work is officially underway on the new 11th Street Bridges, the $300 million four-year project to build three new spans across the Anacostia River to provide both expanded freeway access between I-295 and the SE/SW Freeway and a new local-traffic bridge connecting Anacostia and Near Southeast.
Pile driving in the river is expected to start within the next day or two (it was supposed to start today, but the winds scuttled that, too). Engineers said it should be at least 18 months before there are any changes to the traffic flow on either side of the river.
The biggest changes in the configuration of the bridges will be the new ramps allowing for access from southbound I-295 to the bridges and from the bridges to northbound DC295, meaning that much of the neighborhood cut-through traffic and bad flow on Pennsylvania Avenue should be mitigated, though residents who oppose the expansion of the bridges' capacity--such as the Capitol Hill Restoration Society--differ with DDOT on the benefits of the project.
The third span--a "local street that happens to cross a river," in the words of DDOT's Bart Clark--will be built with streetcar tracks included in the two curb lanes, and will also include wide pedestrian/cycling paths, bulb-out bridge overlooks (where you can stop and look at the view without impeding the flow), and even osprey nest perches down by the water. This span, allowing local traffic to cross the river without having to mix with high-speed freeway traffic as it currently does, will reach street level at O Street on the west side of the river, which will also make for an easy connection to the Anacostia Riverwalk Trail. And all new bridges will be built with shoulders, to help lessen backups when there are accidents.
One additional change in all of this is that the Anacostia Community Boathouse operations, which are currently nestled between the existing spans, will be permanently moved northeast, to the Anacostia marina, and the old red brick buildings will be demolished. (A temporary structure is being built to get their operations moved by spring.)
For the next few months, pile driving and some off-roadway clearing and minor lane shifts on DC-295 will be the extent of the construction, but by late spring or early summer there will begin to be work underway on both O Street and M Street
I've added new graphics to my 11th Street Bridges page that show the plans for the new bridges. It will be an interesting project to watch over the next few years.
In addition, demolition work on the existing ramps to and from RFK has perked back up again, and there will be lane closures on the portion of the freeway that connects to Pennsylvania Avenue within the next few weeks. (If you saw the variable message sign at the Sixth Street SE exit that said "Freeway to be closed on or about 1/9/2010," it was a bit of a verbiage boo-boo that was meant to alert drivers to the coming lane closures, and is being fixed.)
There was a decent amount of press at the briefing (both Dr. Gridlock and Bob Marbourg were in the house, so you know it was serious), and I'll be updating this entry as stories come online, most of which will no doubt give more focus to the changes coming to the east side of the river than I have here (though I have posted some enlarged graphics that show both sides of the river). Here's the DDOT press release, fact sheet, and FAQ.
UPDATE: Links to Dr. Gridlock, WTOP, and City Paper. And WUSA. (I won't bother with pieces written right off the press release.)
UPDATE II: A bike-centric look at the plans from WashCycle.
Comments (2)
   
 
 More About 11th Street Bridges

JDLand.com Home

Comments

G St says: (12/30/09 9:13 AM)
Lookin' for fun and feelin' groovy.

Those bridges needed some work - hope they decide (when they're done) to *light 'em up*... in blue lights, like the one next to Nats Park.


InvestDest says: (12/30/09 9:26 AM)
Another bridge that lacks style and creativity. Is it too much to ask for an awe-inspiring bridge of which we can be proud?

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

dcgent on I'm Dreaming of: I posted the link partly because I'm a Detroiter. Folks in SE are championing De...
jdc on I'm Dreaming of: Love the grandma slices at Wise Guys. And being from MI too, I also love Buddy's...
VelocityChris on I'm Dreaming of: The description and picture of the Detroit-style pizza sounds/looks just like th...
JD on I'm Dreaming of: Longtime readers may remember the many trips with Mr JDLand to Michigan, where h...
dcgent on I'm Dreaming of: Detroit-style pizza coming to undisclosed navy yard location https://dc.eater.c...
Westnorth on I'm Dreaming of: XO sauce is fish-based, as with many Cantonese sauces: https://en.wikipedia.org/...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
No records added or modified in the past two weeks.

Recent Issued Building Permits Archive  
1402 1ST ST SE   
11/25/19 
UNITED STATES OF AMERICA / DAVID C POSTLEWAITE
SB1900412 / CONSTRUCTION
Parcel G2:WSP will complete four borings up to the deepest potential subgrade elevation (approx. 32 ft. bgs). The proposed boring locations would be in the four quadrants of Parcel G2 to check for spatial variability in contaminant concentrations. WSP will collect and analyze three soil samples from each boring from depths corresponding to potential subgrade elevations (i.e. 10-12 ft. bgs, 20-22 ...
1212 4TH ST SE   
11/25/19 
FC 1212 LLC / TAMIKA STATON; OTIS
ER2000409 / SHOP DRAWING
Replace governor car #2 - Part #: TBA20641H6 Replace hoist belts #1 and #4 - Part #: SB0003119
1300 4TH ST SE   
11/15/19 
ASANA PARTNERS / DEBRA MARSHALL; THE DONOHOE COMPANIES INC
B2001773 / CONSTRUCTION
ADD EXTERIOR DOOR, ADD INTERIOR DOOR , ANY RELAYED,ELECTRICAL,PLUMBING, RELOCATING UNBUILT APPROVED NON LOAD BEARING FIRE RATED PARTITIONS @ FIRST FLOOR APPROVED UNDER PERMIT #B1711970. ATTACHED
   
12/06/19 
ASANA PARTNERS / S.A. COMUNALE; S.A. COMUNALE
P2001954 / SUPPLEMENTAL
1346 4TH ST SE   
12/06/19 
KAITLYNN MATTEO / W. SAKIE - BHAR; W. SAKIE - BHAR; NA
SG2000117 / CONSTRUCTION
Install one set of non illuminated sign on to existing store front building
861 NEW JERSEY AVE SE   
11/15/19 
CSX TRANSPORTATION INC / ERICKA CLARK; DGS CONSTRUCTION
TC2000008 / CONSTRUCTION
(2) tower cranes
   
11/26/19 
GREYSTAR GP I I, LLC / KIM MITCHELL; KIM MITCHELL
FD1900040 / CONSTRUCTION
TWO BELOW GRADE PRKING LEVELS, CONCRETE FOUNDATION WALLS, SLAB ON GRADE, COLUMNS ELEVATED DECKS UP TO GRADE WITH UNDERGROUND UTILITIES (MECHANICAL, PLUMBING, ELECTRICAL)
   
12/05/19 
MIKE ALLEN / JANE MCCRAY
AH2000244 / CONSTRUCTION
WO# 1611441 - Mike Allen / P. Helgeson. Pepco to install network transformer
1111 NEW JERSEY AVE SE   
11/15/19 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / TANYA HILL; THYSSENKRUPP
ER2000366 / SHOP DRAWING
REPLACE EXISTING 8MM WORN HOIST CABLES WITH LIKE IN KIND ON ELEVATOR #4. WORK TO ALLOW UNIT TO BE RETURNED TO SERVICE.
125 O ST SE   
11/25/19 
DISTRICT OF COLUMBIA / DAVID C POSTLEWAITE
SB1900411 / CONSTRUCTION
WSP will complete three borings up to the deepest potential subgrade elevation (approx. 32 ft. bgs). WSP assumes that borings will not be installed inside the fleet maintenance facility due to access restrictions imposed by DC Water. The proposed boring locations form an ā€˜Lā€™ shape around the eastern and southern sides of the fleet maintenance facility. WSP will collect and analyze three soil samp...
71 POTOMAC AVE SE   
12/06/19 
MPR REALTY / BOB BIROONAK; BOB BIROONAK; ART DISPLAY CO
SG2000099 / CONSTRUCTION
One building name MAREN Two set of address numbers all signs are non-illuminated
201 TINGEY ST SE   
11/14/19 
BROOKFIELD PROPERTIES / DFM DEVELOPMENT SERVICES, LLC
AH2000197 / CONSTRUCTION
Afterhours work at Tingey Square Project. The work performed will be forming, prepping and paving at Tingey Square park. Friday and Saturday the 15th & 16th, from 7PM to midnight. If required, Sunday the 17th from 7AM to 3PM. ANC Support provided. Associated Permit Include PA328164-R1 and PA10760162.
227 TINGEY ST SE   
12/02/19 
FC 227 LLC / KAYLA SHATTUCK; BROOKFIELD PROPERTIES MANAGEMENT LLC.
RW1900122 / CONSTRUCTION
Construction of new retaining wall located between Canal Street St and Third Street, SE.
300 TINGEY ST SE   
12/04/19 
FC BOILERMAKER LLC / ROBERT S. WATTS; ROBERT S. WATTS
E2002289 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2019 JD.