With the launch a few weeks back of a bike lane on 15th Street NW, attention is beginning to focus on other locations in the city where there is a desire to place new dedicated bike lanes, and one of those spots is M Street SE/SW, running from Sixth Street, SW to 11th Street, SE, which is a route that Tommy Wells has been interested in for quite a while.
Back in early October, WashCycle reported that DDOT's Bicycle Advisory Facility Committee discussed the M Street concept, and in mid-November the members of the Capitol Riverfront BID were briefed on a feasibility analysis done by the Toole Design Group, with the assembled BIDders told that FY10 funds are available and that there's a desire by Wells and DDOT to get the lanes built before the start of the 2010 baseball season, which apparently caught a number of the briefing attendees by surprise.
In the analysis that was presented to the BID (which you can see here, although appendices A and B were left blank in the handouts), the main recommendations are:
* Configure the two curb lanes on M Street as "cycle tracks" with flexible posts, a temporary measure suggested because of the "unknowns" of any future streetcar implementations along M Street. There would also be a widening of the sidewalks between Half streets SE and SW, moving the cycle track onto the widened sidewalk, because this area is where the "most intense traffic on the corridor occurs."
* Eliminate all parking along M Street at all hours, though "after a period of evaluation it may be appropriate to allow parking adjacent to the cycle track if it is desired."
* Move all transit stops to the far sides of intersections, where buses and bikes can more easily cross and where buses can still pick up and drop off passengers at a curb rather than on street level.
* Reconfigure all traffic signals to allow bikes time to get through intersections before vehicle traffic gets a green light (the bikes and the pedestrian "walk" signals would go green first, followed then by the vehicular greens).
The "very preliminary" cost estimates for the options developed by the study come in around the $450,000 range according to the document, but it must be remembered that this is a study, and not the final plans, and the numbers could go up or down.
There apparently were some business owners at the BID meeting who were displeased with the plans, centering mainly around the traffic implications of the loss of one lane in each direction, which during rush hour and ballpark events are travel lanes and which are parking for customers/workers/residents/etc. the rest of the time.
This could especially be an issue during events at Nationals Park, a scenario which isn't mentioned at all in the feasibility study and which has the Nationals particularly concerned (as apparently voiced by the Nats' Gregory McCarthy at the briefing), since it's not out of the realm of possibility (my words, not theirs) that attendance at the ballpark could rise substantially if the team's fortunes improve, making the backups that are seen when the stadium is sold out--such as during the Red Sox series this summer--considerably worse.
There's been no meeting with ANC 6D commissioners yet about this, though reportedly one is coming soon. I've got a request in to Tommy Wells's office for more information (and what better time to ask a question like that than right around Thanksgiving), so no doubt there is much more to come.
Comments (8)
   
 
 More About M Street

JDLand.com Home

Comments

w says: (11/30/09 4:55 PM)
DC is a real city and many many people here do not drive and are NOT auto-oriented-use transit, walk, bicycle- and we desperately need better bicycle infrastructure .There is no reason to fight this excellent idea.


JM says: (12/2/09 2:28 PM)
JD-

Does the news that there will be no "groundbreakings" in DC regarding new properties refer also to any projects such as the Yards, where there are existing buildings that are having additions built on to them or re-done in the inside, etc? Or does it only refer to buildings that have yet to have any ground broken on them? I'm just wondering if there has been any word on any of the commercial projects in Near Southeast as of late? When I attended the Capitol Riverfront BID picnic and neighborhood tour over the summer, the gal giving the tour said that some of the buildings that make up the Yards will begin heavy construction in early 2010.


JD says: (12/2/09 3:55 PM)
I went to Forest City at the time to ask about what the BID folks were telling people at that picnic/tour, and Forest City wouldn't confirm any plans for the start of construction on any projects. They told me they were hoping to be able to have an announcement soon, but that was back in late September.

So, as of now, I don't know of any projects that would get underway any time soon, except perhaps Phase 2 of Capitol Quarter and maybe the mixed-income apartment building to be built by the Housing Authority at 7th and L, if the bond sale happens. The only commercial project that looked like a possibility in 2010--Akridge Half Street--has made no moves that I've seen toward any groundbreakings. Maybe the second half of 2010 will see some movement, but nothing that can really be foreseen right now.


E says: (12/3/09 2:20 PM)
Apparently, SWNA meeting on November 23 (reported on page 3 in the Southwester link mention was made of the Yards, although it isn't in Southwest.


JM says: (12/4/09 12:52 PM)
Hey E Street, your link didn't work.


Andy says: (12/4/09 3:26 PM)
JM, take the parenthesis off the end of E's link in the address bar after you click on it. That's how I got it to work for me.


Andy says: (12/5/09 8:24 AM)
Hurray! It's a good thing to city's leadership is pushing for this - long over due improvements to ensure cyclist's safety and still allow flow of traffic.


JM says: (12/7/09 9:55 AM)
Thanks, Andy. E Street, good stuff in that newsletter. Thanks for posting the link. Sounds like a representative from Forest City is saying similar things that the BID did a few months ago. Construction is going to start back up after the New Year and also there will be some announcements in the next few months on restaurants that will be going into a restaurant pavillion (can't remember which building, maybe the Boilermaker Shop).

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts
  

202_cyclist on Catching Up With: @AllIsNotWells -- that is what I thought. Thank you for confirming.
202_cyclist on Catching Up With: @AllIsNotWells -- that is what I thought. Thank you for confirming.
AllIsNotWells on Catching Up With: @202 New member orientation for the 116th congress.
202_cyclist on Catching Up With: Folks— what big event is happening at the Courtyard Marriott this week?
CJBabyDaddy on Catching Up With: @spiritequality: Rhymes with “groovy tea waiter” and “newbie fee hater?”
JNB on Catching Up With: HQ2 to Crystal City. Just announced.
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
150 B/O L ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/12/18
400 B/O M ST SE   THEFT FROM AUTO
Theft Of Motor Vehicle Parts Or Accessories
 11/11/18
700 B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle) - Convenience Store
 11/11/18
800 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 11/09/18
700 B/O M ST SE   THEFT
Theft First Degree (all Other Larceny)
 11/09/18
1200 B/O 4TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/08/18
400 B/O M ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 11/07/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/07/18
800 B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 10/31/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/30/18
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (theft From Building)
 10/29/18
50 B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 10/28/18
100 B/O O ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 10/28/18
1400 B/O M ST SE   ASSAULT WITH A DANGEROUS WEAPON  10/26/18
100 B/O M ST SE   THEFT
Theft 2nd Degree - Felony (all Other Larceny)
 10/23/18
900 B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 10/23/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/22/18
900 B/O 5TH ST SE   HOMICIDE
Murder I
 10/20/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/20/18
1000 B/O 1ST ST SE   THEFT
Theft 2nd Degree (theft From Building)
 10/19/18
400 B/O M ST SE   THEFT
Shoplifting
 10/17/18
100 B/O N ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 10/17/18

Recent Issued Building Permits Archive  
1100 2ND PL SE   
10/23/18 
null / ANDY MCKELVEY
SP1800044 / CONSTRUCTION
Construct outdoor swimming pool on 10th floor roof of new building
1013 4TH ST SE   
11/05/18 
EVA WALTER / KYLE YOST
SOL1900066 / CONSTRUCTION
5.89kw rooftop solar pv system, less than 4' above roof
   
11/07/18 
EVA WALTER / null
E1901297 / SUPPLEMENTAL
1346 4TH ST SE   
10/18/18 
FC 1346, LLC / DFM DEVELOPMENT SERVICES, LLC
B1809670 / CONSTRUCTION
Parcel O-2 at the Yards. Revision to Permit B1610576 for installation of flood wall on 5th Street, SE, the reduction of roadway width, and widening of sidewalk to provide adequate pedestrian clear space between flood wall and edge of tree pit. TPR
   
11/01/18 
ALAN OWINGS / ROBERT HENRY
AH1900133 / CONSTRUCTION
After Hours Permit for 11 / 12 / 2018, to perform construction work with the below activities: Interior Operations: 7AM-7PM Exterior Operations: 9AM-7PM
1000 5TH ST SE   
10/31/18 
UNITED STATES OF AMERICA / JOY WILDER
B1901427 / CONSTRUCTION
Non Construction permit to change load for current Child Development Center with 26 children 3 to 6 years old +3 Staff to Child Development Center with 30 Children + 3 Staff.
2 I ST SE   
10/17/18 
MCDONALDS CORPORATION / DONNA G GRAHAM
AH1900080 / CONSTRUCTION
WR #3573836 - M.ALLEN / BRUNO - WARD 6 - 20003 - PEPCO CREWS WILL BE WORKING #2 I ST SE - MAY NEED TO BLOCK "I" STREET ON OCCASION TO INSTALL NETWORK TRANSFORMERS AND INSTALL AND SPLICE CABLES - CREW WILL BE WORKING AT NIGHTS DURING THE WEEK (MONDAY-FRIDAYS) FROM 9PM TIL 7AM - PEPCO CREWS WILL ALSO BE WORKING SATURDAY AND SUNDAYS FROM 6AM TIL 6PM - WORK IS ONGOING
   
11/05/18 
CRESCENT CAPITAL VIEW / CASSANDRA MOSLEY
AH1900160 / CONSTRUCTION
Installation of wet utility services to the new building at 4 I Street SE including fire service, domestic service, and storm sewer.
10 I ST SE   
10/24/18 
CAPITOL HILL RACQUET CLUB / BOB BIROONAK; N/A
SG1900026 / CONSTRUCTION
Relocating existing freestanding sign
110 I ST SE   
11/06/18 
null
E1901238 / SUPPLEMENTAL
200 I ST SE 20009   
10/25/18 
DISTRICT OF COLUMBIA / null
M1900267 / SUPPLEMENTAL
200 I ST SE   
11/05/18 
GOVERNMENT OF THE DISTRICT OF COLUMBIA / null
E1901223 / SUPPLEMENTAL
   
10/25/18 
DISTRICT OF COLUMBIA / CLIFFORD DIXON
B1809410 / CONSTRUCTION
DGS OCTO BUILDING...NEW GENERATOR ON THE ROOF WITH ASSOCIATED MECHANICAL
   
11/07/18 
DISTRICT OF COLUMBIA / DANIEL MCGUIRE
P1901098 / SUPPLEMENTAL
300 M ST SE 8TH FL   
10/24/18 
FEDERAL CENTER LP / ALFRED JORDAN 2024375067
E1900838 / SUPPLEMENTAL
300 M ST SE 8TH FLOOR 20003   
10/22/18 
JBG SMITH - MORGAN JOHNSON-MASSEY / null
E1900736 / SUPPLEMENTAL
130 M ST SE   
11/09/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / RICHARD PLUMLEY
P1901176 / SUPPLEMENTAL
250 M ST SE   
11/07/18 
WCSMITH - BRIAN STROTT / GEORGE ARTHUR KING
SB1900025 / CONSTRUCTION
Drill and construct two 2 inch diameter observation wells 42 feet below existing grade utilizing mud rotary drilling methods. All drill spoils will be contained, tested and disposed of per DOEE regulation.
400 M ST SE   
10/18/18 
CAPPER SENIOR 11 LIMITED PARTNERSHIP / null
E1900650 / SUPPLEMENTAL
   
11/02/18 
CAPPER SENIOR 11 LIMITED PARTNERSHIP / null
E1901156 / SUPPLEMENTAL
861 NEW JERSEY AVE SE   
10/31/18 
CONSOLIDATED RAIL CORPORATION / BRANDON KNAPP
AH1900131 / CONSTRUCTION
Work in the public ROW with the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, concrete structure, paving, and site restoration construction activities.
   
11/07/18 
CONSOLIDATED RAIL CORPORATION / RPS INC
SB1900023 / CONSTRUCTION
Per Work Plan, Geotechnical Investigation, dated October 18, 2018 (see attached), the work involves drilling 12 soil borings using a HSA rig for the purpose of collecting soil samples for geotechnical subsurface exploration. Boring depths range from 80 to 150 ft. Borings will be properly backfilled after completion.
1111 NEW JERSEY AVE SE   
10/17/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
E1900581 / SUPPLEMENTAL
   
10/23/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / MICHAEL PISA; PISA
SG1800505 / CONSTRUCTION
Install 2 sets of wall mounted illuminated channel letters
   
10/25/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / null
E1900860 / SUPPLEMENTAL
   
11/05/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / MICHAEL B. BELL
E1901199 / SUPPLEMENTAL
227 TINGEY ST SE   
10/17/18 
UNITED STATES OF AMERICA / DFM DEVELOPMENT SERVICES, LLC
AH1900079 / CONSTRUCTION
Yards Parcel L-2. Afterhours permit for the purpose of installing precast concrete façade panels. Work to take place 7PM to 7AM, 10 / 22 through 11 / 3.
   
11/01/18 
JOHN MORIARTY & ASSOCIATES / DFM DEVELOPMENT SERVICES, LLC
AH1900141 / CONSTRUCTION
Yards Parcel L-2. Afterhours permit for the purpose of installing precast concrete façade panels. Work to take place 7PM to 7AM, 11 / 5 through 12 / 5.
300 TINGEY ST SE   
11/05/18 
FC BOILERMAKER LLC / DREW PEISHEL; JOHN RANOUS
B1813340 / CONSTRUCTION
Minor interior tenant improvment including building one non-load bearing partitiion wall adding millwork fixtures including cash desk, fitting rooms. No Structural work. Some electrical updates. **LEVEL 2 ALTERATION
   
11/08/18 
FC BOILERMAKER LLC / STEPHEN ADAMS 2403042373
E1901337 / SUPPLEMENTAL
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.