Yesterday the US Department of Housing and Urban Development announced the awarding of $500 million in stimulus-money grants to housing authorities around the country, with the DC Housing Authority receiving the $9.5 million it requested to help get the second phase of Capper townhomes at Capitol Quarter moving forward.
In my post on DCHA's application back in June, I explained it this way:

According to this "narrative and schedule" that DCHA included with its application to HUD, the money would finance both public infrastructure and private site improvements needed to begin the construction of the second phase of the Capitol Quarter mixed-income townhouse development (the blocks between Third and Fourth south of I), which will have 163 units, 47 of which are public housing rental units (along with 60 market-rate, 39 workforce-rate, and 17 public housing home ownership units). The narrative indicates that the $55 million Capper PILOT bonds approved by the city council last year that were to fund the new community center and infrastructure improvements not only in the Phase II blocks but also on the north and east sides of Canal Park and over to the DPW site never made it into the bond market; attempts to secure loans from both Fannie Mae and Wachovia also were fruitless.
There's a lot of detail in the narrative that I'm not going to try to summarize (I start to glaze over once I get to Low Income Housing Tax Credits [LIHTC] and anything having to do with "leveraging"):, but it does say that if awarded the HUD CFRC grant money, DCHA would immediately have its engineers complete permit drawings, which can then be put into the city's permitting process (estimated to last 90 days), after which infrastructure work can begin--the schedule at the end of the document estimates a start date of Dec. 1. This work would include repair or replacement underground water, sewer, and "dry utilities" lines, new streets, curbs, and gutters, additional lighting, and public landscaping.
The HUD funds would also be used to pay for the land preparation costs and foundation construction of the 47 public housing units, covering a $1 million gap that occurred in the planned Phase II funding thanks to problems in the LIHTC market.
From what I understand, DCHA is already talking to contractors, with hopes of being able to start delivering the first phase 2 townhomes by late next year; this would be in the blocks between Third and Fourth south of I.
There may also be some money coming for the other Capper-related improvements listed above that were to be paid for by the $55 million PILOT bonds, but not as part of this grant.
Comments (1)
   
 
 More About Capper
 All posts: Capper, Capitol Quarter

JDLand.com Home

Comments

Velocity Guy says: (9/24/09 4:24 PM)
Wow, this is a big win for EYA and the Capitol Quarter people. Congrats ya'll.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

JD on Wednesday Tidbits: I knew this was coming. We'll do something at Anchovy Social when the weather is...
202_cyclist on Wednesday Tidbits: JD-- with all of these new neighbors wanting to meet, I remember it has been a l...
EnvySquared on Wednesday Tidbits: Stopped in at the Thompson bar tonight and was told that Anchovy Social's offici...
JES on Wednesday Tidbits: Ventured up to Shaw tonight for the grand opening of Emmy Squared to check it ou...
Jscott280 on Wednesday Tidbits: @AGH I heard from Laura that the 2nd floor will be settling closer to early Marc...
Sasq on Wednesday Tidbits: @AGH...Hey there neighbor!!! ***fingers crossed** Look forward to meeting you a...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1200 B/O HALF ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 01/14/20
1100 B/O 1ST ST SE   BURGLARY
Burglary One
 01/12/20
100 B/O L ST SE   ROBBERY  01/08/20
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 01/08/20
1100 B/O 2ND PLACE SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 01/06/20
40 N ST SE   ROBBERY  01/05/20
1100 B/O 9TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 01/03/20
139 N ST SE   THEFT FROM AUTO
Theft First Degree (theft From Motor Vehicle)
 01/02/20
100 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 01/02/20
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/31/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/30/19
UNIT B/O M ST SE   BURGLARY
Burglary Two
 12/30/19
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/29/19
UNIT B/O I ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 12/28/19
500 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 12/28/19
700 B/O I ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 12/28/19
UNIT B/O I ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 12/27/19
300 B/O VIRGINIA AVE SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 12/27/19
1220 HALF ST SE   BURGLARY
Burglary Two
 12/27/19
300 B/O WATER ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 12/26/19
900 B/O NEW JERSEY AVE SE   BURGLARY
Burglary Two
 12/25/19
2 I ST SE   THEFT
Theft 2nd Degree (all Other Larceny) - Highway/ Road/ Alley/ Street/ Sidewalk
 12/24/19
2 I ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle) - Highway/ Road/ Alley/ Street/ Sidewalk
 12/23/19
UNIT B/O POTOMAC AVE SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle) - Highway/ Road/ Alley/ Street/ Sidewalk
 12/22/19
400 B/O M ST SE   THEFT
Shoplifting
 12/21/19
1100 B/O NEW JERSEY AVE SE   BURGLARY
Burglary Two
 12/21/19
250 B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 12/18/19

Recent Issued Building Permits Archive  
909 4TH ST SE   
12/30/19 
MEREDITH FASCETT / KYLE YOST
SOL2000550 / CONSTRUCTION
rooftop solar pv system, less than 4' above roof
1300 4TH ST SE 912   
01/07/20 
DEBORAH J ISRAEL / DORIS A MINOR; DORIS A MINOR
B2003615 / CONSTRUCTION
REPLACE KITCHEN CABINETS
900 5TH ST SE   
01/10/20 
DISTRICT OF COLUMBIA HOUSING AUTHORITY / WILLIAM ANDERSON; WILLIAM ANDERSON
P2002846 / SUPPLEMENTAL
415 I ST SE   
01/10/20 
MEGHAN E RILEY / DAEHO PARK; DAEHO PARK
P2002836 / SUPPLEMENTAL
300 M ST SE   
01/03/20 
FEDERAL CENTER LP / null
E2003217 / SUPPLEMENTAL
861 NEW JERSEY AVE SE   
12/31/19 
CONSOLIDATED RAIL CORPQ / null
E2003162 / SUPPLEMENTAL
   
12/31/19 
DISTRICT OF COLUMBIA / JANE MCCRAY
AH2000399 / CONSTRUCTION
Pepco will be splicing cable at 861 New Jersey Avenue, SE, from 9PM to 7AM, Monday thru Friday.
   
01/03/20 
CSX TRANSPORTATION INC / SUSANA VAZQUEZ; JOHN MORIARTY & ASSOCIATES OF VIRGINIA LLC
TC2000014 / CONSTRUCTION
Tower Crane
1100 NEW JERSEY AVE SE 1ST FL   
01/06/20 
SQUARE 742 LLC / JAMES W. LASHER; JAMES W. LASHER
E2003296 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
12/30/19 
SQUARE 742 LLC / RYAN FITZGERALD; NEXIUS SOLUTIONS, INC.
AN2000023 / CONSTRUCTION
AT&T proposes to replace (3) existing antennas with (3) new antennas and install (3) new antennas.
   
01/02/20 
SQUARE 742 LLC C/O WCSMITH / PATRICIA J STAUB; CDH CONSTRUCTION INC
B2001972 / CONSTRUCTION
Provide Landlord Work (warm white shell) for Tenant buildout of 1827 SF.
   
01/07/20 
SQUARE 742 LLC / ;
P2002715 / SUPPLEMENTAL
   
01/08/20 
SQUARE 742 LLC / null
P2002765 / SUPPLEMENTAL
1275 NEW JERSEY AVE SE   
01/03/20 
MILLER AND LONG / WILLIAM MOORE; MILLER LONG
TC2000016 / CONSTRUCTION
towercrane for jobsite use 1 / 25 / 2020 to 1 / 25 / 2021
355 WATER ST SE   
12/30/19 
UNITED STATES OF AMERICA / KELSI EVANS
TN2000035 / CONSTRUCTION
1 40' x 80 tent
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2020 JD.