Since January, 2003
            
 Sliding from Before to After

In a blissfully short 26-minute hearing, the city's Zoning Commission approved tonight the series of amendment requests to allow the Trapeze School New York to set up shop on Parcel O at the Yards, on the southeast corner of Fourth and Tingey.
The commissioners seemed satisfied with the information they had in the Office of Planning report and the submissions from Forest City and the Trapeze School, and asked few questions (Chairman Hood was clearly trying to move things along). This is a temporary approval, allowing the Trapeze School to be at the Yards for five years, or longer if a Special Exception is later granted. The text amendments also waved the on-site parking requirement for the school, with new commissioner Konrad Schlater saying he was "comfortable" with it because parking "is definitely overbuilt" in the area around the ballpark. ANC 6D had voted 7-0 in support of the case as well. It's now expected that the National Capital Planning Commission will address the Trapeze School at its Oct. 1 meeting.
No date for the opening of the school in its new home was mentioned, though it was explained that Forest City was trying to expedite the process since the school is having to vacate its home at the old convention center site. There will still be building permits to be filed for and approved before the tent can be lifted.
Toward the end of the hearing, Ramsey Meiser of Forest City gave a bit of an update on the other projects in the first phase of the Yards. Here's the latest:
* They are continuing to work with the city's Housing Finance Agency to get the money together to (re)start on the Foundry Lofts, with a hoped-for completion date of late 2010 or early 2011.
* The Boilermaker Shop could open in 2011; this dovetails with what a commenter in this thread reported hearing over the weekend, although earlier today Forest City would not officially confirm for me any scheduled start date for the project, only that some retail tenants have been signed, but that Forest City can't name them publicly just yet. (Maybe in October.)
* The first retail in the Park at the Yards (in the old Lumber Shed building) could open in 2012; the park itself is expected to open next summer.
* "Parcel D", on the southeast corner of Fourth and M, is the site of the expected Harris Teeter (though Meiser didn't name them, saying only "a grocery store," since neither Forest City nor Harris Teeter have confirmed this rumor yet), and is now apparently going to be a residential building instead of office, which had been hinted at recently. It's expected delivery date is currently 2013.
* The Factory 202 lofts building at Fifth and M is not expected before 2014.
And all that's just the first phase! Meiser also said that Parcel N, the site of a surface parking lot on the southwest corner of Fourth and Tingey, would probably be the first project of Phase 2. But no date on that yet.
If you want to watch the hearing, visit DCOZ's On Demand Video page.
Comments (0)
   
 
 More About Yards/Parcel O

JDLand.com Home

Comments

No comments posted.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Top News

RMP on DDOT Unveils Planned: I support this change. I like the current Ciculator route in theory, but it take...
NavyYardGuy on Peet's Coffee Coming: @ JD..was that a hint..like Compass coffee is coming to Navy Yard too?
Ampersand on DDOT Unveils Planned: aaaaaaand now that I've posted that I see exactly such a route would also be cre...
JD on DDOT Unveils Planned: (That includes Eastern Market.)
JD on DDOT Unveils Planned: "Circulator service between Union Station, Barracks Row, and the Washington Navy...
Message Board (beta)

Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
900 B/O 5TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/15/17
1200 B/O 4TH ST SE   THEFT
Theft 2nd Degree (theft From Building)
 12/12/17
1200 B/O 4TH ST SE   THEFT
Theft 2nd Degree (theft From Building)
 12/11/17
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/11/17
1100 B/O 1ST ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/08/17
900 B/O NEW JERSEY AVE SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 12/08/17
1100 B/O NEW JERSEY AVE SE   THEFT
Shoplifting
 12/03/17
300 B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 12/02/17
500 B/O L ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 12/02/17
1100 5TH ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 12/01/17
400 B/O M ST SE   THEFT
Shoplifting
 11/29/17
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/28/17
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/27/17
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/26/17
1000 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 11/26/17
1000 B/O 8TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 11/24/17
1200 B/O NEW JERSEY AVE SE   THEFT
Theft First Degree (all Other Larceny)
 11/24/17
400 B/O M ST SE   THEFT
Shoplifting
 11/22/17
100 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 11/19/17
70 B/O I ST SE   BURGLARY
Burglary Two
 11/16/17

Recent Issued Building Permits Archive  
1100 2ND PL SE   
12/13/17 
BAKER DC / CHRISTINE LONG
AH1800290 / CONSTRUCTION
An after hours permit is respectfully requested from 5am thru 9pm daily
1331 2ND ST SE   
11/29/17 
DC WATER / DAVE LEVINE
AH1800282 / CONSTRUCTION
After Hours work for structure excavation and support for B1311474 DC Water. Corman Construction 301-343-5417
2 I ST SE   
11/29/17 
MCDONALDS CORPORATION / MICHAEL ERIC CAMPBELL
M1800603 / SUPPLEMENTAL
   
11/29/17 
MCDONALDS CORPORATION / DANIEL P. THOMPSON
P1801598 / SUPPLEMENTAL
   
12/01/17 
CRESCENT CAPITAL VIEW, LLC N/A / ERICKA CLARK
AH1800280 / CONSTRUCTION
Place and finish concrete. Minimal noise impact, and required for reduction on impact to traffic.
   
12/14/17 
CRESCENT CAPITAL VIEW, LLC N/A / ERICKA CLARK
AH1800324 / CONSTRUCTION
Place and finish concrete. Minimal noise impact, and required for reduction on impact to traffic.
70 I ST SE   
11/28/17 
DISTRICT OF COLUMBIA / OTIS ELEVATOR COMPANY; OTIS ELEVATOR COMPANY
ER1800447 / SHOP DRAWING
BODY OF WORK: Replace machine and recable elevator # 1.
337 L ST SE   
12/06/17 
JENNIFER LANCASTER / null
E1802092 / SUPPLEMENTAL
347 L ST SE   
12/07/17 
THOMAS PAQUIN / null
E1802129 / SUPPLEMENTAL
   
12/14/17 
THOMAS PAQUIN / BJORN FALK
SOL1800006 / CONSTRUCTION
Installation of a 5.4kW solar PV system. Parapet mounted, 15 panels
555 L ST SE   
11/27/17 
UNITED STATES OF AMERICA / CLIFFORD DIXON
B1714199 / CONSTRUCTION
DGS PROJECT This permit is for interior work only.SWING SPACE FOR WARD 6 CLINIC TO EXISTING VACANT JOY EVANS RECREATION CENTER TEMPORARILY FOR 12 TO 18 MONTHS
515 M ST SE   
12/11/17 
null / BLUE STAR DESIGN BUILD
BP1801085 / POST CARD
300 M ST SE STE# 402 20024   
12/13/17 
FEDERAL CENTER LP / null
P1802065 / SUPPLEMENTAL
100 M ST SE   
12/05/17 
CRANE SERVICE CO / CHRISTINE LONG
AH1800304 / CONSTRUCTION
An after hours permit is respectfully requested from 7AM Saturday thru 7PM Sunday
110 M ST SE   
12/13/17 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / THUY LE
TL1700234 / CONSTRUCTION
Interior alteration for new tenant, restaurant with 37 seats, 49 in occupancy load.
410 M ST SE   
11/20/17 
DC HOUSING / COLLINS ELEVATOR SERVICES INC.; COLLINS ELEVATOR SERVICES INC.
ER1800511 / SHOP DRAWING
BODY OF WORK: 1. Remove old piston. Replace & install jack on car # 1.
861 NEW JERSEY AVE SE   
12/14/17 
CSX TRANSPORTATION INC. / NA CSX TRANSPORTATION, INC.
AH1800330 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities.
1100 NEW JERSEY AVE SE 3RD FL   
11/22/17 
SQUARE 742 LLC / null
P1801490 / SUPPLEMENTAL
1100 NEW JERSEY AVE SE   
11/20/17 
SQUARE 742 LLC / null
P1801410 / SUPPLEMENTAL
   
12/06/17 
SQUARE 742 LLC / DOMINIC E TOTARO
M1800664 / SUPPLEMENTAL
   
12/08/17 
SQUARE 742 LLC / SAM HOLLEN
B1801219 / CONSTRUCTION
INTERIOR RENOVATION TO 2ND FLOOR OFFICE SPACE. PARTITIONS, FURNITURE, MEP, LIFE SAFETY AND STRUCTURAL HANGING MOVABLE PARTITION. 25,226 SQUARE FEET. ALION SCIENCE AND TECHNOLOGY **LEVEL 2 ALTERATION
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2017 JD.