How can I possibly summarize in this small space the never-ending parade of testimony and questions at last night's hearing on the various Capper zoning modification requests? (I just thank the heavens I watched the web cast and didn't attend in person.) If you didn't avail yourself of this entertainment, you'll just have to wait for the transcript to come out to get all the specifics, but here's a few bullet points on issues that were brought up (read the Office of Planning report on what was actually being requested):
* Commissioner May was displeased that there were no "sample boards" of the exterior finishes for the two new apartment buildings, as is apparently required for a stage 2 planned-unit-development approval.
* The commissioners were clearly befuddled by the scope of the requests, variances, and exceptions before them, even though last year they had requested that the three separate filings be grouped together in a single hearing.
* There was much discussion of the request to further delay the construction of the community center until at least 2011, with the Housing Authority testifying at length as to the financial realities of the bond and lending markets (see more about that here), and members of the public and ANC commissioners (Siegel and McBee of 6D) emphasizing as they have in the past "the community's" need for the center and questioning DCHA's idea that the neighborhood needs to reach a "critical mass" before the center should be built (does 300 completed units out of a planned 1700 meet that threshold?). DCHA said repeatedly that building a community center is a promise they have made that will not be broken, but that right now it's just not a possibility.
* Two former Capper residents testified to their belief that the Housing Authority is not adhering to what's required in terms of job training and other social services that are supposed to be provided while residents are waiting to move back, which got chair Anthony Hood into a bit of a dander. (Read pages 12-14 of the 2004 Capper zoning order to see what is expected in this realm.) This and the other public comments (such as the "why can't you use Obama's stimulus money?" question that had come up at ANC 6D) brought a somewhat forceful response from David Cortiella of the Housing Authority as to what they're doing for the former residents, and he again went through the current barriers to financing the center. There was then a minor dustup between commissioners Jeffries and May, with May pressing the housing authority on its performance and timeline and Jeffries expressing some level of surprise that the zoning commission was questioning a Hope VI redevelopment's financial problems "in this economic climate."
By the time the hearing wrapped up at 11:15 pm (and I'd be lying if I said I had paid attention to every word), the commission was requesting a series of additional filings from the housing authority and its team, and put it all on their April 27 agenda. (And look for this to be back on the ANC 6D agenda on April 13, too.)
Comments (0)
   
 
 More About Capper
 All posts: ANC News, Capper, meetings, zoning

JDLand.com Home

Comments

No comments posted.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 

JDLand.com's Official Unofficial Guide, Updated for 2018!
 Top News
  

conngs0 on Wednesday Om Nom: Yep. I also couldn't tell the difference when it reopened the first time. I'm ...
jdc on Wednesday Om Nom: Is it me, or is something just weird about that Five Guys repeatedly closing? I'...
greb22 on Wednesday Tidbits: I went to Declaration for happy hour on a non game day and they charged me regul...
Lambau88 on Wednesday Tidbits: Tried out Declaration on a non-game night. Quality food and friendly/attentive s...
Message Board (beta)

Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
1100 B/O NEW JERSEY AVE SE   SEX ABUSE
First Degree Sexual Abuse
 04/17/18
400 B/O M ST SE   THEFT
Shoplifting
 04/17/18
100 B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 04/17/18
UNIT B/O N ST SE   ROBBERY  04/14/18
100 B/O I ST SE   THEFT
Theft 2nd Degree (theft From Building)
 04/12/18
UNIT B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 04/12/18
1200 B/O 4TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 04/09/18
150 B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 04/07/18
1000 B/O 3RD ST SE   BURGLARY
Burglary One
 04/07/18
1200 B/O NEW JERSEY AVE SE   ROBBERY
Assault W/i To Commit Robbery (simple Assault)
 04/05/18
UNIT B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 04/01/18
1100 B/O NEW JERSEY AVE SE   THEFT
Theft 2nd Degree (all Other Larceny)
 03/31/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 03/28/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (theft From Building)
 03/28/18
300 B/O I ST SE   ASSAULT WITH A DANGEROUS WEAPON  03/25/18
UNIT B/O L ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 03/23/18
100 B/O K ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 03/23/18
UNIT B/O I ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 03/23/18
800 B/O L ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 03/19/18

Recent Issued Building Permits Archive  
1331 2 ST SE   
04/02/18 
DISTRICT OF COLUMBIA / MARK HARLOW CLIFFORD
SB1800225 / CONSTRUCTION
Application for Well Abandonment Workplan Approval for the abandonment of 8 monitoring wells and 21 inclinometers at the Main Pumping Station site for the DC Water Clean Rivers Project, Division I, installed under Permit Number SB1400419.
1331 2ND ST SE 20003   
04/05/18 
DC WATER / DAVE LEVINE
AH1800744 / CONSTRUCTION
After Hours work for structure excavation in support of DC Water, Corrman Construction 301-343-5417.
1346 4TH ST SE   
04/10/18 
ALAN OWINGS / ROBERT HENRY
AH1800796 / CONSTRUCTION
After Hours Permit for 04 / 16 / 18 from 9AM to 7PM to perform facade, interior unit framing and drywall work, and interior Mechanical, Electrical, Plumbing and Sprinkler Rough-In.
1346 4TH ST ST SE 20003   
03/28/18 
FOREST CITY / TYLER D BARRON
AH1800712 / CONSTRUCTION
After hours for 4 / 13 / 18 to 5 / 12 / 18. Work that is to be done is quiet work of window deliveries at 5:30AM to 7:00AM by use of tower crane
82 I ST SE   
04/02/18 
GDVC EYE STREET LLC / null
FB1800055 / SUPPLEMENTAL
150 I ST SE   
03/28/18 
null
E1805313 / SUPPLEMENTAL
   
03/29/18 
null / JOHN THOMSON 3018645080
E1805337 / SUPPLEMENTAL
300 M ST SE 400   
04/09/18 
FEDERAL CENTER LP / null
M1801970 / SUPPLEMENTAL
300 M ST SE STE# 400 20024   
04/05/18 
CHARLES SMITH / EUGENE AHNS 3012811497
E1805597 / SUPPLEMENTAL
300 M ST SE STE# 400   
04/12/18 
FEDERAL CENTER LP / null
P1805161 / SUPPLEMENTAL
140 M ST SE   
03/26/18 
SQUARE 742 LLC / null
P1804630 / SUPPLEMENTAL
300 M ST SE   
03/26/18 
FEDERAL CENTER LP / JERRY BETHEA
M1801846 / SUPPLEMENTAL
401 M ST SE   
04/03/18 
TETRA TECH C/O DOEE / JESSICA REICHARD
AH1800767 / CONSTRUCTION
After hours permit for manhole access to complete inspections for DOEE Anacosta River Sediment clean up project, work hours between 7pm and 7am Monday thru Friday. Rolling work zones for all manhole access under permit # PA10374319-R1
800 NEW JERSEY AVE SE   
04/05/18 
SQUARE 737 LLC / null
P1804974 / SUPPLEMENTAL
   
04/09/18 
SQUARE 737 LLC / null
E1805700 / SUPPLEMENTAL
861 NEW JERSEY AVE SE   
04/02/18 
CONSOLIDATED RAIL CORPORATION / NA CSX TRANSPORTATION, INC.
AH1800715 / CONSTRUCTION
Work in public ROW within the Virginia Avenue Tunnel Reconstruction Project LOD for utility, demolition, and concrete structure construction activities.
   
04/11/18 
CONSOLIDATED RAIL CORPORATION / DEVIN MURDOCK
SB1800265 / CONSTRUCTION
Drill 8 borings to 40ft. Convert 4 borings into 1" temporary wells, collect groundwater from each well and abandon borings.
1100 NEW JERSEY AVE SE   
04/13/18 
SQUARE 742 LLC / CLIFFORD DIXON
B1804348 / CONSTRUCTION
INTERIOR RENOVATIONS TO OFFICE SPACE ON THE 5TH FLOOR. **DEMOLITION, LEVEL 2 ALTERATION
1115 NEW JERSEY AVE SE   
04/06/18 
GALLERY CAPITOL RIVERFRONT PROPERTY LLC / ACCUPERMIT LLC AS AGENT
B1803009 / CONSTRUCTION
Interior alterations for new tenant in existing commercial space to include partitions, mill work, electrical and plumbing fixtures, flooring and wall coverings, dining area furniture and kitchen equipment for a A-2 restaurant with 49 proposed occupancy.
125 O ST SE   
03/29/18 
DISTRICT OF COLUMBIA / JAMES M. HALLER
P1804624 / SUPPLEMENTAL
   
04/09/18 
DISTRICT OF COLUMBIA / TAMIKA STATON; OTIS
EN1801762 / SHOP DRAWING
I New G2S Elevator - 3500LBS @ 200FPM (7 Floors)
   
04/09/18 
DISTRICT OF COLUMBIA / TAMIKA STATON; OTIS
EN1801763 / SHOP DRAWING
Install 1 New G2S Elevator - 3500LBS @ 200FPM (6 Floors)
   
04/09/18 
DISTRICT OF COLUMBIA / TAMIKA STATON; OTIS
EN1801761 / SHOP DRAWING
Install 1 New G2S Elevators 4000LBS @ 200FPM (7 Floors)
71 POTOMAC AVE SE   
03/26/18 
FORIDA ROCK PROPERTIES INC / null
BCIV1800074 / CONSTRUCTION
This permit is for rough grading and erosion and sediment control civil work associated with the temporary parking lot, relocation of the dog park and construction staging area on the undeveloped portion of the lot.
227 TINGEY ST SE   
03/28/18 
UNITED STATES OF AMERICA / ERICKA CLARK
AH1800760 / CONSTRUCTION
significant concrete pours and tower crane erection 5AM - 7AM and 7PM - 10:00PM
   
04/12/18 
UNITED STATES OF AMERICA / STEPHEN J. EXELBERT
P1805022 / SUPPLEMENTAL
300 TINGEY ST SE   
04/12/18 
MERCURY LLC / WILL TEASS
B1803433 / CONSTRUCTION
INTERIOR FIT-OUT / EXTENSION OF EXISTING TENANT SUITE (APPROVED UNDER B1605215) INCLUDING NEW MECHANICAL AND ELECTRICAL WORK. **LEVEL 2 ALTERATION
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.