The last item to summarize from Monday's ANC 6D presentation hearing was an update on the series of changes being requested to the Capper/Carrollsburg PUD. I've been writing about some portion of these requests since July, so here's some bullet points I've previously written (I just can't bring myself to have to compose new entries about this stuff AGAIN), along with comments from the ANC commissioners:
* Expanding the number of units at Capper: "There are five new apartment buildings slated to be built, three of which along the east side of Canal Park where the temporary parking lots are, and another at New Jersey and K on the trash transfer site. And there is a new plan for a fifth apartment building, on L Street across from the Marine Bachelor Enlisted Quarters (B.E.Q), on the northern portion of the old Capper Seniors footprint.
"Under the original Capper plans, there was to be a strip of 61 townhouses built on this spot, but the DC Housing Authority has recognized that these homes would be dwarfed by the B.E.Q. to the north and the two planned office buildings directly behind them at 600 M Street. So DCHA has now filed a request with the Zoning Commission to allow an expansion in the total number of housing units allowed at Capper to 1,747, which would allow the construction of a four-story 189-unit apartment building (with a massing very similar to the B.E.Q.) on this stretch of L Street known as Square 882N. This Zoning Commission request is also looking to expand the number of units in the planned apartment building on the south side of L Street between Second and Third (let's call it Square 769N) to 171 units[.]"
The ANC was told that the Square 769N building was originally designed to be a market-rate condo building only, but that financing realities have forced a switch to rentals. And because rental units can be smaller, they were able to not only add more than 60 units, but make 34 of those units public housing, allowing a lower proportion of public housing units in the other four apartment buildings while still maintaining the required Hope VI one-to-one replacement of the original 695 Capper public housing units.
As for the Square 882 buildings, the change to apartments from townhouses would require a boost in parking spaces from 49 to 172--but they are proposing to lower the total spaces at the office building from 400 to 284. This is part of a request to bring down the overall number of required parking spaces from 1,845 to 1,780, including the removal of the requirement for 70 off-site spaces for 400 M Street, which have been determined to be unnecessary.
(Note that the Square 769 and Square 882 issues before the Zoning Commission are technically a PUD second-stage review.)
* Time Extensions: "There were also requests for three time extensions: to extend the first-stage PUD for an additional five years, to extend the deadline for filing second-stage approvals for the apartment building sites along Canal Park (including the trash-transfer station site) to 2013, and to extend the deadline for filing a building permit application for the planned community center at Fifth and K to January 2011, with an included extension of the start of construction to January 2012."
Commissioner Bob Siegel in particular is very unhappy about the delay in the community center construction, saying that the senior residents of 900 5th Street need an exercise room and other amenities. But he was told that, simply, the community center is unfinanceable right now.
And Commissioner Ron McBee wants to revisit the community benefits that were agreed to in the original Capper PUD, asking the presenters to get him a list of those benefits--I can do it for them, by pointing to pages 12-14 of the 2004 zoning order.
The Zoning Commission will be hearing all these items on March 19. You can see the hearing notice for the zoning-related specifics on the three cases
Comments (5)
   
 
 More About Capper

JDLand.com Home

Comments

SG says: (2/4/09 6:19 PM)
Geez, 695 public housing units is still a ton and may be an unsustainable level unless the market rate units are extremely affordable and nice.


JD says: (2/4/09 6:22 PM)
300 of them are in the two already completed buildings at 900 5th Street and 400 M. There will be 96 scattered throughout the Capitol Quarter townhouses. That leaves 200 in the five apartment buildings still to come.


Sophia says: (2/5/09 5:32 PM)
Can someone who is knowledgeable about financing public projects explain why the Community Center is not financeable now? Wouldn't the financing be in place if they had gotten so far as to employ and architect?

As one of the people that is going to be living across from the dump yard for apparently 2.5 years, I'm very interested in this project!


JD says: (2/6/09 12:53 PM)
Sophia--They got $35 million from the original Hope VI grant, which was enough to do some things but which is to be leveraged into the hundreds of millions of dollars needed to complete the entire project. They have to sell bonds, or enter financing deals with banks, or whatever to get that remaining money, and it just isn't very easy right now.

It's like with Capitol Quarter--there was an original $5 million for the infrastructure work, but it wasn't until they completed that huge bond sale last year that they were able to start actual construction.




Sophia says: (2/9/09 7:19 AM)
Thanks for the explanation. It's just too bad that the old building (as unattractive as it may have been) was torn down to make way for the new one... leaving us without anything for several years.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Top News

sameter on Capitol Riverfront BID: congrats on being a constant in the community and being a positive change. well...
CJBabyDaddy on Capitol Riverfront BID: A meet-up after tomorrow’s 15th anniversary gala sounds like a great idea. (Can...
202_cyclist on Capitol Riverfront BID: Yes-- a JD Land birthday party/happy hour would is a great idea.
NavyYardGuy on Capitol Riverfront BID: That's a lot of good information--congrats on the award and the upcoming anniver...
Message Board (beta)

  
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
300 B/O K ST SE   BURGLARY
Burglary Two
 01/13/18
1000 B/O 4TH ST SE   THEFT FROM AUTO
Theft (theft From Motor Vehicle)
 01/11/18
500 B/O M ST SE   THEFT FROM AUTO
Theft 2nd Degree (theft From Motor Vehicle)
 01/09/18
900 B/O 4TH ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 01/07/18
100 B/O I ST SE   MOTOR VEHICLE THEFT
Theft First Degree (Stolen Auto)
 01/04/18
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 01/04/18
400 B/O M ST SE   THEFT
Shoplifting
 01/02/18
UNIT B/O K ST SE   THEFT
Theft 2nd Degree (theft From Building)
 12/31/17
400 B/O M ST SE   THEFT
Theft 2nd Degree (all Other Larceny)
 12/19/17

Recent Issued Building Permits Archive  
1331 2ND ST SE   
12/22/17 
DC WATER / DAVE LEVINE
AH1800369 / CONSTRUCTION
After Hours work for structure excavation and support for B1311474 DC Water, Corman Construction 301-343-5417. TO EXCLUDE LEGAL HOLIDAYS.
1331 4TH ST SE CU   
12/27/17 
FC 1331 LLC / GARY BRENT; N/A
SG1800119 / CONSTRUCTION
Install 1 illuminated blade sign and 7 non-illuminated window vinyl signs - CHLOE BY HAIDAR KAROUM
   
12/28/17 
FC 1331 LLC / BEN BEDDO
TL1700205 / CONSTRUCTION
New Tenant Layout for restaurant
1300 4TH ST SE   
01/05/18 
FORREST CITY WASHINGTON / GEORGE ARTHUR KING
SB1800091 / CONSTRUCTION
To abandon 18 6 inch diameter 80 foot deep dewatering wells and 4 2 inch diameter 50 feet deep observation wells per the DOEE regulations
1346 4TH ST SE   
01/12/18 
ALAN OWINGS / ROBERT HENRY
AH1800415 / CONSTRUCTION
After Hours Permit for 1 / 15 / 18 from 7AM to 7PM to perform concrete operations, framing, operations, and utility operations.
411 I ST SE   
12/27/17 
ABIGAIL A SMITH / ROBERT D. JOHNSTON
E1802679 / SUPPLEMENTAL
337 L ST SE   
12/22/17 
JENNIFER LANCASTER / null
E1802602 / SUPPLEMENTAL
   
01/11/18 
JENNIFER LANCASTER / BJORN FALK
SOL1800005 / CONSTRUCTION
Installation of a 3.6kW solar PV system. Roof Mounted, 10 panels
300 M ST SE STE# 400   
01/03/18 
FEDERAL CENTER LP / SAM HOLLEN
B1803531 / CONSTRUCTION
INTERIOR RENOVATION TO 4TH FLOOR OFFICE CONFERENCE ROOM. PARTITIONS, CEILING, MECHANICAL, ELECTRICAL AND LIFE SAFETY. NO PLUMBING OR STRUCTURAL. 680 SQUARE FEET. CACI SUITE 400
25 POTOMAC AVE SE DOCK 79   
01/11/18 
RIVERFRONT HOLDINGS I LLC / null
P1802701 / SUPPLEMENTAL
227 TINGEY ST SE   
12/29/17 
JW CAPITAL PARTNERS / MELISSA DIAZ
FD1700126 / CONSTRUCTION
Parcel L1- Foundation to Grade permit for the new construction on an 11 story full service hotel building with restaurant and retail.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2018 JD.