ANC 6D heard a presentation on Monday night from the team working on the South Capitol Street Environmental Impact Statement, which is now in its "final preferred alternative" stage. Their PowerPoint presentation was pretty close to the one I posted last month, and one of the consultants did tweak me a bit about how I "spoiled the surprise" on the choice of the arched bascule design for the new Douglass Bridge.
Here again are the (long!) bullet points about what the preferred alternative designs are for the portion of South Capitol west of the Anacostia (see the presentation if you're interested in the preferred alternatives chosen for east of the river), along with some issues raised by the ANC:
* It was emphasized that these new designs will not be adding any capacity, but that the main goal is to bring back the "boulevard" feeling of the corridor.
* The new bridge will have 20-foot-wide sidewalks on each side, and only two piers will need to be built in the river, compared to 3-5 piers that would have been needed with the other designs. (The cable stayed swing bridge would have had just one pedestrian/bike path, 16 feet wide, in the middle of the bridge, surrounded by six lanes of traffic.)
* There will be a seven-acre traffic oval at the foot of the new bridge (which will be located to the south of the current bridge), reshaping the intersection of South Capitol Street and Potomac Avenue. (The ballpark's Home Plate Gate and entrance promenade will be the northeast edge of the oval.) The city is already in the process of acquiring seven properties or portions of properties that will be needed for the oval and bridge footprint, including the red brick warehouse on the northwest corner of South Capitol and Potomac. This oval is on the NCPC list of locations for future memorials and museums.
* The intersection of South Capitol Street and M Street will become an at-grade intersection (no more underpass for through traffic). ANC chair Andy Litsky expressed great concern about how this could make the intersection even more dangerous than it already is, to which the DDOT team replied that the reconfiguration should make it safer. (Certainly it would seem that having a "normal" intersection with two left-turn lanes in most directions would be an improvement safety-wise over the existing mish-mash of lights and poorly striped turn-lanes, but then there will also be a lot more cars cycling through once the tunnel lanes are gone.)
* There will be modifications to South Capitol's interchange with the SE/SW Freeway, with the replacement of the ramp that begins at I Street with an at-grade intersection underneath the freeway that would have two left-turn lanes to a new ramp. With the existing ramp removed, the intersection at South Capitol and I would also be reconfigured.
* The northern section of South Capitol Street will match the reconfigured portion between N Street and Potomac Avenue, as a six-lane boulevard with a median and wide sidewalks.
Commissioners McBee and Moffatt asked as they have in the past about whether the existing bridge could be kept as a pedestrian/bike-only bridge, but DDOT explained that since the swing span would continue to need to be opened for river traffic, the cost of maintaining the old bridge just isn't feasible. (The RiverFront folks might also be a teensy bit upset that their land that's beneath the current bridge wouldn't be coming back to them.) And the team also indicated that this new bridge does not preclude the construction (Some Day, Perhaps, in Some Far Off Time) of a tunnel to move non-local traffic from Anacostia to I-395.
They expect the final Record of Decision from the feds this fall; however, when pressed for a start date, they said 2011 would be the absolute earliest for the start of construction (with completion possibly in 2015), but that as of now there's no funding for the $700 million project. It's also possible that portions of the designs could be undetaken if partial funding is received.
Comments (1)
   
 
 More About South Capitol St.

JDLand.com Home

Comments

Jim says: (2/3/09 12:27 PM)
The M St/S Capitol intersection is currently very dangerous for pedestrians. If you are driving north to turn onto M, there are walls on both sides (especially the left), making it hard to see pedestrians on the sidewalk.

Add a Comment:

Comments are closed for this post.

JDLand Comments RSS Feed


 More News


See All Current News Items | Full Blog Archive

 
 Recent Posts

DCbaseball on Meet the New: Any word on what's coming to old Justin's/Roy Boys? folks have been in there las...
bdj on Meet the New: Anyone heard any rumors about what's going into Crossing DC? With the news about...
Jscott280 on Meet the New: Also heard that they are close to naming a replacement for punchbowl social, as ...
Jscott280 on Meet the New: @jd: I do not have a link yet. I spoke to the construction crew that is building...
JD on Meet the New: @JScott280: I am intrigued by your Silver Diner tidbit. Do you have a link?
Blorty on Meet the New: @JD - I think it's been lapped by the new Douglass bridge (original announcement...
Get JDLand Updates In Your Inbox!



City Government Data for Near Southeast Records added or updated recently displayed here; click the "archive" links to see additional detail and older records. All data from DC Government databases and RSS feeds. JDLand takes no responsibility for errors, omissions, etc. (read CapStat disclaimer). Data is retrieved daily.

Recent Crime Incidents Archive  
No records added or modified in the past two weeks.

Recent Issued Building Permits Archive  
1300 4TH ST SE 1001   
02/22/21 
AP BOWER RETAIL LLC / null
E2104231 / SUPPLEMENTAL
1346 4TH ST SE APT 1M   
02/06/21 
null / NA NA NA
EHOP21945129 / HOME OCCUPATION
1331 4TH ST SE R-2   
02/08/21 
FC 1331 LLC / FC 1331 LLC
BP2101814 / POST CARD
10 I ST SE   
02/16/21 
CAPITOL HILL RACQUET CLUB / NA; VICTORIA STEINHOFF
SB2100112 / CONSTRUCTION
Installation of up to six (6) 3-inch diameter direct-push Geoprobe borings to depths of up to 30 feet below grade as part of an environmental assessment.
555 L ST SE   
01/29/21 
UNITED STATES OF AMERICA / RENNE WELL; RICK HARLAN SCHNEIDER
B2102004 / CONSTRUCTION
DGS PROJECT REHABILITATION+RESTORATION OF THE HISTORIC LINCOIN FIELDHOUSE
861 NEW JERSEY AVE SE 20003   
02/23/21 
809-853 NEW JERSEY AVE ACQUISITION LLC / SUSANA VAZQUEZ
AH2100728 / CONSTRUCTION
Dismantling of tower crane.
809 NEW JERSEY AVE SE   
02/11/21 
GREYSTAR GP LLC 809-853 NEW JERSEY AVENUE ACQUISITION LLC / null
E2103926 / SUPPLEMENTAL
853 NEW JERSEY AVE SE   
02/11/21 
GREYSTAR GP LLC / null
E2103924 / SUPPLEMENTAL
861 NEW JERSEY AVE SE   
02/05/21 
GS CSX HOTEL OWNER LLC / null
E2103762 / SUPPLEMENTAL
1275 NEW JERSEY AVE SE   
02/02/21 
FC 1275 NJ LLC / null
E2103662 / SUPPLEMENTAL
   
02/11/21 
FC 1275 NJ LLC / null
P2103445 / SUPPLEMENTAL
848 SOUTH CAPITOL ST SE   
02/16/21 
CXS TRANSPORTATION INC / VICTORIA STEINHOFF; TBD
SB2100111 / CONSTRUCTION
Installation of up to six (6) 3-inch diameter direct-push Geoprobe borings to depths of up to 30 feet below grade as part of an environmental assessment.
AH = After Hours; B = Alteration & Repair; D = Demolition; E = Electrical; FB = Boiler; M = Mechanical; P = Plumbing and Gas; PC = Post Card; R = Raze; SG = Sign; TL = Tenant Layout; TN = Tent; RW = Retaining Wall;

Real Property Sales Archive  
No commercial transaction records added or modified in the past two weeks.


Project Directory
Completed
Thompson Hotel ('20)
West Half ('19)
Novel South Capitol ('19)
Yards/Guild Apts. ('19)
Capper/The Harlow ('19)
New DC Water HQ ('19)
Yards/Bower Condos ('19)
Virginia Ave. Tunnel ('19)
99 M ('18)
Agora ('18)
1221 Van ('18)
District Winery ('17)
Insignia on M ('17)
F1rst/Residence Inn ('17)
One Hill South ('17)
Homewood Suites ('16)
ORE 82 ('16)
The Bixby ('16)
Dock 79 ('16)
Community Center ('16)
The Brig ('16)
Park Chelsea ('16)
Yards/Arris ('16)
Hampton Inn ('15)
Southeast Blvd. ('15)
11th St. Bridges ('15)
Parc Riverside ('14)
Twelve12/Yards ('14)
Lumber Shed ('13)
Boilermaker Shops ('13)
Camden South Cap. ('13)
Canal Park ('12)
Capitol Quarter ('12)
225 Virginia/200 I ('12)
Foundry Lofts ('12)
1015 Half Street ('10)
Yards Park ('10)
Velocity Condos ('09)
Teague Park ('09)
909 New Jersey Ave. ('09)
55 M ('09)
100 M ('08)
Onyx ('08)
70/100 I ('08)
Nationals Park ('08)
Seniors Bldg Demo ('07)
400 M ('07)
Douglass Bridge Fix ('07)
US DOT HQ ('07)
20 M ('07)
Capper Seniors 1 ('06)
Capitol Hill Tower ('06)
Courtyard/Marriott ('06)
Marine Barracks ('04)


Overviews
Capper/Carrollsburg
Anacostia Riverwalk
New Jersey Avenue
M Street
South Capitol Street
The Yards
Lower 8th Street
East M Street
Boathouse Row





                  © Copyright 2021 JD.